Chapter 469 — Energy; Conservation Programs; Energy Facilities

 

2023 EDITION

 

 

ENERGY; CONSERVATION PROGRAMS; ENERGY FACILITIES

 

HOUSING; LOTTERY AND GAMES; ENVIRONMENT

 

GENERAL PROVISIONS

 

469.010     Policy

 

469.020     Definitions

 

STATE DEPARTMENT OF ENERGY; ADMINISTRATION

 

469.030     State Department of Energy; duties

 

Note          Legislative findings about offshore wind energy--2021 c.376 §1

 

469.040     Director; duties; appointment; rules

 

469.050     Limitations on subsequent employment of director; sanctions

 

469.055     Authority of department to require fingerprints

 

469.059     Biennial comprehensive report; contents; compilation; public comment

 

469.062     Comprehensive state energy strategy; periodic update

 

469.064     Energy security plan; requirements; fuel storage capacity; report

 

469.080     Energy resource information; subpoena power; depositions; limitations on obtaining information; protection from abuse

 

469.085     Procedure for imposing civil penalties; rules

 

469.090     Confidentiality of information submitted under ORS 469.080

 

469.097     Duty to monitor industry progress in energy conservation

 

469.100     Agency consideration of legislative policy; agency review of rules

 

469.110     Dealings with federal government; intervention by State Department of Energy in agency action

 

469.120     State Department of Energy Account; appropriation; record of moneys

 

469.135     Energy Conservation Clearinghouse for Commerce and Industry

 

469.137     Biogas and renewable natural gas inventory; contents; use; advisory committee

 

469.150     Energy suppliers to provide conservation services and information; rules

 

469.155     Advisory energy conservation standards for dwellings; rules

 

469.161     Single resource for providing information and assistance related to energy efficiency incentives and programs

 

469.166     Program to assist environmental justice communities

 

469.181     Definitions for ORS 469.181 and 469.183

 

469.183     Accelerating adoption of green electrolytic and renewable hydrogen fuels

 

ENERGY EFFICIENCY STANDARDS

 

469.229     Definitions for ORS 469.229 to 469.261

 

469.233     Energy efficiency standards

 

469.238     Sale of products not meeting standards prohibited; exemptions

 

469.239     Installation of products not meeting standards prohibited; exemptions

 

469.255     Manufacturers to test products; test methods; certification of products; rules

 

469.261     Department to review standards; rules; postponement of operative dates of standards; application for waiver of federal preemption

 

ENERGY PERFORMANCE STANDARDS FOR COVERED COMMERCIAL BUILDINGS

 

469.275     Definitions for ORS 469.275 to 469.291

 

469.277     Department adoption of performance standards; enforcement; rules

 

469.279     Tier 1 buildings report; exemptions; department support program; correction notice; civil penalties

 

469.281     Implementation; enforcement; advisory committee; rules

 

469.283     County assessors to provide information to department

 

Note          Annual report on implementation of energy performance standards--2023 c.442 §13

 

469.285     When action to comply not required; incentives for voluntary or early compliance

 

469.287     Tier 2 buildings; requirement and standards for providing data; advisory committee; rules

 

469.289     Contracting to administer incentive payments for early compliance

 

469.291     Incentive program for early and voluntary implementation of standards; application process; rules

 

REGULATION OF ENERGY FACILITIES

 

(General Provisions)

 

469.300     Definitions

 

469.310     Policy

 

(Siting)

 

469.320     Site certificate required; exceptions

 

469.330     Notice of intent to file application for site certificate; public notice; standards, application requirements and study requirements; project order; rules

 

469.350     Application for site certificate; comment and recommendation

 

469.360     Evaluation of notice of intent, site application or expedited review request; costs; payment

 

469.370     Draft proposed order for hearing; issues raised; final order; expedited processing

 

469.373     Expedited processing for certain natural gas energy facilities

 

469.375     Required findings for radioactive waste disposal facility certificate

 

469.378     Land use compatibility statement for energy facility

 

469.401     Energy facility site certificate; conditions; effect of issuance on state and local government agencies

 

469.402     Delegation of review of future action required by site certificate

 

469.403     Rehearing on approval or rejection of application for site certificate or amendment; appeal; judicial review vested in Supreme Court; stay of order

 

469.405     Amendment of site certificate; judicial review; exemption; rules

 

469.407     Amendment of application to increase capacity of facility

 

469.409     Amendment of site certificate to demonstrate compliance with carbon dioxide emissions standard; binding arbitration to resolve disputes

 

469.410     Energy facility site certificate applications filed or under construction prior to July 2, 1975; conditions of site certificate; monitoring programs

 

469.413     Power generation from fossil fuels; requirements for new and amended site certificates

 

469.421     Fees; exemptions; assessment of certain utilities and suppliers; penalty

 

469.424     Energy resource suppliers; notice regarding comments in proceedings; rules

 

469.426     Advisory group; energy resource suppliers

 

469.430     Site inspections; compliance reviews

 

469.440     Grounds for revocation or suspension of certificates

 

469.441     Justification of fees charged; judicial review

 

(High Voltage Transmission Lines)

 

469.442     Procedure prior to construction of transmission line in excess of 230,000 volts; review committee

 

(Administration)

 

469.450     Energy Facility Siting Council; appointment; confirmation; term; restrictions

 

469.460     Officers; meetings; compensation and expenses

 

469.470     Powers and duties; rules

 

469.480     Local government advisory group; special advisory groups; compensation and expenses; Electric and Magnetic Field Committee; rules

 

(Rules; Standards; Compliance)

 

469.490     Adoption of rules; determination of validity

 

469.501     Energy facility siting, construction, operation and retirement standards; exemptions; rules

 

469.503     Requirements for approval of energy facility site certificate; carbon dioxide emissions standard; offset funds; use of offset funds by qualifying organization; rules

 

469.504     Facility compliance with statewide planning goals; exception; amendment of local plan and land use regulations; conflicts; technical assistance; rules

 

469.505     Consultation with other agencies

 

469.507     Monitoring environmental and ecological effects of construction and operation of energy facilities

 

469.520     Cooperation of state governmental bodies; adoption of rules by state agencies on energy facility development

 

(Plant Operations; Radioactive Wastes)

 

469.525     Prohibitions on radioactive waste disposal, arrangements for disposal, transportation for disposal and disposal facilities; exceptions; rules

 

469.530     Review and approval of security programs

 

469.533     State Department of Energy rules for health protection and evacuation procedures in nuclear emergency

 

469.534     County procedures

 

469.535     Governor may assume control of emergency operations during nuclear accident or catastrophe

 

469.536     Public utility to disseminate information under ORS 469.533

 

469.540     Reductions or curtailment of operations for violation of safety standards; notice; time period for repairs; transport and disposal of radioactive materials

 

469.550     Order for halt of plant operations or activities with radioactive material; notice

 

469.553     Active uranium mill or mill tailings disposal facility site certification required; procedure for review; fees

 

469.556     Rules governing uranium-related activities

 

469.559     Cooperative agreements authorized between council and federal officials and agencies; rules; powers of Governor; exception for inactive or abandoned site

 

(Records)

 

469.560     Records; public inspection; confidential information

 

(Insurance)

 

469.561     Property insurance required; exceptions; filing of policy

 

469.562     Eligible insurers

 

(Enforcement)

 

469.563     Court orders for enforcement

 

469.564     Records or information for enforcement; correction of violation; determination of compliance; costs

 

(Oregon Hanford Cleanup Board)

 

469.566     Legislative findings

 

469.568     Construction of ORS 469.566 to 469.583

 

469.569     Definitions for ORS 469.566 to 469.583

 

469.571     Oregon Hanford Cleanup Board; members; appointment

 

469.572     Compensation of board members

 

469.573     Purpose of Oregon Hanford Cleanup Board

 

469.574     Duties of Oregon Hanford Cleanup Board; coordination with Washington

 

469.575     Duties of chairperson of Oregon Hanford Cleanup Board

 

469.576     Review of Hanford as site selected for long-term disposal of high-level radioactive waste

 

469.577     Lead agency; agreements with federal agencies related to long-term disposal of high-level radioactive waste

 

469.578     Oregon Hanford Cleanup Board to implement agreements with federal agencies

 

469.579     Authority to accept moneys; disbursement of funds; rules

 

469.581     Advisory and technical committees

 

469.582     Cooperation with Oregon Hanford Cleanup Board; technical assistance from other state agencies

 

469.583     Rules

 

(Federal Site Selection)

 

469.584     Findings

 

469.585     Activities of state related to selection of high-level radioactive waste disposal site

 

(Hanford Nuclear Reservation)

 

469.586     Findings

 

469.587     Position of State of Oregon related to operation of Hanford Nuclear Reservation

 

(Siting of Nuclear-Fueled Thermal Power Plants)

 

469.590     Definitions for ORS 469.590 to 469.595

 

469.593     Findings

 

469.594     Storage of high-level radioactive waste after expiration of license prohibited; continuing responsibility for storage; implementation agreements

 

469.595     Condition to site certificate for nuclear-fueled thermal power plant

 

469.597     Election procedure; elector approval required

 

469.599     Public Utility Commission’s duty

 

469.601     Effect of ORS 469.595 on applications and applicants

 

(Transportation of Radioactive Material)

 

469.603     Intent to regulate transportation of radioactive material

 

469.605     Permit to transport required; application; delegation of authority to issue permits; fees; rules

 

469.606     Determination of best and safest route

 

469.607     Authority of council; rules

 

469.609     Annual report to state agencies and local governments on shipment of radioactive wastes

 

469.611     Emergency preparedness and response program; radiation emergency response team; training

 

469.613     Records; inspection; rules

 

469.615     Indemnity for claims against state insurance coverage certification; reimbursement for costs incurred in nuclear incident

 

469.617     Report to legislature; content

 

469.619     State Department of Energy to make federal regulations available

 

RESIDENTIAL ENERGY CONSERVATION ACT

 

(Investor-Owned Utilities)

 

469.631     Definitions for ORS 469.631 to 469.645

 

469.633     Investor-owned utility program

 

469.634     Contributions for urban and community forest activities by customers of investor-owned utilities; rules; uses

 

469.635     Alternative program of investor-owned utilities

 

469.636     Additional financing program by investor-owned utility for rental dwelling

 

469.637     Energy conservation part of utility service of investor-owned utility

 

469.639     Billing for energy conservation measures

 

469.641     Conditions for cash payments to dwelling owner by investor-owned utility

 

469.643     Formula for customer charges; rules

 

469.645     Implementation of program by investor-owned utility

 

(Publicly Owned Utilities)

 

469.649     Definitions for ORS 469.649 to 469.659

 

469.651     Publicly owned utility program

 

469.652     Contributions for urban and community forest activities by customers of publicly owned utilities; rules; uses

 

469.653     Alternative program of publicly owned utility

 

469.655     Energy conservation as part of utility service of publicly owned utility

 

469.657     Conditions for cash payments to dwelling owner by publicly owned utility

 

469.659     Implementation of program by publicly owned utility

 

(Miscellaneous)

 

469.685     Use of earlier energy audit

 

469.687     Title for ORS 456.594 to 456.599 and 469.631 to 469.687

 

ENERGY CONSERVATION PROGRAMS

 

(Single Family Residence)

 

469.700     Energy efficiency ratings; public information; “single family residence” defined

 

(Home Energy Performance Score System)

 

469.703     Home energy performance score system; home energy assessors; reports; database; rules

 

(Low Interest Loans)

 

469.710     Definitions for ORS 469.710 to 469.720

 

469.715     Low interest loans for cost-effective energy conservation; rate

 

469.717     When installation to be completed

 

469.719     Eligibility of lender for tax credit not affected by owner’s failure

 

469.720     Energy audit required; permission to inspect required; owner not to receive other incentives

 

(Public Buildings)

 

469.730     Declaration of purpose

 

469.735     Definitions for ORS 469.730 to 469.745

 

469.740     Rules establishing energy conservation standards for public buildings; bases

 

469.745     Voluntary compliance program

 

469.748     State agencies to conduct assessments of energy use and greenhouse gas emissions of state-owned buildings; planning targets in capital projects; state agency reporting

 

469.750     State purchase of alternative fuels

 

(State Agency Projects)

 

469.752     Definitions for ORS 469.752 to 469.756

 

469.754     Authority of state agencies to establish projects; use of savings

 

469.756     Rules; technical assistance; evaluations

 

DESIGNATED STATE AGENCY PROGRAMS FOR ENERGY EFFICIENCY IN BUILDINGS

 

469.760     Legislative findings; state goals related to adoption and use of heat pump technologies

 

469.763     Definitions related to designated state agency programs

 

469.766     Biennial report on adoption of heat pump technologies in this state

 

469.769     Program to reduce barriers to home energy efficiency and resilience

 

469.772     Energy Efficient Technologies Information and Training Fund

 

PACIFIC NORTHWEST ELECTRIC POWER AND CONSERVATION PLANNING COUNCIL

 

469.802     Definition for ORS 469.802 to 469.845

 

469.803     Oregon participation in Pacific Northwest Electric Power and Conservation Planning Council

 

469.805     State members of council; confirmation; qualifications

 

469.810     Conflicts of interest prohibited

 

469.815     Status of members; duties; attendance at public meetings; technical assistance

 

469.820     Term; reappointment; vacancy

 

469.825     Prohibited activities of members

 

469.830     Removal of members; grounds; procedure

 

469.835     Salary of members; staff

 

469.840     Northwest Regional Power and Conservation Account; uses

 

469.845     Annual report to Governor and legislature

 

COMMERCIAL ENERGY CONSERVATION SERVICES PROGRAM

 

469.860     Definitions for ORS 469.860 to 469.900

 

469.863     Gas utility to adopt commercial energy audit program; rules

 

469.865     Electric utility to adopt commercial energy conservation services program

 

469.870     Application of ORS 469.865, 469.870 and 469.900 (1) to electric utility

 

469.875     Fee for gas utility audit

 

469.880     Energy audit program; rules

 

469.885     Publicly owned utility to adopt commercial energy audit program; fee

 

469.890     Publicly owned utility to adopt commercial energy conservation program; fees; rules

 

469.895     Application of ORS 469.890 to 469.900 to publicly owned utility

 

469.900     Duty of commission to avoid conflict with federal requirements

 

NORTHWEST INTERSTATE COMPACT ON LOW-LEVEL RADIOACTIVE WASTE MANAGEMENT

 

469.930     Northwest Interstate Compact on Low-Level Radioactive Waste Management

 

POWER COSTS AND RATES

 

469.950     Authority to enter into interstate cooperative agreements to control power costs and rates; Bonneville Power Administration

 

PENALTIES

 

469.990     Penalties

 

469.992     Civil penalties

 

GENERAL PROVISIONS

 

      469.010 Policy. The Legislative Assembly finds and declares that:

      (1) Continued growth in demand for nonrenewable energy forms poses a serious and immediate, as well as future, problem. It is essential that future generations not be left a legacy of vanished or depleted resources, resulting in massive environmental, social and financial impact.

      (2) It is the goal of Oregon to promote the efficient use of energy resources and to develop permanently sustainable energy resources. The need exists for comprehensive state leadership in energy production, distribution and utilization. It is, therefore, the policy of Oregon:

      (a) That development and use of a diverse array of permanently sustainable energy resources be encouraged utilizing to the highest degree possible the private sector of our free enterprise system.

      (b) That through state government example and other effective communications, energy conservation and elimination of wasteful and uneconomical uses of energy and materials be promoted. This conservation must include, but not be limited to, resource recovery and materials recycling.

      (c) That the basic human needs of every citizen, present and future, shall be given priority in the allocation of energy resources, commensurate with perpetuation of a free and productive economy with special attention to the preservation and enhancement of environmental quality.

      (d) That state government assist every citizen and industry in adjusting to a diminished availability of energy.

      (e) That energy-efficient modes of transportation for people and goods shall be encouraged, while energy-inefficient modes of transportation shall be discouraged.

      (f) That cost-effectiveness be considered in state agency decision-making relating to energy sources, facilities or conservation, and that cost-effectiveness be considered in all agency decision-making relating to energy facilities.

      (g) That state government shall provide a source of impartial and objective information in order that this energy policy may be enhanced. [1975 c.606 §1; 1979 c.723 §1]

 

      469.020 Definitions. As used in ORS 176.820, 469.010 to 469.155, 469.860 (3), 469.880 to 469.895, 469.900 (3), 469.990, 469.992, 757.710 and 757.720, unless the context requires otherwise:

      (1) “Agency” includes a department or other agency of state government, city, county, municipal corporation, political subdivision, port, people’s utility district, joint operating agency and electric cooperative.

      (2) “Coal supplier” means any person engaged in the wholesale distribution in this state of coal intended for use in this state for an energy facility.

      (3) “Cost-effective” means that an energy resource, facility or conservation measure during its life cycle results in delivered power costs to the ultimate consumer no greater than the comparable incremental cost of the least cost alternative new energy resource, facility or conservation measure. Cost comparison under this definition shall include but not be limited to:

      (a) Cost escalations and future availability of fuels;

      (b) Waste disposal and decommissioning costs;

      (c) Transmission and distribution costs;

      (d) Geographic, climatic and other differences in the state; and

      (e) Environmental impact.

      (4) “Council” means the Energy Facility Siting Council established under ORS 469.450.

      (5) “Department” means the State Department of Energy created under ORS 469.030.

      (6) “Director” means the Director of the State Department of Energy appointed under ORS 469.040.

      (7) “Energy facility” has the meaning given in ORS 469.300.

      (8) “Energy generation area” means an area within which the effects of two or more small generating plants may accumulate so the small generating plants have effects of a magnitude similar to a single generating plant of 25 megawatts or more. An energy generation area for facilities using a geothermal resource and covered by a unit agreement, as provided in ORS 522.405 to 522.545 or by federal law, shall be defined in that unit agreement. If no such unit agreement exists, an energy generation area for facilities using a geothermal resource shall be the area that is within two miles, measured from the electrical generating equipment of the facility, of an existing or proposed geothermal electric power generating plant, not including the site of any other such plant not owned or controlled by the same person.

      (9) “Geothermal reservoir” means an aquifer or aquifers containing a common geothermal fluid.

      (10) “Nominal electric generating capacity” has the meaning given in ORS 469.300.

      (11) “Person” means an individual, partnership, joint venture, private or public corporation, association, firm, public service company, political subdivision, municipal corporation, government agency, people’s utility district, or any other entity, public or private, however organized.

      (12) “Petroleum supplier” means a petroleum refiner in this state, or any person engaged in the wholesale distribution of crude petroleum or derivative thereof or of propane in this state.

      (13) “Related or supporting facilities” means any structure, proposed by the applicant, to be constructed or substantially modified in connection with the construction of an energy facility, including associated transmission lines, reservoirs, storage facilities, intake structure, road and rail access, pipelines, barge basins, office or public buildings, and commercial and industrial structures. “Related or supporting facilities” does not include geothermal or underground gas storage reservoirs, production, injection or monitoring wells or wellhead equipment or pumps.

      (14) “Site” means a proposed location of an energy facility, and its related or supporting facilities.

      (15) “Thermal power plant” has the meaning given that term by ORS 469.300.

      (16) “Utility” includes:

      (a) An individual, a regulated electrical company, a people’s utility district, a joint operating agency, an electric cooperative, municipality or any combination thereof, engaged in or authorized to engage in the business of generating, transmitting or distributing electric energy;

      (b) A person or public agency generating electric energy from an energy facility for its own consumption; and

      (c) A person engaged in this state in the transmission or distribution of natural or synthetic gas. [1975 c.606 §2; 1977 c.794 §1; 1979 c.723 §2; 1981 c.629 §1; 1981 c.792 §1; 1991 c.480 §3; 1993 c.569 §1; 1995 c.505 §4; 1995 c.551 §2; 2003 c.186 §16]

 

STATE DEPARTMENT OF ENERGY; ADMINISTRATION

 

      469.030 State Department of Energy; duties. (1) There is created the State Department of Energy.

      (2) The State Department of Energy shall:

      (a) Be the central repository within the state government for the collection of data on energy resources;

      (b) Endeavor to utilize all public and private sources to inform and educate the public about energy problems and ways in which the public can conserve energy resources;

      (c) Engage in research, but whenever possible, contract with appropriate public or private agencies and dispense funds for research projects and other services related to energy resources, except that the State Department of Energy shall endeavor to avoid duplication of research whether completed or in progress;

      (d) Qualify for, accept and disburse or utilize any private or federal moneys or services available for the administration of ORS 176.820, 192.338, 192.345, 192.355, 192.690, 469.010 to 469.155, 469.300 to 469.563, 469.990, 757.710 and 757.720;

      (e) Administer federal and state energy allocation and conservation programs and energy research and development programs and apply for and receive available funds therefor;

      (f) Be a clearinghouse for energy research to which all agencies shall send information on all energy related research;

      (g) Prepare contingent energy programs to include all forms of energy not otherwise provided pursuant to ORS 757.710 and 757.720;

      (h) Maintain an inventory of energy research projects in Oregon and the results thereof;

      (i) Collect, compile and analyze energy statistics, data and information;

      (j) Contract with public and private agencies for energy activities consistent with ORS 469.010 and this section;

      (k) Upon request of the governing body of any affected jurisdiction, coordinate a public review of a proposed transmission line according to the provisions of ORS 469.442; and

      (L) Advise the Governor on energy-related matters. [1975 c.606 §4; 1981 c.792 §2; 1987 c.200 §4; 1993 c.569 §2; 1995 c.551 §3; 1999 c.934 §5; 1999 c.1043 §9; 2003 c.186 §1; 2013 c.656 §7]

 

      Note: Section 1, chapter 376, Oregon Laws 2021, provides:

      Sec. 1. Legislative findings about offshore wind energy. (1) The Legislative Assembly finds that:

      (a) Oregon offshore wind holds tremendous potential and promise for this state to diversify its energy portfolio.

      (b) Oregon has an opportunity to participate in a growing global market by contributing to the development of the nascent offshore wind energy supply chain.

      (c) An intergovernmental task force led by the Bureau of Ocean Energy Management has reengaged and is expected to reveal offshore wind call areas in 2021 for the development of floating offshore wind energy within the federal waters off the Oregon coast.

      (d) Oregon has an opportunity to participate in holistic west coast planning for the strategic integration of floating offshore wind energy within the next decade and to position itself for potential market expansion thereafter.

      (e) The Department of Land Conservation and Development has an established role as the lead state agency coordinating with the federal process for floating offshore wind development and, as the lead agency of the federally approved Oregon Coastal Management Program, the department implements the state’s federal consistency authority pursuant to the Coastal Zone Management Act of 1972 and associated federal regulations. The department implements federal consistency review by evaluating federal activities for compliance with state enforceable policies and their reasonably foreseeable effects to coastal uses and resources of the Oregon coastal zone, and the department will coordinate with networked agency and local government partners to evaluate floating offshore wind development activities for consistency with the Oregon Coastal Management Program.

      (f) The Oregon Business Development Department has established a leadership role in facilitating attracting the floating offshore wind energy industry to this state and in facilitating floating offshore wind energy supply chain development.

      (g) Understanding the impacts, benefits, opportunities and barriers of floating offshore wind energy with respect to Oregon’s fishing communities, ocean and shore-side recreational users, tribes, ports, coastal ecosystems, natural resources, manufacturing industry, maritime sector, disaster recovery planning, workforce development and electricity ratepayers can maximize the benefits to this state, while minimizing the conflicts between floating offshore wind energy, the ocean ecosystem and ocean users.

      (h) Defining a pathway for Oregon to take advantage to the fullest extent possible of the federal offshore wind investment tax credit and other federal infrastructure investment programs that could benefit Oregon’s ports and transmission system can facilitate immediate economic investments as well as long term ratepayer savings.

      (i) Understanding the feasibility of using offshore wind as a clean power source for the future in-state generation of renewable fuel such as renewable hydrogen will strengthen state and regional energy decarbonization planning scenarios.

      (j) Investigating potential mechanisms to integrate floating offshore wind energy into Oregon’s future energy mix will strengthen state and regional energy decarbonization strategies.

      (2) In furtherance of the findings set forth in subsection (1) of this section, the Legislative Assembly finds and declares that:

      (a) It is the goal of this state to plan for the development of up to three gigawatts of floating offshore wind energy projects within the federal waters off the Oregon coast by 2030;

      (b) It is further the goal of this state that the planning described in this subsection be conducted in a manner that will maximize benefits to this state while minimizing conflicts between floating offshore wind energy, the ocean ecosystem and ocean users; and

      (c) Consistent with applicable federal law, it shall be the policy position of the State of Oregon that:

      (A) Any federal planning or permitting process for offshore energy research and development in federal waters off the Oregon coast and for any related transmission and other facilities, particularly those that transverse Oregon’s territorial sea, shall adequately consider the prompt decommissioning of any offshore facility after permanent cessation of use of the facility; and

      (B) Adequate consideration as described in this paragraph must include consideration of the removal or decommissioning of anchors, cables and any other equipment related to the facility in a manner that will serve to avoid future conflicts between the equipment and fishing operations conducted by persons who hold licenses issued pursuant to the commercial fishing laws. [2021 c.376 §1]

 

      469.040 Director; duties; appointment; rules. (1) The State Department of Energy shall be under the supervision of the Director of the State Department of Energy, who shall:

      (a) Supervise the day-to-day functions of the State Department of Energy;

      (b) Supervise and facilitate the work and research on energy facility siting applications at the direction of the Energy Facility Siting Council;

      (c) Hire, assign, reassign and coordinate personnel of the State Department of Energy, prescribe their duties and fix their compensation, subject to the State Personnel Relations Law; and

      (d) Adopt rules and issue orders to carry out the duties of the director and the State Department of Energy in accordance with ORS chapter 183 and the policy stated in ORS 469.010.

      (2) The director may delegate to any officer or employee the exercise and discharge in the director’s name of any power, duty or function of whatever character vested in the director by law. The official act of any person acting in the director’s name and by the director’s authority shall be considered an official act of the director.

      (3) The director shall be appointed by the Governor, subject to confirmation by the Senate in the manner provided by ORS 171.562 and 171.565. [1975 c.606 §5; 1985 c.593 §1; 1993 c.496 §3; 1995 c.551 §4; 1999 c.934 §6; 1999 c.1043 §10; 2003 c.186 §3; 2017 c.314 §1]

 

      469.050 Limitations on subsequent employment of director; sanctions. (1) A person who has been the Director of the State Department of Energy shall not, within two years after the person ceases to be the director, be an employee of:

      (a) An owner or operator of an energy facility;

      (b) An applicant for a site certificate; or

      (c) Any person who engages in the sale or manufacture of any energy resource or of any major component of an energy facility in Oregon.

      (2) Employment of any individual in violation of subsection (1)(a) or (b) of this section shall be grounds for the revocation of any license issued by this state or any agency thereof and held by the person that employs such individual. [1975 c.606 §§6,7]

 

      469.055 Authority of department to require fingerprints. For the purpose of requesting a state or nationwide criminal records check under ORS 181A.195, the State Department of Energy may require the fingerprints of a person who:

      (1)(a) Is employed or applying for employment by the department; or

      (b) Provides services or seeks to provide services to the department as a contractor or volunteer; and

      (2) Is, or will be, working or providing services in a position:

      (a) In the Hanford nuclear safety program;

      (b) In which the person conducts energy audits in schools, colleges, universities or medical facilities;

      (c) In the budget and finance section of the department;

      (d) That has personnel or human resources functions as one of the position’s primary responsibilities;

      (e) In which the person is providing information technology services and has control over, or access to, information technology systems that would allow the person to harm the information technology systems or the information contained in the systems;

      (f) In which the person has access to personal information about employees or members of the public including Social Security numbers, dates of birth, driver license numbers or criminal background information; or

      (g) In which the person has access to tax or financial information about individuals or business entities or processes tax credits. [2005 c.730 §7]

 

      Note: 469.055 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.059 Biennial comprehensive report; contents; compilation; public comment. (1) No later than November 1 of every even-numbered year, the State Department of Energy shall transmit to the Governor and the Legislative Assembly a comprehensive report on energy resources, policies, trends and forecasts in Oregon. The purposes of the report shall be to inform local, state, regional and federal energy policy development, energy planning and energy investments, and to identify opportunities to further the energy policies stated in ORS 469.010 and 469.310.

      (2) Consistent with the legislatively approved budget, the report shall include, but need not be limited to, data and information on:

      (a) The consumption, generation, transmission and production of energy, including fuel energy;

      (b) Energy costs;

      (c) Energy sectors, markets, technologies, resources and facilities;

      (d) Energy efficiency and conservation;

      (e) The effects of energy use, including effects related to greenhouse gas emissions;

      (f) Local, state, regional and federal regulations, policies and planning activities related to energy; and

      (g) Emerging energy opportunities, challenges and impacts.

      (3) The report may include, but need not be limited to:

      (a) Recommendations for the development and maximum use of cost-effective conservation methods and renewable resources, consistent with the energy policies stated in ORS 469.010 and 469.310 and, where appropriate, the energy plan and fish and wildlife program adopted by the Pacific Northwest Electric Power and Conservation Planning Council pursuant to P.L. 96-501; and

      (b) Recommendations for proposed research, development and demonstration projects and programs necessary to further the energy policies stated in ORS 469.010 and 469.310.

      (4) The report shall be compiled by collecting, organizing and refining data and information acquired by the department in the performance of its existing duties and under its existing authority.

      (5)(a) This section is not intended to allow disclosure of records exempt from disclosure under ORS 192.311 to 192.478.

      (b) The department shall establish procedures for the development and compilation of the report that:

      (A) Allow for a person to request the exclusion from the report of specific data or information submitted by the person to the department and to provide, in the request, reasoning as to why the data or information is exempt from disclosure under ORS 192.311 to 192.478; and

      (B) Protect data and information that the department determines to be exempt from disclosure in accordance with ORS 192.338.

      (c) The department may utilize data and information that is exempt from disclosure under ORS 192.311 to 192.478 in compilation or analysis that is included in the report, provided that the exempt data and information is not disclosed in a manner that is individually identifiable.

      (6) Upon request from the department, other agencies shall assist the department in the performance of its duties under this section.

      (7) The department shall seek public input and provide opportunities for public comment during the development of the report. [2017 c.286 §3]

 

      469.060 [1975 c.606 §8; 1983 c.273 §1; 1989 c.466 §1; 1995 c.505 §5; 1995 c.551 §19a; repealed by 2017 c.286 §1]

 

      469.062 Comprehensive state energy strategy; periodic update. (1) The State Department of Energy shall develop a comprehensive state energy strategy that identifies optimized pathways to achieving the state’s energy policy objectives.

      (2) The state energy strategy must be informed, at a minimum, by the following:

      (a) Stakeholder perspectives;

      (b) State laws, policies and targets regarding energy and greenhouse gas emissions;

      (c) Existing energy and integrated resource plans;

      (d) Energy-related studies and data analysis; and

      (e) State energy policy objectives.

      (3) In identifying optimized pathways to achieving the state’s energy policy objectives, the state energy strategy must take into account, at a minimum, the following factors:

      (a) State energy demand and trends;

      (b) Energy resources and technology choices in consideration of costs, energy efficiency, feasibility and availability;

      (c) Economic and employment impacts;

      (d) Energy burden and affordability;

      (e) Energy resilience, as defined in section 29, chapter 508, Oregon Laws 2021, and energy reliability;

      (f) Environmental justice, as defined in ORS 469A.400;

      (g) Land use considerations;

      (h) Natural resource impacts;

      (i) Emerging technologies and investment opportunities;

      (j) Energy generation, transmission and distribution infrastructure needed to achieve state energy policy objectives;

      (k) Existing and potential incentives to support energy efficiency, development and deployment;

      (L) Energy security and impacts of broader markets;

      (m) Community benefits; and

      (n) Community energy resilience, as defined in section 29, chapter 508, Oregon Laws 2021.

      (4)(a) In developing the state energy strategy, the department shall engage with relevant state agencies, federally recognized Indian tribes and stakeholders. At a minimum, the stakeholders must represent a diverse range of:

      (A) Interests, perspectives, expertise and education;

      (B) Socioeconomic backgrounds;

      (C) Communities; and

      (D) Geographic areas of this state.

      (b) The department may convene an advisory work group to inform the department on the department’s engagement with stakeholders and development of the state energy strategy.

      (5)(a) The department shall ensure that the state energy strategy developed under this section reflects the best available information, data analyses and time horizons necessary to achieving the state’s energy policy objectives.

      (b) The department shall periodically update the state energy strategy to reflect current information, data analysis and state energy policy objectives.

      (c) The department shall inform the Governor and Legislative Assembly when the department updates the state energy strategy.

      (6) The department may contract with third parties for assistance in performing the department’s duties under this section, including assistance with technical or facilitation services.

      (7) All agencies of state government, as defined in ORS 174.111, are directed, to the extent permitted by laws relating to confidentiality, to furnish such information and advice to the department as the department considers necessary to perform the department’s duties under this section. [2023 c.562 §2]

 

      Note: 469.062 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      Note: Sections 3 and 4, chapter 562, Oregon Laws 2023, provide:

      Sec. 3. (1) The State Department of Energy shall produce a report regarding the state energy strategy developed under section 2 of this 2023 Act [469.062]. The report, at minimum, must:

      (a) Summarize the state energy strategy and optimized pathways to achieving the state’s energy policy objectives;

      (b) Describe the department’s engagement process with stakeholders and how stakeholder perspectives informed the state energy strategy; and

      (c) Recommend legislation or changes to policy necessary to implement the state energy strategy.

      (2) The department shall submit the report produced under subsection (1) of this section to the Governor and the appropriate interim committees of the Legislative Assembly in the manner provided under ORS 192.245 no later than November 1, 2025. [2023 c.562 §3]

      Sec. 4. Section 3 of this 2023 Act is repealed on January 2, 2026. [2023 c.562 §4]

 

      469.064 Energy security plan; requirements; fuel storage capacity; report. (1) The State Department of Energy shall develop an energy security plan. The energy security plan must meet the requirements for a state energy security plan described in 42 U.S.C. 6326.

      (2) To the extent consistent with the requirements of 42 U.S.C. 6326, the energy security plan must align with strategies in the Oregon Fuel Action Plan developed by the department and must include, but need not be limited to:

      (a) An evaluation of the state’s ability to recover quickly from physical threats, including a magnitude 9.0 Cascadia Subduction Zone earthquake, and cybersecurity threats.

      (b) Recommendations for increasing the geographic diversity of fuel storage capacity throughout this state.

      (c) An assessment of the seismic resilience of existing fuel storage facilities throughout this state.

      (d) Consistent with state programs to reduce greenhouse gas emissions associated with transportation fuels, an assessment of the use of renewable fuels and other innovative alternatives to improve disaster resilience.

      (e) An evaluation of strategies for mitigating barriers to implementing a geographically distributed fuel network throughout this state, including:

      (A) Adoption of Oregon Fuel Action Plan criteria for predesignated fuel points of distribution for receiving emergency fuel supplies at selected fuel diversification sites.

      (B) Strategies for expanding storage capacities at public facilities with existing capability to store and dispense unleaded, diesel or aviation fuel, including an evaluation of whether fuel storage sites contain properly installed seismically certified generators and adequate on-site fuel storage capacity to power backup generators so that independent operations can be maintained for three or more weeks after a Cascadia Subduction Zone earthquake.

      (C) Partnerships with private-sector companies to build fuel storage capacity at identified, prioritized locations, especially private-sector companies that provide an emergency or essential service mission to save or sustain life or support the restoration of critical lifelines and services in support of the state’s overall response and recovery effort.

      (D) Strategies for increasing geographically distributed fuel storage that prioritize areas of this state that are expected to be most vulnerable to a Cascadia Subduction Zone earthquake, including local or regional islanding effects that would isolate a region from the rest of this state as a result of road or bridge damage.

      (E) An evaluation of potential impacts to communities adjacent to potential locations for emergency fuel storage or expanded fuel storage, including consultation and outreach with those communities.

      (3) In developing and implementing the energy security plan, the department shall consult with:

      (a) Relevant state government agencies, including the Public Utility Commission, the Department of Environmental Quality, the Department of Transportation, the Oregon Department of Aviation, the Oregon Department of Emergency Management, the State Department of Geology and Mineral Industries and the Environmental Justice Council;

      (b) Local governments;

      (c) Tribal governments;

      (d) Consumer-owned and investor-owned electric utilities;

      (e) Natural gas utilities;

      (f) Fuel suppliers;

      (g) Qualified technical experts in disaster resilience; and

      (h) Any other person with relevant knowledge or experience.

      (4) No later than September 15 of each even-numbered year, the State Department of Energy shall provide to the interim committees of the Legislative Assembly related to energy a report in the manner provided under ORS 192.245 describing the implementation or revision of the energy security plan developed under this section. [2022 c.99 §12; 2022 c.99 §13]

 

      Note: 469.064 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      Note: Sections 16 and 17, chapter 99, Oregon Laws 2022, provide:

      Sec. 16. The State Department of Energy shall submit the energy security plan developed under section 12 of this 2022 Act [469.064] in a report to the interim committees of the Legislative Assembly related to energy, in the manner provided under ORS 192.245, no later than June 1, 2024. [2022 c.99 §16]

      Sec. 17. Sections 15 and 16 of this 2022 Act are repealed on January 2, 2025. [2022 c.99 §17]

 

      469.070 [1975 c.606 §9; 1977 c.794 §3; 1983 c.273 §2; 2003 c.186 §17; repealed by 2017 c.286 §1]

 

      469.080 Energy resource information; subpoena power; depositions; limitations on obtaining information; protection from abuse. (1) The Director of the State Department of Energy may obtain all necessary information from producers, suppliers and consumers of energy resources within Oregon, and from political subdivisions in this state, as necessary to carry out ORS 176.820, 192.338, 192.345, 192.355, 192.690, 469.010 to 469.155, 469.300 to 469.563, 469.990, 469.992, 757.710 and 757.720. Such information may include, but not be limited to:

      (a) Sales volume;

      (b) Forecasts of energy resource requirements;

      (c) Inventory of energy resources; and

      (d) Local distribution patterns of information under paragraphs (a) to (c) of this subsection.

      (2) In obtaining information under subsection (1) of this section, the director, with the written consent of the Governor, may subpoena witnesses, material and relevant books, papers, accounts, records and memoranda, administer oaths, and may cause the depositions of persons residing within or without Oregon to be taken in the manner prescribed for depositions in civil actions in circuit courts, to obtain information relevant to energy resources.

      (3) In obtaining information under this section, the director:

      (a) Shall avoid eliciting information already furnished by a person or political subdivision in this state to a federal, state or local regulatory authority that is available to the director for such study; and

      (b) Shall cause reporting procedures, including forms, to conform to existing requirements of federal, state and local regulatory authorities.

      (4) Any person who is served with a subpoena to give testimony orally or in writing or to produce books, papers, correspondence, memoranda, agreements or the documents or records as provided in ORS 176.820, 192.338, 192.345, 192.355, 192.690, 469.010 to 469.155, 469.300 to 469.563, 469.990, 469.992, 757.710 and 757.720, may apply to any circuit court in Oregon for protection against abuse or hardship in the manner provided in ORCP 36 C. [1975 c.606 §18; 1977 c.358 §9; 1977 c.794 §4a; 1979 c.284 §154; 2003 c.186 §18]

 

      469.085 Procedure for imposing civil penalties; rules. (1) Except as otherwise provided in this section, civil penalties under ORS 469.992 shall be imposed as provided in ORS 183.745.

      (2) Notwithstanding ORS 183.745 (2), the notice to the person against whom a civil penalty is to be imposed shall reflect a complete statement of the consideration given to the factors listed in subsection (7) of this section. The notice may be served by either the Director of the State Department of Energy or the Energy Facility Siting Council.

      (3) Notwithstanding ORS 183.745, if a hearing is not requested or if the person requesting a hearing fails to appear, a final order shall be entered upon a prima facie case made on the record of the agency.

      (4) The provisions of this section are in addition to and not in lieu of any other penalty or sanction provided by law. An action taken by the director or the council under this section may be joined by the director or the council with any other action against the same person under this chapter.

      (5) Any civil penalty recovered under this section shall be paid into the General Fund.

      (6) The director or the council shall adopt by rule a schedule of the amount of civil penalty that may be imposed for a particular violation.

      (7) In imposing a penalty under ORS 469.992, the director or the council shall consider:

      (a) The past history of the person incurring a penalty in taking all feasible steps or procedures necessary or appropriate to correct or prevent any violation;

      (b) Any prior violations of ORS chapter 469 or rules, orders or permits relating to the alleged violation;

      (c) The impact of the violation on public health and safety or public interests in fishery, navigation and recreation;

      (d) Any other factors determined by the director or the council to be relevant; and

      (e) The alleged violator’s cooperativeness and effort to correct the violation.

      (8) The penalty imposed under ORS 469.992 may be remitted or mitigated upon such terms and conditions as the director or council determines to be proper. Upon the request of the person incurring the penalty, the director or council shall consider evidence of the economic and financial condition of the person in determining whether a penalty shall be remitted or mitigated. [1991 c.480 §2; 1991 c.734 §106; 2003 c.186 §19]

 

      469.090 Confidentiality of information submitted under ORS 469.080. (1) Information furnished under ORS 469.080 shall be confidential and maintained as such, if so requested by the person providing the information, if the information meets one of the following requirements:

      (a) The information is proprietary in nature; or

      (b) The information consists of geological and geophysical information and data, including maps, concerning oil, gas or geothermal resource wells.

      (2) Nothing in this section prohibits the use of confidential information to prepare statistics or other general data for publication, so presented as to prevent identification of particular persons. [1975 c.606 §19]

 

      469.095 [1979 c.561 §9; repealed by 1993 c.475 §3]

 

      469.097 Duty to monitor industry progress in energy conservation. The State Department of Energy shall to the extent permitted by its resources monitor industry progress in achieving energy conservation. [1981 c.865 §3; 1987 c.158 §96]

 

      469.100 Agency consideration of legislative policy; agency review of rules. (1) All agencies shall consider the policy stated in ORS 469.010 in adopting or modifying their rules and policies.

      (2) All agencies shall review their rules and policies to determine their consistency with the policy stated in ORS 469.010. [1975 c.606 §3; 1995 c.551 §20]

 

      469.110 Dealings with federal government; intervention by State Department of Energy in agency action. (1) At the direction of the Director of the State Department of Energy, the State Department of Energy may represent the state’s energy-related interests in any matter involving the federal government, its departments or agencies, which is within the scope of the power and duties of the State Department of Energy, and may, upon request, represent the interest of a county, city, state agency, federally recognized Native American or American Indian tribe, special district or owner or operator of an energy facility.

      (2) At the direction of the director, the department may intervene in any proceeding undertaken by an agency for the purpose of expressing its views as to the effect of an agency action, upon state energy resources and state energy policy. [1975 c.606 §12; 2013 c.656 §4]

 

      469.120 State Department of Energy Account; appropriation; record of moneys. (1) The State Department of Energy Account is established.

      (2) The account shall consist of all funds received by the State Department of Energy pursuant to law. All moneys in the account are continuously appropriated to the State Department of Energy for payment of expenses of the department and of the Energy Facility Siting Council.

      (3) Moneys collected under ORS 469.421 (8) may be expended only for the purposes of programs and activities that the council and the department are charged with administering and authorized to conduct under the laws of this state, including those enumerated in ORS 469.030.

      (4) The Director of the State Department of Energy shall keep a record of all moneys deposited in the account. The record shall indicate by special cumulative accounts the source from which moneys are derived and the individual activity or program, including any activities described in ORS 469.424, against which each withdrawal is charged. On or after October 1 of each year, the director shall make available, upon request, the record for the prior fiscal year to any energy resource supplier that has paid the assessment imposed under ORS 469.421 (8). The director shall make the record available within 30 days of receiving the request. [1975 c.606 §13; 1995 c.551 §5; 2003 c.186 §7; 2013 c.656 §8]

 

      469.130 [1975 c.606 §47; 1977 c.794 §5; 1977 c.891 §10; 1987 c.879 §16; repealed by 1995 c.551 §21]

 

      469.135 Energy Conservation Clearinghouse for Commerce and Industry. The State Department of Energy shall expand the Energy Conservation Clearinghouse for Commerce and Industry so that it provides:

      (1) Current information to business and industry on:

      (a) State and federal financing mechanisms;

      (b) Tax advantages of energy conservation investments; and

      (c) General economic advantages of energy conservation investments.

      (2) Teaching on conservation techniques and management of energy by corporations. [1981 c.865 §2]

 

      469.137 Biogas and renewable natural gas inventory; contents; use; advisory committee. (1) As used in this section:

      (a) “Biogas” means gas that is generated from organic waste or other organic materials through anaerobic digestion, gasification, pyrolysis or other technology that converts organic waste to gas.

      (b) “Renewable natural gas” is biogas that has been processed to be interchangeable with conventional natural gas for the purpose of meeting pipeline quality standards or transportation fuel grade requirements.

      (2) The State Department of Energy shall develop, maintain and periodically update an inventory of biogas and renewable natural gas resources available to this state. The inventory must include, but need not be limited to:

      (a) A list of the potential biogas and renewable natural gas sources in this state and the estimated potential production quantities available at each source;

      (b) An estimate of the energy content of listed potential biogas and renewable natural gas sources;

      (c) An estimate of the range of technologies available to this state for renewable natural gas production by conversion technologies such as anaerobic digestion and thermal gasification; and

      (d) A list of the existing biogas production sites in this state that includes:

      (A) The location of each site; and

      (B) An assessment of the supply-chain infrastructure associated with the site.

      (3) The department shall utilize the inventory required by this section, and any other relevant information as considered necessary by the department, to develop and periodically revise an estimate of:

      (a) The potential quantity of renewable natural gas that could be produced in this state and delivered for use:

      (A) As a transportation fuel in the form of compressed natural gas or liquefied natural gas; and

      (B) By residential, commercial and industrial consumers of natural gas;

      (b) The potential for the use of renewable natural gas in this state to reduce greenhouse gas emissions;

      (c) The potential for renewable natural gas in this state to improve air quality; and

      (d) The technical, market, policy and regulatory barriers to developing and utilizing renewable natural gas in this state.

      (4) The department shall appoint an advisory committee to assist in developing, maintaining and periodically updating the inventory required by this section. The committee must include but not be limited to persons familiar with the renewable natural gas industry. The committee shall make recommendations to the department:

      (a) Regarding the identification and removal of barriers to producing and utilizing biogas and renewable natural gas in this state as a means toward providing the greatest feasible reductions in greenhouse gas emissions and improvements in air quality;

      (b) On establishing policies to promote renewable natural gas; and

      (c) On any other matters related to this section, as requested by the department. [2017 c.328 §1]

Note: 469.137 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.140 [1975 c.606 §48; repealed by 1977 c.794 §6]

 

      469.150 Energy suppliers to provide conservation services and information; rules. (1) As used in this section “energy conservation services” means services provided by energy suppliers to educate and inform customers and the public about energy conservation. Such services include but are not limited to providing answers to questions concerning energy saving devices and providing inspections and making suggestions concerning the construction and siting of buildings and residences.

      (2) Energy suppliers other than public utilities as defined in ORS 757.005, that produce, transmit, deliver or furnish heat, light or power shall establish energy conservation services and shall provide energy conservation information to customers and to the public. The services shall be performed in accordance with such guidelines as the Director of the State Department of Energy may by rule prescribe.

      (3) As used in this section “energy supplier” means a publicly owned utility or fuel oil dealer which supplies electricity or fuel oil for the space heating of dwellings. [1977 c.887 §13]

 

      469.155 Advisory energy conservation standards for dwellings; rules. (1) As used in this section:

      (a) “Dwelling” means real or personal property inhabited as the principal residence of an owner or renter. “Dwelling” includes a manufactured dwelling as defined in ORS 446.003, a floating home as defined in ORS 830.700 and multiple unit residential housing. “Dwelling” does not include a recreational vehicle as defined in ORS 174.101.

      (b) “Energy conservation standards” means standards for the efficient use of energy for space and water heating in a dwelling.

      (2) The Director of the State Department of Energy shall establish advisory energy conservation standards for existing dwellings. The standards shall be adopted by rule in accordance with ORS 183.310 to 183.410. The standards:

      (a) Shall take cost-effectiveness into account; and

      (b) Shall be compatible with and further the state’s incentive programs for residential energy conservation.

      (3) The director shall publicize the energy conservation standards and encourage home owners to voluntarily comply with the standards. [1981 c.565 §2; 1987 c.158 §97; 1989 c.648 §65; 2003 c.186 §20; 2019 c.422 §33]

 

      469.157 [1981 c.746 §7; repealed by 1995 c.79 §287]

 

      469.160 [1977 c.196 §2; 1979 c.670 §3; 1981 c.894 §4; 1983 c.346 §1; 1983 c.768 §2; 1987 c.492 §2; 1989 c.880 §1; 1995 c.746 §19a; 1997 c.534 §4; 1999 c.510 §1; 2001 c.584 §5; 2005 c.832 §6; 2007 c.843 §28; 2011 c.730 §70; renumbered 469B.100 in 2011]

 

      469.161 Single resource for providing information and assistance related to energy efficiency incentives and programs. (1) The State Department of Energy shall create a single resource that provides to interested persons information, technical assistance and assistance in identifying contractors and financing options, related to available energy efficiency incentives and programs.

      (2) The department shall coordinate information and data exchanges between federal and state agencies, private and public utility providers, and energy efficiency incentive or program providers as may be necessary to:

      (a) Create and maintain the single resource described under subsection (1) of this section; and

      (b) Support the implementation and reporting requirements of available energy efficiency incentives and programs.

      (3) The department may contract with a nonprofit or other entity as may be necessary to carry out the provisions of this section.

      (4) Entities that exchange, compile or maintain information or data under this section or that are involved in carrying out the provisions of this section shall use best practices to maintain the confidentiality and security of the information and data as required by federal and state law, including the Oregon Consumer Information Protection Act and ORS 192.355. [2023 c.562 §9]

 

      Note: 469.161 to 469.183 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.165 [1977 c.196 §3; 1989 c.880 §2; 1997 c.534 §5; 2005 c.832 §7; 2007 c.843 §30; 2011 c.730 §70a; renumbered 469B.103 in 2011]

 

      469.166 Program to assist environmental justice communities. The State Department of Energy shall establish a program to provide assistance related to energy projects and activities to environmental justice communities, as defined in ORS 469A.400. At a minimum, the program must provide environmental justice communities with information regarding:

      (1) Funding resources.

      (2) Technical assistance.

      (3) Other support that may be available. [2023 c.562 §1]

 

      Note: See note under 469.161.

 

      469.170 [1977 c.196 §4; 1979 c.670 §4; 1981 c.894 §5; 1983 c.346 §2; 1987 c.492 §3; 1989 c.880 §3; 1995 c.746 §20; 1997 c.534 §6; 1999 c.21 §78; 2001 c.584 §6; 2003 c.186 §21; 2005 c.832 §8; 2007 c.843 §31; 2011 c.730 §71; renumbered 469B.106 in 2011]

 

      469.171 [1999 c.765 §2; renumbered 469B.109 in 2011]

 

      469.172 [1989 c.880 §7; 1995 c.746 §20a; 1999 c.510 §2; 2001 c.584 §7; 2005 c.832 §9; 2007 c.843 §32; 2011 c.730 § 72; renumbered 469B.112 in 2011]

 

      469.175 [1977 c.196 §5; 1979 c.670 §5; 1981 c.894 §6; 1983 c.346 §3; 1987 c.492 §4; repealed by 1989 c.880 §4 (469.176 enacted in lieu of 469.175)]

 

      469.176 [1989 c.880 §5 (enacted in lieu of 469.175); 1997 c.534 §7; 2005 c.832 §10; 2007 c.843 §33; renumbered 469B.115 in 2011]

 

      469.180 [1977 c.196 §6; 1979 c.670 §6; 1981 c.894 §7; 1983 c.346 §4; 1987 c.492 §5; 1989 c.880 §8; 1993 c.684 §1; 1997 c.534 §10; 2003 c.186 §22; 2005 c.832 §11; 2007 c.843 §34; renumbered 469B.118 in 2011]

 

      469.181 Definitions for ORS 469.181 and 469.183. As used in this section and ORS 469.183:

      (1)(a) “Green electrolytic hydrogen” means hydrogen produced through electrolysis using:

      (A) A renewable energy source as defined in ORS 469A.005;

      (B) Nonemitting electricity that is not derived from a fossil fuel; or

      (C) Electricity that has a carbon intensity that is equal to or less than the average carbon intensity of the electricity served in this state in the calendar year in which construction or expansion of the facility that produces the green electrolytic hydrogen began.

      (b) “Green electrolytic hydrogen” does not include hydrogen manufactured using any conversion technology or steam reforming that produces hydrogen from a fossil fuel feedstock.

      (2) “Nonemitting electricity” has the meaning given that term in ORS 469A.400.

      (3) “Renewable hydrogen” means hydrogen produced using:

      (a) A renewable energy source as defined in ORS 469A.005;

      (b) Nonemitting electricity that is not derived from a fossil fuel; or

      (c) Electricity that has a carbon intensity that is equal to or less than the average carbon intensity of the electricity served in this state in the calendar year in which construction or expansion of the facility that produces the renewable hydrogen began. [2023 c.98 §1]

 

      Note: See note under 469.161.

 

      469.183 Accelerating adoption of green electrolytic and renewable hydrogen fuels. To support the state’s transition to clean energy by accelerating the production, distribution and end use of renewable hydrogen and green electrolytic hydrogen fuels, the State Department of Energy shall:

      (1) Where appropriate, seek and apply for federal funds for which the state is eligible, and support other applications for federal funds, that may be used to support the development and deployment of renewable hydrogen and green electrolytic hydrogen in this state; and

      (2) Provide education and increase awareness regarding renewable hydrogen and green electrolytic hydrogen for federally recognized Indian tribes, local governments, other state agencies, federal agencies, private entities, this state’s four-year public institutions of higher education, labor unions, environmental justice communities and other relevant entities. [2023 c.98 §2]

 

      Note: See note under 469.161.

 

      469.185 [1979 c.512 §3; 1981 c.894 §17; 1985 c.745 §1; 1991 c.711 §1; 1997 c.534 §11; 1997 c.656 §5; 1999 c.365 §1; 1999 c.623 §4; 1999 c.765 §4; 2001 c.583 §4; 2007 c.591 §1; 2007 c.843 §16; 2010 c.76 §4; 2011 c.474 §25; renumbered 469B.130 in 2011]

 

      469.190 [1979 c.512 §2; renumbered 469B.133 in 2011]

 

      469.195 [1979 c.512 §4; 1985 c.745 §2; 2010 c.76 §6; renumbered 469B.136 in 2011]

 

      469.197 [2007 c.843 §22; 2008 c.29 §1; 2010 c.76 §7; 2011 c.474 §26; renumbered 469B.139 in 2011]

 

      469.200 [1979 c.512 §5; 1981 c.894 §18; 1985 c.745 §3; 1987 c.158 §98; 1991 c.711 §3; 1993 c.684 §2; 1995 c.746 §15a; 1997 c.534 §12; 1997 c.656 §6a; 1999 c.365 §2; 2003 c.186 §23; 2007 c.843 §17; 2008 c.29 §2; 2010 c.76 §§8,9,9a; 2011 c. 474 §§27,28,29; renumbered 469B.142 in 2011]

 

      469.205 [1979 c.512 §6; 1981 c.894 §19; 1985 c.745 §4; 1989 c.765 §7; 1991 c.711 §2; 1993 c.684 §3; 1995 c.746 §16; 1997 c.656 §7; 1999 c.623 §5; 1999 c.765 §5; 2001 c.583 §5; 2001 c.660 §2; 2003 c.186 §24; 2007 c.843 §18; 2008 c.29 §3; 2010 c.76 §10; 2011 c.474 §30; renumbered 469B.145 in 2011]

 

      469.206 [1997 c.534 §9; 2001 c.583 §6; 2007 c.843 §19; 2009 c.288 §4; renumbered 469B.148 in 2011]

 

      469.207 [1985 c.745 §9; 1993 c.684 §4; 1995 c.746 §16a; 2001 c.583 §7; renumbered 469B.151 in 2011]

 

      469.208 [1993 c.684 §6; renumbered 469B.154 in 2011]

 

      469.210 [1979 c.512 §7; 1995 c.746 §17; 1997 c.656 §8; 1999 c.365 §3; 2001 c.583 §7a; 2003 c.186 §25; 2010 c.76 §11; renumbered 469B.157 in 2011]

 

      469.215 [1979 c.512 §8; 1981 c.894 §20; 1985 c.745 §5; 1989 c.765 §8; 1991 c.711 §4; 1995 c.746 §18; 1997 c.656 §9; 1999 c.365 §4; 1999 c.623 §6; 2001 c.583 §8; 2001 c.660 §1b; 2003 c.186 §26; 2007 c.843 §20; 2008 c.29 §4; 2010 c.76 §12; renumbered 469B.161 in 2011]

 

      469.217 [1985 c.745 §8; renumbered 469B.164 in 2011]

 

      469.220 [1979 c.512 §9; 2010 c.76 §13; 2011 c.693 §3; renumbered 469B.167 in 2011]

 

      469.225 [1979 c.512 §10; 2003 c.186 §27; 2008 c.29 §5; 2010 c.76 §14; 2011 c.474 §31; renumbered 469B.169 in 2011]

 

      469.228 [1989 c.926 §1; 1991 c.67 §134; 1991 c.641 §5; 1993 c.617 §1; repealed by 1999 c.880 §2]

 

ENERGY EFFICIENCY STANDARDS

 

      469.229 Definitions for ORS 469.229 to 469.261. As used in ORS 469.229 to 469.261, unless the context clearly requires otherwise:

      (1) “À la carte charger” means a battery charger that is individually packaged without batteries, including a multiport charger or a charger with multivoltage capability.

      (2) “Ballast” means a device used with an electric discharge lamp to obtain necessary circuit conditions for starting and operating the lamp.

      (3) “Battery” or “battery pack” means an assembly of one or more rechargeable cells intended to provide electrical energy to a product, in one of the following forms:

      (a) A detachable battery that is contained in an enclosure separate from the product and that is intended to be removed or disconnected from the product for charging; or

      (b) An integral battery that is contained within the product and is not removed from the product for charging.

      (4) “Battery analyzer” means a device:

      (a) Used to analyze and report a battery’s performance and overall condition;

      (b) Capable of being programmed and performing service functions to restore capability in deficient batteries; and

      (c) Not intended or marketed to be used on a daily basis for the purpose of charging batteries.

      (5) “Battery backup” or “uninterruptible power supply charger (UPS)” means a small battery charger system that is voltage and frequency dependent (VFD) and designed to provide power to an end-use product in the event of a power outage, including a UPS as defined in International Electrotechnical Commission (IEC) publication 62040-3 (March 2011 edition), where the output of the VFD UPS is dependent on changes in AC input voltage and frequency and is not intended to provide additional corrective functions, such as those relating to the use of tapped transformers.

      (6)(a) “Battery charger system” means a battery charger coupled with its batteries, including:

      (A) Electronic devices with a battery that are normally charged from AC line voltage or DC input voltage through an internal or external power supply and a dedicated battery charger;

      (B) The battery and battery charger components of devices that are designed to run on battery power during part or all of their operations;

      (C) Dedicated battery systems primarily designed for electrical or emergency backup; and

      (D) Devices whose primary function is to charge batteries, along with the batteries the devices are designed to charge, including chargers for power tool batteries and chargers for automotive, AA, AAA, C, D, or nine-volt rechargeable batteries and chargers for batteries used in larger industrial motive equipment and à la carte chargers.

      (b) “Battery charger system” does not mean a battery charger:

      (A) Used to charge a motor vehicle that is powered by an electric motor drawing current from rechargeable storage batteries, fuel cells or other portable sources of electrical current, including a nonelectrical source of power designed to charge batteries and components thereof, except for battery chargers for forklifts, electric personal assistive mobility devices or low-speed vehicles;

      (B) That is classified as a Class II or Class III device for human use under the Federal Food, Drug, and Cosmetic Act, as in effect on January 1, 2014, and that requires listing and approval as a medical device;

      (C) Used to charge a battery or batteries in an illuminated exit sign, including those products that are a combination illuminated exit sign and emergency egress lighting;

      (D) With input that is three phases of line-to-line 300 volts root mean square or more and is designed for a stationary power application;

      (E) That is a battery analyzer;

      (F) That is a voltage independent or voltage and frequency independent uninterruptible power supply as defined in International Electrotechnical Commission (IEC) publication 62040-3 (March 2011 edition); or

      (G) That is contained completely within a larger product and that provides power for data storage or for continuity within volatile cache or memory systems, that maintains information for system use and that is not capable of powering full operation of the larger product when external AC line voltage is removed.

      (c) The charging circuitry of battery charger systems may or may not be located within the housing of the end-use device. In many cases, the battery may be charged with a dedicated external charger and power supply combination that is separate from the device that runs on power from the battery.

      (7) “Battery maintenance mode” means the mode of operation when the battery charger system is connected to the main electricity supply and the battery is fully charged and connected to the charger.

      (8) “Bottle-type water dispenser” and “water cooler” have the meanings given those terms by the Director of the State Department of Energy by rule.

      (9) “Charge return factor” means the number of ampere-hours returned to the battery during the charge cycle divided by the number of ampere-hours delivered by the battery during discharge.

      (10) “Combination television” means a system in which a television or television monitor and an additional device or devices, including a video cassette recorder, are combined into a single unit in which the additional device or devices are included in the television casing.

      (11) “Commercial dishwasher” has the meaning given that term by the director by rule.

      (12) “Commercial fryer” has the meaning given that term by the director by rule.

      (13)(a) “Commercial hot food holding cabinet” means an appliance that is a heated, fully-enclosed compartment with one or more solid doors and is designed to maintain the temperature of hot food that has been cooked in a separate appliance.

      (b) “Commercial hot food holding cabinet” does not include heated glass merchandising cabinets, drawer warmers or cook-and-hold appliances.

      (14) “Commercial steam cooker” has the meaning given that term by the director by rule.

      (15)(a) “Compact audio product,” also known as a mini, mid, micro or shelf audio system, means an integrated audio system encased in a single housing that includes an amplifier and radio tuner and attached or separable speakers that can reproduce audio from one or more of the following media:

      (A) Magnetic tape;

      (B) Compact disc;

      (C) DVD; or

      (D) Flash memory.

      (b) “Compact audio product” does not include products that can be independently powered by internal batteries, have a powered external satellite antenna or can provide a video output signal.

      (16) “Compensation” means money or any other valuable thing, regardless of form, received or to be received by a person for services rendered.

      (17) “Component television” means a television composed of two or more separate components, including separate display device and tuner, marketed as a television under one model or system designation and having one or more power cords.

      (18) “Computer” has the meaning given that term by the director by rule.

      (19) “Computer monitor” has the meaning given that term by the director by rule.

      (20) “Digital versatile disc” or “DVD” means a laser-encoded plastic medium capable of storing a large amount of digital audio, video and computer data.

      (21)(a) “Digital versatile disc player” or “digital versatile disc recorder” means a commercially available electronic product encased in a single housing that includes an integral power supply and for which the sole purpose is, respectively, the decoding and the production or recording of digitized video signal on a DVD.

      (b) “Digital versatile disc recorder” does not include models that have an electronic programming guide function that provides an interactive, on-screen menu of television listings and downloads program information from the vertical blanking interval of a regular television signal.

      (22) “Electric storage water heater” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (23) “Electronic programming guide” means an application that provides an interactive, on-screen menu of television listings that downloads program information from the vertical blanking interval of a regular television signal.

      (24) “Faucet” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (25) “High color-rendering index fluorescent lamp” and “high CRI fluorescent lamp” have the meanings given those terms by the director by rule.

      (26) “High-intensity discharge lamp” means a lamp in which light is produced by the passage of an electric current through a vapor or gas, and in which the light-producing arc is stabilized by bulb wall temperature and the arc tube has a bulb wall loading in excess of three watts per square centimeter.

      (27)(a) “High light output double-ended quartz halogen lamp” means a lamp that:

      (A) Is designed for general outdoor lighting purposes;

      (B) Contains a tungsten filament;

      (C) Has a rated initial lumen value of greater than 6,000 and less than 40,000 lumens;

      (D) Has at each end a recessed single contact, R7s base;

      (E) Has a maximum overall length between four and 11 inches;

      (F) Has a nominal diameter less than three-fourths inch (T6); and

      (G) Is designed to be operated at a voltage between 110 volts and 200 volts or is designed to be operated at a voltage between 235 volts and 300 volts.

      (b) “High light output double-ended quartz halogen lamp” does not mean a lamp that is:

      (A) A tubular quartz infrared heat lamp; or

      (B) Marked and marketed as a stage and studio lamp with a rated life of 500 hours or less.

      (28) “Inductive charger system” means a small battery charger system that transfers power to the charger through magnetic or electric induction.

      (29) “Kitchen faucet” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (30) “Kitchen replacement aerator” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (31)(a) “Large battery charger system” means a battery charger system with a rated input power of more than two kilowatts.

      (b) “Large battery charger system” does not mean a battery charger system for golf carts.

      (32) “Lavatory faucet” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (33) “Lavatory replacement aerator” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (34) “Multiport charger” means a battery charger that is capable of simultaneously charging two or more batteries and that may have multivoltage capability, allowing two or more batteries of different voltages to charge simultaneously.

      (35) “No battery mode” means the mode of operation in which a battery charger is connected to the main electricity supply and the battery is not connected to the charger.

      (36) “Plumbing fitting” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (37) “Portable electric spa” has the meaning given that term by the director by rule.

      (38) “Public lavatory faucet” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (39) “Power conversion efficiency” means the instantaneous DC output power of the battery charger system divided by the simultaneous utility AC input power.

      (40) “Pressure regulator” means a device that maintains constant operating pressure immediately downstream from the device, given higher pressure upstream.

      (41) “Residential ventilating fan” has the meaning given that term by the director by rule.

      (42) “Selected input mode” means the input port selected that the television uses as a source to produce a visible or audible output and that is required for televisions with multiple possible inputs, including coaxial, composite, S-Video, HDMI and component connectors.

      (43) “Showerhead” has the meaning given that term by the director by rule, after consultation with the State Plumbing Board.

      (44) “Small battery charger system” means:

      (a) A battery charger system with a rated input power of two kilowatts or less.

      (b) A golf cart battery charger system, regardless of input power or battery capacity.

      (45) “Spray sprinkler body” means the exterior case or shell of a sprinkler incorporating a means of connection to the piping system designed to convey water to a nozzle or orifice.

      (46)(a) “Television” means an analog or digital device, including a combination television, a television monitor, a component television and any unit marketed as a television, designed for the display and reception of a terrestrial, satellite, cable or Internet protocol or other broadcast or recorded transmission of analog or digital video or audio signals.

      (b) “Television” does not mean a computer monitor.

      (47) “Television monitor” means a television that does not have an internal tuner, receiver or playback device.

      (48) “Television standby-passive mode” means the mode of operation in which the television is connected to a power source, produces neither sound nor picture but can be switched into another mode with the remote control unit or via an internal signal.

      (49) “USB charger system” means a small battery charger system that uses a universal serial bus (USB) connector as the only power source to charge the battery, and is packaged with an external power supply rated with a voltage output of five volts and a power output of 15 watts or less. [2005 c.437 §1; 2007 c.375 §1; 2007 c.649 §1; 2013 c.418 §§1,2; 2017 c.295 §1; 2021 c.108 §1; 2022 c.4 §1]

 

      Note: 469.229 to 469.261 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.230 [1989 c.926 §3; repealed by 1999 c.880 §2]

 

      469.232 [1989 c.926 §§4,10; 1993 c.617 §2; 1997 c.249 §165; 1997 c.632 §9; repealed by 1999 c.880 §2]

 

      469.233 Energy efficiency standards. The following minimum energy efficiency standards for new products are established:

      (1) Bottle-type water dispensers or water coolers manufactured on or after January 1, 2022, and included in the scope of the United States Environmental Protection Agency’s “Energy Star Program Requirements Product Specification for Water Coolers, Version 2.0,” must have an “on mode with no water draw” energy consumption less than or equal to the following values as measured in accordance with the test requirements of that specification:

      (a) 0.16 kilowatt-hours per day for cold-only units and cook and cold units;

      (b) 0.87 kilowatt-hours per day for storage type hot and cold units; and

      (c) 0.18 kilowatt-hours per day for on demand hot and cold units.

      (2) Commercial hot food holding cabinets shall have a maximum idle energy rate of 40 watts per cubic foot of interior volume, as determined by the “Idle Energy Rate-dry Test” in ASTM F2140-01, “Standard Test Method for Performance of Hot Food Holding Cabinets” published by ASTM International. Interior volume shall be measured in accordance with the method shown in the United States Environmental Protection Agency’s “Energy Star Program Requirements for Commercial Hot Food Holding Cabinets,” as in effect on August 15, 2003.

      (3) Compact audio products may not use more than two watts in standby passive mode for those without a permanently illuminated clock display and four watts in standby passive mode for those with a permanently illuminated clock display, as measured in accordance with International Electrotechnical Commission (IEC) test method 62087:2002(E), “Methods of Measurement for the Power Consumption of Audio, Video, and Related Equipment.”

      (4) Digital versatile disc players and digital versatile disc recorders may not use more than three watts in standby passive mode, as measured in accordance with International Electrotechnical Commission (IEC) test method 62087:2002(E), “Methods of Measurement for the Power Consumption of Audio, Video, and Related Equipment.”

      (5) Portable electric spas manufactured on or after January 1, 2022, must meet the requirements of the American National Standards Institute’s “American National Standard for Portable Electric Spa Energy Efficiency (ANSI/APSP/ICC-14 2019).”

      (6) A television manufactured on or after January 1, 2014, must automatically enter television standby-passive mode after a maximum of 15 minutes without video or audio input on the selected input mode. A television must enter television standby-passive mode when turned off with the remote control unit or via an internal signal. The peak luminance of a television in home mode, or in the default mode as shipped, may not be less than 65 percent of the peak luminance of the retail mode or the brightest selectable preset mode of the television. A television must meet the standards in the following table:

______________________________________________________________________________

 

      Television Standby-           Maximum On Mode    Minimum

      Viewable                            passive Mode               Power Usage (P in               Power

      Screen                                 Power Usage                Watts, A is Viewable           Factor for

      Area                                    (Watts)                         Screen area)                         (P ≥ 100W)

 

      < 1400 sq. in                       1 W                               P ≤ 0.12 x A + 25                 0.9

      ≥ 1400 sq. in                       3 W                               NA                                       NA

______________________________________________________________________________

      (7)(a) Large battery charger systems manufactured on or after January 1, 2014, must meet the minimum efficiencies in the following table:

______________________________________________________________________________

 

Standards for Large Battery Charger Systems

 

 

Performance                                                               Standard

Parameter

 

Charge Return

Factor                               100 percent                        Crf ≤ 1.10

                                         Depth of Discharge

 

                                         80 percent                          Crf ≤ 1.10

                                         Depth of Discharge

 

                                         40 percent                          Crf ≤ 1.15

                                         Depth of Discharge

 

Power Conversion

Efficiency                                                                   ≥ 89 percent

 

Power Factor                                                              ≥ 0.90

 

Battery Maintenance

Mode Power                                                               ≤ 10

+0.0012Eb W

(Eb = battery

capacity of

tested battery)

 

No Battery

Mode Power                                                               ≤ 10 W

______________________________________________________________________________

      (b)(A) As described in subparagraph (B) of this paragraph, inductive charger systems and small battery charger systems must meet the minimum energy efficiency standards in the following table:

______________________________________________________________________________

 

Standards for Inductive and Small Battery Charger Systems

 

Performance                                       Standard

Parameter

 

Maximum 24-hour                              For Eb of 2.5 Wh or less: 16 x N

charge and

maintenance                                       For Eb > 2.5 Wh and

energy (Wh)                                       ≤ 100 Wh: 12 x N+1.6Eb

(Eb = capacity

of all batteries in                                 For Eb > 100 Wh and

ports and N =                                      ≤ 1000 Wh: 22 x N+1.5Eb

number of charger

ports)                                                  For Eb > 1000 Wh:

                                                            36.4 x N + 1.486Eb

 

Battery Maintenance                          The sum of battery maintenance mode power and no

Mode Power and No                           battery mode power must be less than or equal to:

Battery Mode Power (W)                   1 x N+0.0021xEb

 

Power Factor (Eb = capacity

of all batteries in ports and

N = number of charger ports)

______________________________________________________________________________

 

      (B) The requirements in subparagraph (A) of this paragraph must be met by:

      (i) Small battery charger systems for sale at retail that are not USB charger systems with a battery capacity of 20 watt-hours or more and that are manufactured on or after January 1, 2014.

      (ii) Small battery charger systems for sale at retail that are USB charger systems with a battery capacity of 20 watt-hours or more and that are manufactured on or after January 1, 2014.

      (iii) Small battery charger systems that are not sold at retail that are manufactured on or after January 1, 2017.

      (iv) Inductive charger systems manufactured on or after January 1, 2014, unless the inductive charger system uses less than one watt in battery maintenance mode, less than one watt in no battery mode and an average of one watt or less over the duration of the charge and battery maintenance mode test.

      (v) Battery backups and uninterruptible power supplies, manufactured on or after January 1, 2014, for small battery charger systems for sale at retail, which may not consume more than 0.8+ (0.0021xEb) watts in battery maintenance mode, where (Eb) is the battery capacity in watt-hours.

      (vi) Battery backups and uninterruptible power supplies, manufactured on or after January 1, 2017, for small battery charger systems not sold at retail, which may not consume more than 0.8+ (0.0021xEb) watts in battery maintenance mode, where (Eb) is the battery capacity in watt-hours.

      (C) The requirements in subparagraph (A) of this paragraph do not need to be met by an à la carte charger that is:

      (i) Provided separately from and subsequent to the sale of a small battery charger system described in this paragraph;

      (ii) Necessary as a replacement for, or as a replacement component of, a small battery charger system; and

      (iii) Provided by a manufacturer directly to a consumer or to a service or repair facility.

      (8) A high light output double-ended quartz halogen lamp manufactured on or after January 1, 2016, must have a minimum efficiency of:

      (a) 27 lumens per watt for lamps with a minimum rated initial lumen value of greater than 6,000 lumens and a maximum initial lumen value of 15,000 lumens; or

      (b) 34 lumens per watt for lamps with a rated initial lumen value of greater than 15,000 and less than 40,000 lumens.

      (9) High CRI fluorescent lamps manufactured on or after January 1, 2023, must meet or exceed the lamp efficacy standards contained in 10 C.F.R. 430.32(n)(4), as in effect on January 1, 2020.

      (10) Computers and computer monitors manufactured on or after January 1, 2022, must meet the requirements contained in the California Code of Regulations, Title 20, section 1605.3(v), as adopted on May 10, 2017, and amended on November 8, 2017.

      (11) The following plumbing fittings manufactured on or after January 1, 2022, must meet the requirements in the California Code of Regulations, Title 20, section 1605.3(h), as in effect on January 1, 2020:

      (a) Lavatory faucets and lavatory replacement aerators;

      (b) Kitchen faucets and kitchen replacement aerators;

      (c) Public lavatory faucets; and

      (d) Showerheads.

      (12) Commercial fryers manufactured on or after January 1, 2022, and included in the scope of the United States Environmental Protection Agency’s “Energy Star Program Requirements Product Specification for Commercial Fryers, Version 2.0,” must meet the qualification criteria, testing requirements and other requirements of that specification.

      (13) Commercial dishwashers manufactured on or after January 1, 2022, and included in the scope of the United States Environmental Protection Agency’s “Energy Star Program Requirements Product Specification for Commercial Dishwashers, Version 2.0,” must meet the qualification criteria, testing requirements and other requirements of that specification.

      (14) Commercial steam cookers manufactured on or after January 1, 2022, and included in the scope of the United States Environmental Protection Agency’s “Energy Star Program Requirements Product Specification for Commercial Steam Cookers, Version 1.2,” must meet the qualification criteria, testing requirements and other requirements of that specification.

      (15) Residential ventilating fans manufactured on or after January 1, 2022, and included in the scope of the United States Environmental Protection Agency’s “Energy Star Program Requirements Product Specification for Residential Ventilating Fans, Version 3.2,” must meet the qualification criteria, testing requirements and other requirements of that specification.

      (16)(a) Electric storage water heaters manufactured on or after January 1, 2022, must have a modular demand response communications port compliant with:

      (A) The March 2018 version of the ANSI/CTA-2045-A communication interface standard or a standard determined by the Director of the State Department of Energy to be equivalent; and

      (B) The March 2018 version of the ANSI/CTA-2045-A application layer requirements.

      (b) A request that the director determine that a communication interface standard is equivalent to the March 2018 version of the ANSI/CTA-2045-A communication interface standard under paragraph (a)(A) of this subsection must be made in the manner prescribed by the director by rule.

      (17) Spray sprinkler bodies manufactured on or after January 1, 2023, and included in the scope of the United States Environmental Protection Agency’s “WaterSense Specification for Spray Sprinkler Bodies, Version 1.0,” must include an integral pressure regulator and meet the water efficiency and performance criteria and other requirements of that specification. [2005 c.437 §5; 2007 c.375 §§2,3; 2007 c.649 §2; 2013 c.418 §§3,4; 2015 c.276 §§1,2; 2021 c.108 §2; 2022 c.4 §2]

 

      Note: See note under 469.229.

 

      469.234 [1989 c.926 §§5,9; 1993 c.617 §4; repealed by 1999 c.880 §2]

 

      469.235 [2007 c.375 §4; repealed by 2021 c.108 §7]

 

      469.236 [1989 c.926 §6; repealed by 1999 c.880 §2]

 

      469.238 Sale of products not meeting standards prohibited; exemptions. (1) Except as provided in subsection (2) of this section, a person may not sell or offer for sale a new bottle-type water dispenser, commercial hot food holding cabinet, compact audio product, digital versatile disc player, digital versatile disc recorder, portable electric spa, television, inductive charger system, large battery charger system, small battery charger system, high light output double-ended quartz halogen lamp, high color-rendering index fluorescent lamp, computer, computer monitor, lavatory faucet, kitchen faucet, public lavatory faucet, lavatory replacement aerator, kitchen replacement aerator, showerhead, commercial fryer, commercial steam cooker, commercial dishwasher, residential ventilation fan, electric storage water heater or spray sprinkler body unless the energy efficiency of the new product meets or exceeds the minimum energy efficiency standards specified in ORS 469.233.

      (2) A person may sell or offer for sale a new product not meeting efficiency standards specified in subsection (1) of this section if the product is:

      (a) Manufactured in this state and sold outside this state;

      (b) Manufactured outside this state and sold at wholesale inside this state for final retail sale and installation outside this state;

      (c) Installed in a mobile or manufactured home at the time of construction; or

      (d) Designed expressly for installation and use in recreational vehicles. [2005 c.437 §§2,3,4; 2007 c.649 §3; 2013 c.418 §§5,6; 2021 c.108 §3; 2022 c.4 §3]

 

      Note: See note under 469.229.

 

      469.239 Installation of products not meeting standards prohibited; exemptions. (1) Except as provided in subsection (2) of this section, a person may not install a new bottle-type water dispenser, commercial hot food holding cabinet, compact audio product, digital versatile disc player, digital versatile disc recorder, portable electric spa, television, inductive charger system, large battery charger system, small battery charger system, high light output double-ended quartz halogen lamp, high color-rendering index fluorescent lamp, computer, computer monitor, commercial fryer, commercial steam cooker, commercial dishwasher, residential ventilation fan or spray sprinkler body for compensation unless the energy efficiency of the new product meets or exceeds the minimum energy efficiency standards specified in ORS 469.233.

      (2) A person may install a new product not meeting efficiency standards specified in subsection (1) of this section if the product is:

      (a) Installed in a mobile or manufactured home at the time of construction; or

      (b) Designed expressly for installation and use in recreational vehicles. [2005 c.437 §6; 2005 c.437 §7; 2007 c.649 §4; 2013 c.418 §§7,8; 2021 c.108 §4; 2022 c.4 §4]

 

      Note: See note under 469.229.

 

      469.240 [1989 c.926 §§11,12; repealed by 1999 c.880 §2]

 

      469.241 [1993 c.617 §22; repealed by 1999 c.880 §2]

 

      469.242 [1993 c.617 §20; repealed by 1999 c.880 §2]

 

      469.243 [1993 c.617 §21; repealed by 1999 c.880 §2]

 

      469.244 [1989 c.926 §§16,25; repealed by 1993 c.617 §28]

 

      469.245 [1993 c.617 §19; repealed by 1999 c.880 §2]

 

      469.246 [1989 c.926 §§13,18; 1991 c.67 §135; 1993 c.617 §5; repealed by 1999 c.880 §2]

 

      469.247 [1993 c.617 §16; repealed by 1999 c.880 §2]

 

      469.248 [1989 c.926 §39; 1991 c.67 §136; 1993 c.617 §6; repealed by 1999 c.880 §2]

 

      469.249 [1993 c.617 §18; repealed by 1999 c.880 §2]

 

      469.250 [1989 c.926 §§7,8; 1991 c.67 §137; repealed by 1999 c.880 §2]

 

      469.252 [1989 c.926 §§14,15; repealed by 1993 c.617 §28]

 

      469.253 [1993 c.617 §17; repealed by 1999 c.880 §2]

 

      469.254 [1989 c.926 §19; 1993 c.617 §7; 1997 c.838 §6; repealed by 1999 c.880 §2]

 

      469.255 Manufacturers to test products; test methods; certification of products; rules. (1) A manufacturer of a product specified in ORS 469.238 that is sold or offered for sale, or installed or offered for installation, in this state shall test samples of the manufacturer’s products in accordance with the test methods specified in ORS 469.233 or, if more stringent, those specified in the state building code.

      (2) If the test methods for products required to be tested under this section are not provided for in ORS 469.233 or in the state building code, the State Department of Energy shall adopt test methods for these products. The department shall use test methods approved by the United States Department of Energy or, in the absence of federal test methods, other appropriate nationally recognized test methods for guidance in adopting test methods. The State Department of Energy may periodically review and revise its test methods.

      (3) A manufacturer of a product regulated pursuant to ORS 469.229 to 469.261 shall certify to the State Department of Energy that the products are in compliance with the minimum energy efficiency standards specified in ORS 469.233. The department shall establish rules governing the certification of these products and may coordinate with the certification and testing programs of other states and federal agencies with similar standards.

      (4)(a) The department shall establish rules governing the identification of the products that comply with the minimum energy efficiency standards specified in ORS 469.233. The rules shall be coordinated to the greatest extent practicable with the labeling programs of other states and federal agencies with equivalent efficiency standards.

      (b) Identification required under paragraph (a) of this subsection shall be by means of a mark, label or tag on the product and packaging at the time of sale or installation.

      (c) The department shall waive marking, labeling or tagging requirements for products marked, labeled or tagged in compliance with federal requirements or for products certified pursuant to subsection (3) of this section, unless the department determines that state marking, labeling or tagging is required to provide adequate energy efficiency information to the consumer. [2005 c.437 §9; 2007 c.375 §6; 2007 c.649 §5a; 2021 c.108 §5]

 

      Note: See note under 469.229.

 

      469.256 [1989 c.926 §29; repealed by 1993 c.617 §29]

 

      469.258 [1989 c.926 §20; 1991 c.641 §6; repealed by 1999 c.880 §2]

 

      469.259 [1991 c.641 §2; 1993 c.617 §8; repealed by 1999 c.880 §2]

 

      469.260 [1989 c.926 §21; 1991 c.67 §138; repealed by 1999 c.880 §2]

 

      469.261 Department to review standards; rules; postponement of operative dates of standards; application for waiver of federal preemption. (1) The State Department of Energy shall periodically review the minimum energy efficiency standards specified in ORS 469.233.

      (2)(a) After the review pursuant to subsection (1) of this section and notwithstanding ORS 469.233, the Director of the State Department of Energy may adopt rules to update the minimum energy efficiency standards specified in ORS 469.233 if the director determines that the standards need to be updated:

      (A) To promote energy conservation in the state;

      (B) To achieve cost-effectiveness for consumers; or

      (C) Due to federal action or to the outcome of collaborative consultations with manufacturers and the energy departments of other states.

      (b)(A) In addition to the rules adopted under paragraph (a) of this subsection, the director may postpone by rule the operative date of any of the minimum energy efficiency standards specified in ORS 469.233 if the director determines that:

      (i) Adjoining states with similar minimum energy efficiency standards have postponed the operative date of their corresponding minimum energy efficiency standards; or

      (ii) Failure to modify the operative date of any of the minimum energy efficiency standards would impose a substantial hardship on manufacturers, retailers or the public.

      (B)(i) The director may not postpone the operative date of a minimum energy efficiency standard under subparagraph (A) of this paragraph for more than one year.

      (ii) If at the end of the first postponement period the director determines that adjoining states have further postponed the operative date of minimum energy efficiency standards and the requirements of subparagraph (A) of this paragraph continue to be met, the director may postpone the operative date for not more than one additional year.

      (c) After the review pursuant to subsection (1) of this section, the director may adopt rules to establish new minimum energy efficiency standards if the director determines that new standards are needed:

      (A) To promote energy conservation in the state;

      (B) To achieve cost-effectiveness for consumers; or

      (C) Due to federal action or to the outcome of collaborative consultations with manufacturers and the energy departments of other states.

      (d) If the director adopts rules under paragraph (a) of this subsection to update the minimum energy efficiency standards specified in ORS 469.233 or under paragraph (c) of this subsection to establish new minimum energy efficiency standards:

      (A) The rules may not take effect until one year following their adoption by the director; and

      (B) The Governor shall cause to be introduced at the next Legislative Assembly a bill to conform the statutory minimum energy efficiency standards to the minimum energy efficiency standards adopted by the director by rule.

      (3) Notwithstanding ORS 469.229 and 469.233 and the requirements of subsection (2) of this section, and after consultation with the appropriate advisory boards to the Department of Consumer and Business Services, the director may adopt rules to update the minimum energy efficiency standards or test methods specified in ORS 469.233 to a more recent version, including any product definitions associated with the standard or test method, if the director determines that the standard or test method needs to be updated to maintain or improve consistency with other comparable standards in other states. Rules adopted under this subsection shall take effect on or after the effective date of a similar standard or test method adopted by another state.

      (4) If the director determines that implementation of a state minimum energy efficiency standard requires a waiver of federal preemption, the director shall apply for a waiver of federal preemption pursuant to 42 U.S.C. 6297(d). [2005 c.437 §8; 2007 c.375 §7; 2007 c.649 §6a; 2021 c.108 §6]

 

      Note: See note under 469.229.

 

      469.262 [1989 c.926 §24; repealed by 1999 c.880 §2]

 

      469.267 [1989 c.926 §26; 1993 c.617 §9; repealed by 1999 c.880 §2]

 

      469.269 [1989 c.926 §27; 1993 c.617 §10; repealed by 1999 c.880 §2]

 

      469.270 [1989 c.926 §28; 1991 c.67 §139; repealed by 1993 c.617 §29]

 

      469.274 [1989 c.926 §§31,32; 1991 c.641 §7; 1993 c.617 §11; repealed by 1999 c.880 §2]

 

ENERGY PERFORMANCE STANDARDS FOR COVERED COMMERCIAL BUILDINGS

 

      469.275 Definitions for ORS 469.275 to 469.291. As used in ORS 469.275 to 469.291:

      (1)(a) “Agricultural building” means a structure that is used for:

      (A) Storing, maintaining or repairing farm or forestry machinery and equipment;

      (B) Raising, harvesting and selling crops or forest products;

      (C) Feeding, breeding, managing and selling livestock, poultry, fur-bearing animals or honeybees or the produce of livestock, poultry, fur-bearing animals or honeybees;

      (D) Dairying and selling dairy products; or

      (E) Any other agricultural, forestry or horticultural use or animal husbandry, or any combination of agricultural, horticultural or animal husbandry uses, including preparing and storing produce raised on the farm for human use and animal use, preparing, processing and storing agricultural and forestry products and goods and disposing, by marketing or otherwise, of farm produce or forest products.

      (b) “Agricultural building” does not include:

      (A) A dwelling;

      (B) A structure used for a purpose other than growing plants in which 10 or more persons are present at any one time;

      (C) A structure regulated by the State Fire Marshal pursuant to ORS chapter 476;

      (D) A structure used by the public; or

      (E) A structure that is subject to the National Flood Insurance Act of 1968 (42 U.S.C 4001 to 4127), as amended, and regulations promulgated under that Act.

      (2) “Conditional compliance” means a temporary method that a building owner can use to demonstrate that the building owner has implemented required energy use reduction strategies when the building owner cannot demonstrate full compliance with a required energy use intensity target.

      (3) “Covered commercial building” means a tier 1 building or a tier 2 building.

      (4) “Eligible building owner” means:

      (a) An owner of a tier 1 building that must comply with the standard established in ORS 469.277; or

      (b) An owner of a tier 2 building.

      (5) “Energy” means:

      (a) Electricity, including electricity that is delivered through the electric grid and electricity that is generated at a building site using solar or wind energy resources;

      (b) Natural gas;

      (c) Steam, hot water or chilled water used for heating or cooling;

      (d) Propane;

      (e) Fuel oil;

      (f) Wood;

      (g) Coal; or

      (h) Any other fuel that meets a covered commercial building’s energy load.

      (6) “Energy use intensity” means a measurement that weather normalizes a building’s site energy use relative to the building’s size, calculated by dividing the total net energy the building consumes in one year by the building’s gross floor area, excluding any parking garage, and that is reported in thousands of British thermal units per square foot per year.

      (7) “Energy use intensity target” means a net energy use intensity that complies with the standard set forth in ORS 469.277.

      (8) “Greenhouse gas” has the meaning given that term in ORS 468A.210.

      (9)(a) “Gross floor area” means the total number of square feet of a building, measured from the exterior surfaces of a building’s fixed enclosing walls, including all floor space used as offices, lobbies, restrooms, equipment storage areas, mechanical rooms, break rooms and elevator shafts.

      (b) “Gross floor area” does not include bays or docks outside the building.

      (10) “Net energy use” means the sum of metered and bulk fuel energy that enters a building, minus the sum of metered energy that leaves the building.

      (11) “Savings to investment ratio” means the ratio of the total present value of savings to the total present value of costs to implement an energy conservation measure or water conservation measure, in which the numerator of the ratio is the present value of net savings in energy or water or in maintenance costs not related to fuel use or water use that are attributable to the energy conservation measure or water conservation measure and the denominator of the ratio is the present value of the net increase in investment and replacement costs, less the salvage value, of the energy conservation or water conservation measure.

      (12) “Semiheated space” means an enclosed space within a covered commercial building that is heated by a heating system with an output the Department of Consumer and Business Services specifies in an applicable specialty code.

      (13) “Tier 1 building” means a building in which the sum of gross floor area for hotel, motel and nonresidential use equals or exceeds 35,000 square feet, excluding any parking garage.

      (14)(a) “Tier 2 building” means:

      (A) A building with gross floor area, excluding any parking garage, that equals or exceeds 35,000 square feet and that is used as a multifamily residential building, a hospital, a school, a dormitory or a university building; or

      (B) A building in which the sum of gross floor area for hotel, motel and nonresidential use exceeds 20,000 square feet but does not exceed 35,000 square feet, excluding any parking garage.

      (b) “Tier 2 building” does not include a covered commercial building that is classified as a tier 1 building.

      (15) “Unconditioned space” means an enclosed space within a covered commercial building that is not:

      (a) Heated by a heating system or cooled by a cooling system with output capacities the Department of Consumer and Business Services specifies in an applicable specialty code; or

      (b) Indirectly heated or cooled in accordance with standards the department specifies in an applicable specialty code.

      (16) “Weather normalized” means a method for modifying a building’s energy use intensity in a specific year to account for deviations from the building’s energy use intensity as the energy use intensity ordinarily occurs during a year in which the weather does not fluctuate substantially or vary as a consequence of extreme weather events. [2023 c.442 §8]

 

      Note: 469.275 to 469.291 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.276 [1989 c.926 §33; repealed by 1999 c.880 §2]

 

      469.277 Department adoption of performance standards; enforcement; rules. (1)(a) Not later than December 31, 2024, the State Department of Energy, in consultation with the Department of Consumer and Business Services, shall adopt rules that use the American National Standards Institute’s standards for Energy Efficiency in Existing Buildings (ANSI/ASHRAE/IES Standard 100) as an initial model for specifying an energy performance standard for covered commercial buildings. In rulemaking proceedings to adopt or update rules under this paragraph, the State Department of Energy shall disclose the sources of information, including the model described in this paragraph and any peer-reviewed science, that the department relies on in developing or updating the energy performance standard. The department shall update the energy performance standard not later than July 1, 2029, and by the same month and day in each successive period of five years.

      (b) The energy performance standard described in paragraph (a) of this subsection must:

      (A) Comply with the requirements of ORS 469.275 to 469.279;

      (B) Seek to maximize reductions in greenhouse gas emissions from covered commercial buildings;

      (C) Include energy use intensity targets that apply to specific types of buildings; and

      (D) Provide for methods to achieve conditional compliance with an applicable energy use intensity target, which must, at a minimum, require:

      (i) Preparing an energy management plan;

      (ii) Developing a program for building operations and maintenance that aims at achieving the applicable energy use intensity target;

      (iii) Making investments in energy use efficiency measures that aim at achieving the applicable energy use intensity target; and

      (iv) Submitting to energy use audits, which may be based upon or linked to ASHRAE Standard 211 audits.

      (c) Adoption of the energy performance standard described in paragraph (a) of this subsection does not change eligibility criteria for, or benefits or incentives available under, other programs for energy efficiency demand response.

      (2)(a) In adopting the energy performance standard described in subsection (1) of this section, the department:

      (A) Shall:

      (i) Develop energy use intensity targets that are not more stringent than the average energy use intensity for each covered commercial building occupancy classification, adjusting as necessary for a covered commercial building’s unique energy-using features;

      (ii) Consider, for the purpose of establishing energy use intensity targets, regional and local data that identifies building energy use, such as existing benchmarking data from the Energy Star program established under 42 U.S.C. 6294a;

      (iii) Consider, for the purpose of establishing the energy performance standard, federal and local programs that relate to energy efficiency standards, aligning where possible requirements under the energy performance standard to avoid duplicative work by regulators and eligible building owners;

      (iv) Develop energy use intensity targets for two or more climate zones that represent energy use in a year with normal weather;

      (v) Develop energy use intensity targets that exclude energy delivered through electric vehicle supply equipment; and

      (vi) Adopt a conditional compliance method that:

      (I) Requires eligible building owners of covered commercial buildings that do not meet an energy use intensity target to take action to reduce energy use; and

      (II) Specifies investment criteria that meet the requirements set forth in paragraph (b) of this subsection and that ensure progress toward meeting the energy use intensity target; and

      (B) May:

      (i) Consider building occupancy classifications set forth in ANSI/ASHRAE/IES Standard 100 and the United States Environmental Protection Agency’s Energy Star portfolio manager;

      (ii) Base energy use intensity targets for recently constructed covered commercial buildings on statewide energy codes that were in effect at the time the covered commercial building was constructed; and

      (iii) Require utilities, eligible building owners and other entities to aggregate data for covered commercial buildings that have multiple meters and to report or, as appropriate, provide the aggregated data for reports under ORS 469.279.

      (b)(A) Investment criteria the department specifies as part of a conditional compliance method under paragraph (a) of this subsection must:

      (i) Ensure that an eligible building owner meets the covered commercial building’s energy use intensity target by implementing energy efficiency measures identified in energy use audits; and

      (ii) Except as provided in subparagraph (B) of this paragraph, require an eligible building owner to implement an optimized bundle of energy efficiency measures that provide maximum energy savings without resulting in a savings to investment ratio of less than 1.0 or require the eligible building owner to achieve the energy use intensity target by means of an implementation plan that:

      (I) Is based on an energy use audit and life-cycle cost analysis from ANSI/ASHRAE/IES Standard 211 that accounts for the period during which a bundle of energy efficiency measures provide savings;

      (II) Reflects the eligible building owner’s net costs of implementing energy efficiency measures, excluding any costs that utility or government grants cover;

      (III) Allows an exclusion of energy efficiency measures that do not pay back the cost of the energy efficiency measure over the useful life of the energy efficiency measure;

      (IV) Allows an exclusion of energy efficiency measures that are excluded under subparagraph (B) of this paragraph; and

      (V) Allows for phased implementation in which an eligible building owner need not replace a system or equipment before the useful life of the system or equipment ends.

      (B) An eligible building owner need not meet an energy efficiency requirement that would compromise the historical integrity of a covered commercial building or part of a covered commercial building that:

      (i) Is listed on a state or national register of historic places;

      (ii) Is designated as an historic property under a state or local statute, ordinance, rule or other legislative act or a survey conducted under a statute, ordinance, rule or other legislative act;

      (iii) Is certified as a contributing resource within a historic district that is listed on a national register or is locally designated as a historic district; or

      (iv) A state historic preservation officer or the keeper of the national register of historic places has determined in an opinion or certification is eligible to be listed on the national or state register of historic places either as an individual building or as a building that contributes to a historic district.

      (3) The department shall create a database of eligible building owners and covered commercial buildings that are subject to the requirements of ORS 469.275 to 469.279 based on records the department obtains from each county assessor and on other information available to the department.

      (4)(a) Not later than July 1, 2025, the department shall notify eligible building owners of the requirement to comply with the provisions set forth for tier 1 buildings in ORS 469.275 to 469.279.

      (b) The department may approve an eligible building owner’s use of a conditional compliance method in lieu of full compliance with an energy use intensity target if the department determines that the eligible building owner has the capacity to take the actions and make the investments required under the conditional compliance method and otherwise qualifies to use the conditional compliance method.

      (5) A municipality, as defined in ORS 455.010, may by ordinance, rule or land use process, adopt an energy performance standard and greenhouse gas emission reduction standards that are more stringent, or that have broader application, than the energy performance standard that the department adopts under this section, provided:

      (a) The standard does not exceed the energy efficiency requirements of the state building code for new buildings, except where permitted under ORS 455.040;

      (b) The standard does not apply to buildings that are less than six years old, measured from the date of the building’s certificate of occupancy; and

      (c) The municipality cooperates with the department in aligning, where practicable, the energy performance standard the municipality adopts with the energy performance standard the department adopts under this section.

      (6) Construction work performed to comply with the provisions of ORS 469.275 to 469.279 must comply with all applicable provisions of the state building code and permitting procedures that apply to the construction work.

      (7) Except as provided in subsection (5) of this section, this section does not affect or supersede the provisions of ORS 455.040. [2023 c.442 §9]

 

      Note: See note under 469.275.

 

      469.278 [1989 c.926 §34; repealed by 1999 c.880 §2]

 

      469.279 Tier 1 buildings report; exemptions; department support program; correction notice; civil penalties. (1) An eligible building owner of a tier 1 building shall report to the State Department of Energy concerning the eligible building owner’s compliance with the energy performance standard described in ORS 469.277. The eligible building owner shall submit the report in accordance with the schedule specified in subsection (4) of this section and shall submit a new report at the end of every successive five-year period. Each report the eligible building owner submits must include documentation that demonstrates that:

      (a) The tier 1 building’s weather normalized energy use intensity during the previous calendar year is less than or equal to the applicable energy use intensity target;

      (b) The eligible building owner is taking actions and making investments in accordance with a conditional compliance method the department approved; or

      (c) The tier 1 building is exempt from an energy performance standard that otherwise would apply to the tier 1 building because:

      (A) The tier 1 building did not have a certificate of occupancy or temporary certificate of occupancy during all of the 12 months that preceded the date on which the eligible building owner’s report is due;

      (B) The tier 1 building did not have an actual rate of occupancy that exceeded 50 percent of the tier 1 building’s capacity during all of the 12 months that preceded the date on which the eligible building owner’s report is due;

      (C) The sum of the tier 1 building’s gross floor area, minus unconditioned spaces and semiheated spaces, is less than 35,000 square feet;

      (D) The primary use for the tier 1 building is manufacturing or another industrial use, as defined in accordance with the following use designations of the International Building Code:

      (i) Factory group F; or

      (ii) High hazard group H;

      (E) The tier 1 building is an agricultural building; or

      (F) The eligible building owner or the tier 1 building has undergone or is undergoing financial hardship, as measured in accordance with the following criteria:

      (i) Within the 24 months that precede the date on which the eligible building owner’s report is due, a city or county listed the tier 1 building on the city’s or county’s annual tax lien sale list because of arrears in property taxes or water or wastewater charges;

      (ii) A court appointed receiver controls the tier 1 building because of financial distress;

      (iii) A financial institution owns the tier 1 building because of a borrower’s default;

      (iv) Within the 24 months that precede the date on which the eligible building owner’s report is due, the eligible building owner acquired the tier 1 building by means of a deed in lieu of foreclosure;

      (v) The tier 1 building has a senior mortgage that is subject to a notice of default; or

      (vi) Other criteria that the department specifies by rule as indicative of financial hardship.

      (2) The department shall develop methods and procedures for administering reports that eligible building owners of tier 1 buildings submit to the department under subsection (1) of this section.

      (3)(a) The department shall provide a support program to eligible building owners of covered commercial buildings that includes, at a minimum, information and periodic training, technical assistance and telephone and electronic mail support that will assist eligible building owners in complying with the energy performance standard, applicable energy use intensity targets and reporting requirements under ORS 469.275 to 469.279.

      (b) As part of the support program described in paragraph (a) of this subsection, the department may encourage eligible building owners to seek for maintenance staff accreditation from the U.S. Green Building Council’s Green Janitors Education Program.

      (4) An eligible building owner must comply with the energy performance standard adopted under ORS 469.277 by the following dates:

      (a) If the eligible building owner’s tier 1 building has a gross floor area of 200,000 square feet or more, not later than June 1, 2028;

      (b) If the eligible building owner’s tier 1 building has a gross floor area of 90,000 square feet or more but less than 200,000 square feet, not later than June 1, 2029; and

      (c) If the eligible building owner’s tier 1 building has a gross floor area of 35,000 square feet or more but less than 90,000 square feet, not later than June 1, 2030.

      (5)(a) The department shall notify an eligible building owner of a tier 1 building of a failure to comply with ORS 469.275 to 469.279 if the eligible building owner fails to:

      (A) Submit the report described in subsection (1) of this section by the date required or in a form and manner the department requires;

      (B) Meet the energy performance standard or an applicable energy use intensity target or, in lieu of meeting the standard or target, fails to obtain the department’s approval to use a conditional compliance method;

      (C) Provide accurate reporting that meets the requirements of ORS 469.275 to 469.279; or

      (D) Demonstrate as provided in subsection (1)(c) of this section that the eligible building owner is exempt from an otherwise applicable energy performance standard.

      (b) In the notice described in paragraph (a) of this subsection, the department may specify a date by which the eligible building owner of a tier 1 building must correct the failure the department identified in the notice. In addition, the department shall specify the date by which the eligible building owner’s failure to comply or failure to correct a lack of compliance will subject the eligible building owner to a civil penalty under subsection (6) of this section.

      (c) At an eligible building owner’s request, the department shall cite the specific legal authority upon which the department relied as a basis for issuing a notice to the eligible building owner under paragraph (a) of this subsection.

      (6)(a) The department may impose a civil penalty as provided in ORS 183.745 upon an eligible building owner of a tier 1 building to which the department issued a notice under subsection (5) of this section if the department determines that the eligible building owner:

      (A) Has not complied with the requirement set forth in the notice or has not corrected a lack of compliance by the date for correction that the department specifies in the notice; or

      (B) Otherwise violated a provision of ORS 469.275 to 469.279 or a rule the department adopted under ORS 469.275 to 469.279.

      (b) A civil penalty the department imposes under paragraph (a) of this subsection may not exceed $5,000 plus an amount for the duration of a continuing violation, which may not exceed a daily amount that the department calculates by multiplying $1 per year per square foot of gross floor area of the tier 1 building that is the subject of the department’s notice.

      (c) The department shall deposit the proceeds of any civil penalty the department imposes and collects under this subsection into the State Department of Energy Account established under ORS 469.120 and shall allocate the proceeds for the purpose of administering the department’s energy efficiency programs. [2023 c.442 §10]

 

      Note: See note under 469.275.

 

      469.280 [1989 c.926 §35; repealed by 1999 c.880 §2]

 

      469.281 Implementation; enforcement; advisory committee; rules. (1) In addition to the energy performance standard the State Department of Energy adopts in accordance with ORS 469.277, the department shall adopt rules to implement ORS 469.275 to 469.279. The rules must:

      (a) Ensure timely, accurate and complete reporting of compliance with the requirements of ORS 469.275 to 469.279 from all tier 1 buildings;

      (b) Enable the department to effectively enforce the energy performance standard and energy use intensity targets established under ORS 469.275 to 469.279;

      (c) Provide means for affected eligible building owners of tier 1 buildings to appeal decisions and enforcement actions of the department that affect the eligible building owner; and

      (d) Ensure that an eligible building owner of a tier 1 building is responsible for paying the costs of compliance with ORS 469.275 to 469.279.

      (2) Before adopting rules under this section, the department shall establish and consult an advisory committee that includes representatives of eligible building owners, tenants of covered commercial buildings, public utilities, organizations with experience in designing or implementing energy efficiency programs, local governments, organizations that focus on environmental justice and other stakeholders the department identifies as needing representation. The department shall consult with the advisory committee before amending rules the department adopts under this section. [2023 c.442 §11]

 

      Note: See note under 469.275.

 

      469.282 [1989 c.926 §36; repealed by 1999 c.880 §2]

 

      469.283 County assessors to provide information to department. At the request of the State Department of Energy, each county assessor in this state shall provide information from existing records data that the department requires to implement ORS 469.275 to 469.279, including information about covered commercial buildings within the county. [2023 c.442 §12]

 

      Note: See note under 469.275.

 

      Note: Section 13, chapter 442, Oregon Laws 2023, provides:

      Sec. 13. Annual report on implementation of energy performance standards. The State Department of Energy shall report not later than January 15, 2025, and by the same date in each succeeding year until 2035, to the Governor and to committees of the Legislative Assembly that are related to the environment concerning the implementation of the energy performance standard established under section 9 of this 2023 Act [469.277]. The report must include information about the department’s adoption of the ANSI/ASHRAE/IES Standard 100 as the department’s initial model for the energy performance standard, the financial impact the standard has had on eligible building owners of tier 1 buildings, the amount of any incentives the department provided for compliance and any other information that is relevant to the department’s implementation of sections 8 to 10 of this 2023 Act [469.275 to 469.279]. [2023 c.442 §13]

 

      469.284 [1989 c.926 §37; repealed by 1999 c.880 §2]

 

      469.285 When action to comply not required; incentives for voluntary or early compliance. (1) ORS 469.275 to 469.279 do not require an eligible building owner to take action to comply with ORS 469.275 to 469.279:

      (a) If the eligible building owner owns a tier 2 building; or

      (b) Before the State Department of Energy adopts an energy performance standard under ORS 469.277, if the eligible building owner owns a tier 1 building.

      (2) The department may offer incentives for eligible building owners to voluntarily comply with, or for early compliance with, ANSI/ASHRAE/IES Standard 100 or the energy performance standard the department establishes under ORS 469.277. [2023 c.442 §14]

 

      Note: See note under 469.275.

 

      469.286 [1989 c.926 §38; 1991 c.67 §140; 1993 c.617 §12; repealed by 1999 c.880 §2]

 

      469.287 Tier 2 buildings; requirement and standards for providing data; advisory committee; rules. (1)(a) Not later than December 31, 2024, the State Department of Energy by rule shall establish a requirement and standards under which eligible building owners of tier 2 buildings must provide to the department data that would enable the department to establish a benchmark for energy use in, and greenhouse gas emissions from, tier 2 buildings.

      (b) The State Department of Energy shall cooperate with the Department of Education to establish a requirement to provide the data described in paragraph (a) of this subsection in a manner that minimizes costs to schools and avoids or minimizes duplication with the Department of Education’s school facility assessments.

      (2) Not later than July 1, 2025, the State Department of Energy shall notify all eligible building owners of tier 2 buildings of the requirement and standards the department adopts by rule under subsection (1) of this section.

      (3) Not later than July 1, 2028, and by July 1 every five years thereafter, an eligible building owner of a tier 2 building shall provide the department with data the department requires in rules the department adopts under subsection (1) of this section.

      (4) Not later than July 1, 2029, the department shall evaluate and use the data the department receives from eligible building owners of tier 2 buildings to calculate average energy use in, and average greenhouse gas emissions from, each of the categories of tier 2 buildings that exist in this state.

      (5) Not later than July 1, 2025, the department shall establish and consult an advisory committee to identify and evaluate the financial and nonfinancial implications of establishing and implementing an energy performance standard for tier 2 buildings. The advisory committee must include, but is not limited to, representatives of renters, low-income tenants and environmental justice communities, as defined in ORS 469A.400.

      (6) Not later than October 1, 2030, the department shall submit a report to the Governor and to an interim committee of the Legislative Assembly related to energy that:

      (a) Recommends a cost-effective energy performance standard for tier 2 buildings; and

      (b) Includes estimates of costs to eligible building owners, and challenges that eligible building owners would face, in implementing an energy performance standard for tier 2 buildings. [2023 c.442 §15]

 

      Note: See note under 469.275.

 

      469.289 Contracting to administer incentive payments for early compliance. (1) As used in this section, “person” means an individual, corporation, nonprofit corporation, professional corporation, limited liability company, partnership, limited partnership, limited liability partnership, cooperative, business trust, joint venture or other form of business entity, including Energy Trust of Oregon.

      (2) The State Department of Energy may contract with another person to administer incentive payments to eligible building owners for early compliance with the energy performance standard described in ORS 469.277.

      (3) The person with which the department contracts under subsection (2) of this section shall administer incentive payments:

      (a) In a manner that is consistent with rules the department adopts under, and for compliance that is consistent with, ORS 469.275 to 469.279; and

      (b) To eligible building owners that the department certifies as qualifying for incentive payments under, and at rates established for the payments in, ORS 469.291.

      (4) A person that administers incentive payments on the department’s behalf:

      (a) Remains subject to any obligations the person has or will have to provide energy efficiency programs or incentives to the person’s customers; and

      (b) Is not liable for excess incentive payments the person makes in reliance on the department’s certification or determination of the proper amount of the incentive payment, if the person is not otherwise responsible for any inaccuracy in the amount of the incentive payment. [2023 c.442 §16]

 

      Note: See note under 469.275.

 

      469.290 [1989 c.926 §23; 1991 c.641 §8; 1993 c.617 §13; repealed by 1999 c.880 §2]

 

      469.291 Incentive program for early and voluntary implementation of standards; application process; rules. (1) The State Department of Energy by rule shall establish a program to pay incentives to eligible building owners that implement ANSI/ASHRAE/IES Standard 100 or the energy performance standard described in ORS 469.277 for covered commercial buildings before adoption and implementation is mandatory. The program must provide for:

      (a) An application process;

      (b) Standards by which the department may qualify an eligible building owner to receive, or disqualify an eligible building owner from receiving, an incentive payment;

      (c) A method for verifying a covered commercial building’s energy consumption with the eligible building owner and the electric utility, gas company or thermal energy company that supplies energy to the covered commercial building for the purpose of qualifying the eligible building owner to receive an incentive payment;

      (d) A process for calculating the amount of any incentive payment;

      (e) An administrative process by which an eligible building owner may appeal the department’s decision to qualify or disqualify the eligible building owner or the department’s determination of the amount of an incentive payment; and

      (f) A process for authorizing incentive payments and notifying eligible building owners and persons that administer incentive payments of the department’s authorization.

      (2) To qualify for an incentive payment, an eligible building owner must report to the department in accordance with ORS 469.279 by the deadlines and for a period of time the department specifies by rule. In addition:

      (a) The eligible building owner must own a tier 1 building that is or will become subject to the requirements of ORS 469.275 to 469.279 or must own a tier 2 building that qualifies as provided in subsection (3) of this section;

      (b) If the covered commercial building is a tier 1 building, the tier 1 building must have a baseline energy use intensity that exceeds an applicable energy use intensity target by at least 15 energy use intensity units; and

      (c) The eligible building owner must comply with any other requirements the department specifies by rule.

      (3) An eligible building owner of a tier 2 building may receive an incentive payment of 35 cents per square foot of gross floor area, excluding any parking garage, unconditioned space or semiheated space if the eligible building owner has submitted to the department, or has agreed to submit to the department in advance of an established deadline, the data described in ORS 469.287.

      (4)(a) Subject to paragraph (c) of this subsection, an eligible building owner that applies and qualifies for an incentive payment under subsection (2) or (3) of this section may receive for meeting the energy performance standard described in ORS 469.277 early or voluntarily an incentive payment of 85 cents per square foot of gross floor area of the eligible building owner’s covered commercial building, excluding any parking garage, unconditioned space or semiheated space.

      (b) The department may authorize additional incentive payments to an eligible building owner that owns a tier 2 multifamily residential building and that enters into a binding agreement not to displace tenants from the multifamily residential building.

      (c) The department may authorize an incentive payment only if funds are available for the payment and contingent upon an eligible building owner’s compliance with the requirements of this section and any rules the department adopts to govern incentive payments.

      (5) Before qualifying an eligible building owner to receive an incentive payment under this section, the department shall review the eligible building owner’s application and verify any report the eligible building owner must provide under ORS 469.279 and any energy consumption the department must measure for the purposes of the qualification. If the department determines that an eligible building owner qualifies for an incentive payment, the department shall certify the qualification to the eligible building owner and to the person that administers incentive payments under ORS 469.289.

      (6) Not later than September 30, 2026, and by the same date every two years thereafter, the department shall report to interim committees of the Legislative Assembly related to energy concerning the operations and results of the incentive program the department establishes under this section. The report must include recommendations for aligning the incentive program with greenhouse gas emission reduction goals that meet or exceed the goals specified in ORS 468A.205. [2023 c.442 §17]

 

      Note: See note under 469.275.

 

      469.292 [1989 c.926 §22; 1991 c.641 §9; repealed by 1999 c.880 §2]

 

      469.296 [1989 c.926 §17; 1993 c.617 §14; repealed by 1999 c.880 §2]

 

      469.298 [1989 c.926 §2; repealed by 1999 c.880 §2]

 

REGULATION OF ENERGY FACILITIES

 

(General Provisions)

 

      469.300 Definitions. As used in ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992, unless the context requires otherwise:

      (1) “Applicant” means any person who makes application for a site certificate in the manner provided in ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992.

      (2) “Application” means a request for approval of a particular site or sites for the construction and operation of an energy facility or the construction and operation of an additional energy facility upon a site for which a certificate has already been issued, filed in accordance with the procedures established pursuant to ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992.

      (3) “Associated transmission lines” means new transmission lines constructed to connect an energy facility to the first point of junction of such transmission line or lines with either a power distribution system or an interconnected primary transmission system or both or to the Northwest Power Grid.

      (4) “Average electric generating capacity” means the peak generating capacity of the facility divided by one of the following factors:

      (a) For wind facilities, 3.00;

      (b) For geothermal energy facilities, 1.11; or

      (c) For all other energy facilities, 1.00.

      (5) “Combustion turbine power plant” means a thermal power plant consisting of one or more fuel-fired combustion turbines and any associated waste heat combined cycle generators.

      (6) “Construction” means work performed on a site, excluding surveying, exploration or other activities to define or characterize the site, the cost of which exceeds $250,000.

      (7) “Council” means the Energy Facility Siting Council established under ORS 469.450.

      (8) “Department” means the State Department of Energy created under ORS 469.030.

      (9) “Director” means the Director of the State Department of Energy appointed under ORS 469.040.

      (10) “Electric utility” means persons, regulated electrical companies, people’s utility districts, joint operating agencies, electric cooperatives, municipalities or any combination thereof, engaged in or authorized to engage in the business of generating, supplying, transmitting or distributing electric energy.

      (11)(a) “Energy facility” means any of the following:

      (A) An electric power generating plant with a nominal electric generating capacity of 25 megawatts or more, including but not limited to:

      (i) Thermal power;

      (ii) Combustion turbine power plant; or

      (iii) Solar thermal power plant.

      (B) A nuclear installation as defined in this section.

      (C) A high voltage transmission line of more than 10 miles in length with a capacity of 230,000 volts or more to be constructed in more than one city or county in this state, but excluding:

      (i) Lines proposed for construction entirely within 500 feet of an existing corridor occupied by high voltage transmission lines with a capacity of 230,000 volts or more;

      (ii) Lines of 57,000 volts or more that are rebuilt and upgraded to 230,000 volts along the same right of way; and

      (iii) Associated transmission lines.

      (D) A solar photovoltaic power generation facility using more than:

      (i) 240 acres located on high-value farmland as defined in ORS 195.300;

      (ii) 2,560 acres located on land that is predominantly cultivated or that, if not cultivated, is predominantly composed of soils that are in capability classes I to IV, as specified by the National Cooperative Soil Survey operated by the Natural Resources Conservation Service of the United States Department of Agriculture; or

      (iii) 3,840 acres located on any other land.

      (E) A pipeline that is:

      (i) At least six inches in diameter, and five or more miles in length, used for the transportation of crude petroleum or a derivative thereof, liquefied natural gas, a geothermal energy form in a liquid state or other fossil energy resource, excluding a pipeline conveying natural or synthetic gas;

      (ii) At least 16 inches in diameter, and five or more miles in length, used for the transportation of natural or synthetic gas, but excluding:

      (I) A pipeline proposed for construction of which less than five miles of the pipeline is more than 50 feet from a public road, as defined in ORS 368.001; or

      (II) A parallel or upgraded pipeline up to 24 inches in diameter that is constructed within the same right of way as an existing 16-inch or larger pipeline that has a site certificate, if all studies and necessary mitigation conducted for the existing site certificate meet or are updated to meet current site certificate standards; or

      (iii) At least 16 inches in diameter and five or more miles in length used to carry a geothermal energy form in a gaseous state but excluding a pipeline used to distribute heat within a geothermal heating district established under ORS chapter 523.

      (F) A synthetic fuel plant which converts a natural resource including, but not limited to, coal or oil to a gas, liquid or solid product intended to be used as a fuel and capable of being burned to produce the equivalent of two billion Btu of heat a day.

      (G) A plant which converts biomass to a gas, liquid or solid product, or combination of such products, intended to be used as a fuel and if any one of such products is capable of being burned to produce the equivalent of six billion Btu of heat a day.

      (H) A storage facility for liquefied natural gas constructed after September 29, 1991, that is designed to hold at least 70,000 gallons.

      (I) A surface facility related to an underground gas storage reservoir that, at design injection or withdrawal rates, will receive or deliver more than 50 million cubic feet of natural or synthetic gas per day, or require more than 4,000 horsepower of natural gas compression to operate, but excluding:

      (i) The underground storage reservoir;

      (ii) The injection, withdrawal or monitoring wells and individual wellhead equipment; and

      (iii) An underground gas storage reservoir into which gas is injected solely for testing or reservoir maintenance purposes or to facilitate the secondary recovery of oil or other hydrocarbons.

      (J) An electric power generating plant with an average electric generating capacity of 50 megawatts or more if the power is produced from geothermal or wind energy at a single energy facility or within a single energy generation area.

      (b) “Energy facility” does not include a hydroelectric facility or an energy facility under paragraph (a)(A)(iii) or (D) of this subsection that is established on the site of a decommissioned United States Air Force facility that has adequate transmission capacity to serve the energy facility.

      (12) “Energy generation area” means an area within which the effects of two or more small generating plants may accumulate so the small generating plants have effects of a magnitude similar to a single generating plant of 35 megawatts average electric generating capacity or more. An “energy generation area” for facilities using a geothermal resource and covered by a unit agreement, as provided in ORS 522.405 to 522.545 or by federal law, shall be defined in that unit agreement. If no such unit agreement exists, an energy generation area for facilities using a geothermal resource shall be the area that is within two miles, measured from the electrical generating equipment of the facility, of an existing or proposed geothermal electric power generating plant, not including the site of any other such plant not owned or controlled by the same person.

      (13) “Extraordinary nuclear occurrence” means any event causing a discharge or dispersal of source material, special nuclear material or by-product material as those terms are defined in ORS 453.605, from its intended place of confinement off-site, or causing radiation levels off-site, that the United States Nuclear Regulatory Commission or its successor determines to be substantial and to have resulted in or to be likely to result in substantial damages to persons or property off-site.

      (14) “Facility” means an energy facility together with any related or supporting facilities.

      (15) “Geothermal reservoir” means an aquifer or aquifers containing a common geothermal fluid.

      (16) “Local government” means a city or county.

      (17) “Nominal electric generating capacity” means the maximum net electric power output of an energy facility based on the average temperature, barometric pressure and relative humidity at the site during the times of the year when the facility is intended to operate.

      (18) “Nuclear incident” means any occurrence, including an extraordinary nuclear occurrence, that results in bodily injury, sickness, disease, death, loss of or damage to property or loss of use of property due to the radioactive, toxic, explosive or other hazardous properties of source material, special nuclear material or by-product material as those terms are defined in ORS 453.605.

      (19) “Nuclear installation” means any power reactor, nuclear fuel fabrication plant, nuclear fuel reprocessing plant, waste disposal facility for radioactive waste, and any facility handling that quantity of fissionable materials sufficient to form a critical mass. “Nuclear installation” does not include any such facilities that are part of a thermal power plant.

      (20) “Nuclear power plant” means an electrical or any other facility using nuclear energy with a nominal electric generating capacity of 25 megawatts or more, for generation and distribution of electricity, and associated transmission lines.

      (21) “Person” means an individual, partnership, joint venture, private or public corporation, association, firm, public service company, political subdivision, municipal corporation, government agency, people’s utility district, or any other entity, public or private, however organized.

      (22) “Project order” means the order, including any amendments, issued by the State Department of Energy under ORS 469.330.

      (23)(a) “Radioactive waste” includes all material which is discarded, unwanted or has no present lawful economic use, and contains mined or refined naturally occurring isotopes, accelerator produced isotopes and by-product material, source material or special nuclear material as those terms are defined in ORS 453.605.

      (b) “Radioactive waste” does not include:

      (A) Materials identified by the council by rule as presenting no significant danger to the public health and safety.

      (B) Uranium mine overburden or uranium mill tailings, mill wastes or mill by-product materials as those terms are defined in Title 42, United States Code, section 2014, on June 25, 1979.

      (24) “Related or supporting facilities” means any structure, proposed by the applicant, to be constructed or substantially modified in connection with the construction of an energy facility, including associated transmission lines, reservoirs, storage facilities, intake structures, road and rail access, pipelines, barge basins, office or public buildings, and commercial and industrial structures. “Related or supporting facilities” does not include geothermal or underground gas storage reservoirs, production, injection or monitoring wells or wellhead equipment or pumps.

      (25) “Site” means any proposed location of an energy facility and related or supporting facilities.

      (26) “Site certificate” means the binding agreement between the State of Oregon and the applicant, authorizing the applicant to construct and operate a facility on an approved site, incorporating all conditions imposed by the council on the applicant.

      (27) “Thermal power plant” means an electrical facility using any source of thermal energy with a nominal electric generating capacity of 25 megawatts or more, for generation and distribution of electricity, and associated transmission lines, including but not limited to a nuclear-fueled, geothermal-fueled or fossil-fueled power plant, but not including a portable power plant the principal use of which is to supply power in emergencies. “Thermal power plant” includes a nuclear-fueled thermal power plant that has ceased to operate.

      (28) “Transportation” means the transport within the borders of the State of Oregon of radioactive material destined for or derived from any location.

      (29) “Underground gas storage reservoir” means any subsurface sand, strata, formation, aquifer, cavern or void, whether natural or artificially created, suitable for the injection, storage and withdrawal of natural gas or other gaseous substances. “Underground gas storage reservoir” includes a pool as defined in ORS 520.005.

      (30) “Utility” includes:

      (a) A person, a regulated electrical company, a people’s utility district, a joint operating agency, an electric cooperative, municipality or any combination thereof, engaged in or authorized to engage in the business of generating, transmitting or distributing electric energy;

      (b) A person or public agency generating electric energy from an energy facility for its own consumption; and

      (c) A person engaged in this state in the transmission or distribution of natural or synthetic gas.

      (31) “Waste disposal facility” means a geographical site in or upon which radioactive waste is held or placed but does not include a site at which radioactive waste used or generated pursuant to a license granted under ORS 453.635 is stored temporarily, a site of a thermal power plant used for the temporary storage of radioactive waste from that plant for which a site certificate has been issued pursuant to this chapter or a site used for temporary storage of radioactive waste from a reactor operated by a college, university or graduate center for research purposes and not connected to the Northwest Power Grid. As used in this subsection, “temporary storage” includes storage of radioactive waste on the site of a nuclear-fueled thermal power plant for which a site certificate has been issued until a permanent storage site is available by the federal government. [Formerly 453.305; 1977 c.796 §1; 1979 c.283 §1; 1981 c.587 §1; 1981 c.629 §2; 1981 c.707 §1; 1981 c.866 §1; 1991 c.480 §4; 1993 c.544 §3; 1993 c.569 §3; 1995 c.505 §6; 1995 c.551 §10; 1997 c.606 §1; 1999 c.365 §5; 2001 c.134 §2; 2001 c.683 §6; 2003 c.186 §28; 2013 c.320 §1; 2019 c.650 §1; 2021 c.38 §1; 2023 c.336 §3]

 

      469.310 Policy. In the interests of the public health and the welfare of the people of this state, it is the declared public policy of this state that the siting, construction and operation of energy facilities shall be accomplished in a manner consistent with protection of the public health and safety and in compliance with the energy policy and air, water, solid waste, land use and other environmental protection policies of this state. It is, therefore, the purpose of ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992 to exercise the jurisdiction of the State of Oregon to the maximum extent permitted by the United States Constitution and to establish in cooperation with the federal government a comprehensive system for the siting, monitoring and regulating of the location, construction and operation of all energy facilities in this state. It is furthermore the policy of this state, notwithstanding ORS 469.010 (2)(f) and the definition of cost-effective in ORS 469.020, that the need for new generating facilities, as defined in ORS 469.503, is sufficiently addressed by reliance on competition in the market rather than by consideration of cost-effectiveness and shall not be a matter requiring determination by the Energy Facility Siting Council in the siting of a generating facility, as defined in ORS 469.503. [Formerly 453.315; 1997 c.428 §1; 2003 c.186 §29]

 

(Siting)

 

      469.320 Site certificate required; exceptions. (1) Except as provided in subsections (2) and (5) of this section, no facility shall be constructed or expanded unless a site certificate has been issued for the site thereof in the manner provided in ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992. No facility shall be constructed or operated except in conformity with the requirements of ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992.

      (2) A site certificate is not required for:

      (a) An energy facility for which no site certificate has been issued that, on August 2, 1993, had operable electric generating equipment for a modification that uses the same fuel type and increases electric generating capacity, if:

      (A) The site is not enlarged; and

      (B) The ability of the energy facility to use fuel for electricity production under peak steady state operating conditions is not more than 200 million Btu per hour greater than it was on August 2, 1993, or the energy facility expansion is called for in the short-term plan of action of an energy resource plan that has been acknowledged by the Public Utility Commission of Oregon.

      (b) Construction or expansion of any interstate natural gas pipeline or associated underground natural gas storage facility authorized by and subject to the continuing regulation of the Federal Energy Regulatory Commission or successor agency.

      (c) An energy facility, except coal and nuclear power plants, if the energy facility:

      (A) Sequentially produces electrical energy and useful thermal energy from the same fuel source; and

      (B) Under average annual operating conditions, has a nominal electric generating capacity:

      (i) Of less than 50 megawatts and the fuel chargeable to power heat rate value is not greater than 6,000 Btu per kilowatt hour;

      (ii) Of 50 megawatts or more and the fuel chargeable to power heat rate value is not greater than 5,500 Btu per kilowatt hour; or

      (iii) Specified by the Energy Facility Siting Council by rule based on the council’s determination relating to emissions of the energy facility.

      (d) Temporary storage, at the site of a nuclear-fueled thermal power plant for which a site certificate has been issued by the State of Oregon, of radioactive waste from the plant.

      (e) An energy facility as defined in ORS 469.300 (11)(a)(G), if the plant also produces a secondary fuel used on site for the production of heat or electricity, if the output of the primary fuel is less than six billion Btu of heat a day.

      (f) An energy facility as defined in ORS 469.300 (11)(a)(G), if the facility:

      (A) Exclusively uses biomass, including but not limited to grain, whey, potatoes, oilseeds, waste vegetable oil or cellulosic biomass, as the source of material for conversion to a liquid fuel;

      (B) Has received local land use approval under the applicable acknowledged comprehensive plan and land use regulations of the affected local government and the facility complies with any statewide planning goals or rules of the Land Conservation and Development Commission that are directly applicable to the facility;

      (C) Requires no new electric transmission lines or gas or petroleum product pipelines that would require a site certificate under subsection (1) of this section;

      (D) Produces synthetic fuel, at least 90 percent of which is used in an industrial or refueling facility located within one mile of the facility or is transported from the facility by rail or barge; and

      (E) Emits less than 118 pounds of carbon dioxide per million Btu from fossil fuel used for conversion energy.

      (g) A standby generation facility, if the facility complies with all of the following:

      (A) The facility has received local land use approval under the applicable acknowledged comprehensive plan and land use regulations of the affected local government and the facility complies with all statewide planning goals and applicable rules of the Land Conservation and Development Commission;

      (B) The standby generators have been approved by the Department of Environmental Quality as having complied with all applicable air and water quality requirements. For an applicant that proposes to provide the physical facilities for the installation of standby generators, the requirement of this subparagraph may be met by agreeing to require such a term in the lease contract for the facility; and

      (C) The standby generators are electrically incapable of being interconnected to the transmission grid. For an applicant that proposes to provide the physical facilities for the installation of standby generators, the requirement of this subparagraph may be met by agreeing to require such a term in the lease contract for the facility.

      (3) The Energy Facility Siting Council may review and, if necessary, revise the fuel chargeable to power heat rate value set forth in subsection (2)(c)(B) of this section. In making its determination, the council shall ensure that the fuel chargeable to power heat rate value for facilities set forth in subsection (2)(c)(B) of this section remains significantly lower than the fuel chargeable to power heat rate value for the best available, commercially viable thermal power plant technology at the time of the revision.

      (4)(a)(A) Any person who proposes to construct or enlarge an energy facility and who claims an exemption under subsection (2)(a), (c) or (f) of this section from the requirement to obtain a site certificate shall request the Energy Facility Siting Council to determine whether the proposed facility qualifies for the claimed exemption.

      (B) The council may not require a person who operates or proposes to construct or enlarge an energy facility to request that the council determine whether the proposed facility qualifies for exemption under subsection (2)(g) of this section.

      (b) The council shall make its determination within 60 days after the request for exemption is filed. An appeal from the council’s determination on a request for exemption shall be made under ORS 469.403, except that the scope of review by the Supreme Court shall be the same as a review by a circuit court under ORS 183.484. The record on review by the Supreme Court shall be the record established in the council proceeding on the exemption.

      (5) Notwithstanding subsection (1) of this section, a separate site certificate shall not be required for:

      (a) Transmission lines, storage facilities, pipelines or similar related or supporting facilities, if such related or supporting facilities are addressed in and are subject to a site certificate for another energy facility;

      (b) Expansion within the site or within the energy generation area of a facility for which a site certificate has been issued, if the existing site certificate has been amended to authorize expansion; or

      (c) Expansion, either within the site or outside the site, of an existing council certified surface facility related to an underground gas storage reservoir, if the existing site certificate is amended to authorize expansion.

      (6) If the substantial loss of the steam host causes a facility exempt under subsection (2)(c) of this section to substantially fail to meet the exemption requirements under subsection (2)(c) of this section, the electric generating facility shall cease to operate one year after the substantial loss of the steam host unless an application for a site certificate has been filed in accordance with the provisions of ORS 469.300 to 469.563.

      (7) As used in this section:

      (a) “Standby generation facility” means an electric power generating facility, including standby generators and the physical structures necessary to install and connect standby generators, that provides temporary electric power in the event of a power outage and that is electrically incapable of being interconnected with the transmission grid.

      (b) “Total energy output” means the sum of useful thermal energy output and useful electrical energy output.

      (c) “Useful thermal energy” means the verifiable thermal energy used in any viable industrial or commercial process, heating or cooling application.

      (8)(a) If the developer of a facility elects, or the governing body of the local government after consulting with the developer elects, to defer regulatory authority to the Energy Facility Siting Council, the developer of a facility shall obtain a site certificate, in the manner provided in ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992, for a facility that, notwithstanding the definition of “energy facility” in ORS 469.300, is:

      (A) An electric power generating plant with an average electric generating capacity of less than 50 megawatts produced from wind energy at a single energy facility or within a single energy generation area;

      (B) An associated transmission line; or

      (C) A solar photovoltaic power generation facility that is not an energy facility as defined in ORS 469.300 (11)(a)(D).

      (b) An election by a developer or a local government under this subsection is final.

      (c) An election by a local government under this subsection is not a land use decision as defined in ORS 197.015.

      (d) A local government may not make an election under this subsection after a permit application has been submitted under ORS 215.416 or 227.175. [Formerly 453.325; 1977 c.86 §1; 1979 c.730 §8; 1982 s.s.1 c.6 §1; 1987 c.200 §5; 1991 c.480 §5; 1993 c.569 §4; 1995 c.505 §7; 1999 c.365 §6; 1999 c.385 §1; 2001 c.134 §§3,4; 2001 c.683 §§7,8; 2003 c.186 §§76,77; 2005 c.768 §§1,2; 2007 c.739 §33; 2009 c.751 §7; 2019 c.650 §2; 2021 c.109 §1]

 

      469.330 Notice of intent to file application for site certificate; public notice; standards, application requirements and study requirements; project order; rules. (1) Each applicant for a site certificate shall submit to the Energy Facility Siting Council a notice of intent to file an application for a site certificate. The notice of intent must provide information about the proposed site and the characteristics of the facility sufficient for the preparation of the State Department of Energy’s project order.

      (2) The council shall cause public notice to be given upon receipt of a notice of intent by the council. The public notice shall provide a description of the proposed site and facility in sufficient detail to inform the public of the location and proposed use of the site.

      (3) Following review of the notice of intent and any public comments received in response to the notice of intent, the department may hold a preapplication conference with state agencies and local governments that have regulatory or advisory responsibility with respect to the facility. After the preapplication conference, the department shall issue a project order establishing the statutes, administrative rules, council standards, local ordinances, application requirements and study requirements for the site certificate application. A project order is not a final order.

      (4) A project order issued under subsection (3) of this section may be amended at any time by either the department or the council. [Formerly 453.335; 1977 c.794 §9; 1989 c.88 §1; 1993 c.569 §5; 1995 c.505 §8]

 

      469.340 [1975 c.552 §37; 1975 c.606 §26a; repealed by 1981 c.629 §3]

 

      469.350 Application for site certificate; comment and recommendation. (1) Applications for site certificates shall be made to the Energy Facility Siting Council in a form prescribed by the council and accompanied by the fee required by ORS 469.421.

      (2) Copies of the notice of intent and of the application shall be sent for comment and recommendation within specified deadlines established by the council to the Department of Environmental Quality, the Water Resources Commission, the State Fish and Wildlife Commission, the Water Resources Director, the State Geologist, the State Forestry Department, the Public Utility Commission of Oregon, the State Department of Agriculture, the Department of Land Conservation and Development, the Oregon Department of Aviation, any other state agency that has regulatory or advisory responsibility with respect to the facility and any city or county affected by the application.

      (3) Any state agency, city or county that is requested by the council to comment and make recommendations under this section shall respond to the council by the specified deadline. If a state agency, city or county determines that it cannot respond to the council by the specified deadline because the state agency, city or county lacks sufficient resources to review and comment on the application, the state agency, city or county shall contract with another entity to assist in preparing a response. A state agency, city or county that enters into a contract to assist in preparing a response may request funding to pay for that contract from the council pursuant to ORS 469.360.

      (4) The State Department of Energy shall notify the applicant whether the application is complete. When the department determines an application is complete, the department shall notify the applicant and provide notice to the public. [Formerly 453.345; 1977 c.794 §10; 1989 c.88 §2; 1993 c.569 §6; 1995 c.505 §9; 2001 c.683 §10; 2009 c.399 §4]

 

      469.360 Evaluation of notice of intent, site application or expedited review request; costs; payment. (1) The Energy Facility Siting Council shall evaluate each notice of intent, site certificate application or request for expedited review.

      (2) Pursuant to a written contract or agreement, the council may compensate a state agency or a local government affected by the application for expenses directly related to participation by the compensated agency or local government in the following evaluation activities:

      (a) Consultation initiated by an applicant after payment of the fee under ORS 469.421 (2) for the notice of intent or request for expedited review but prior to submittal of the notice or request;

      (b) Review of the notice of intent, the application or a request for an expedited review; and

      (c) Participation in a council proceeding, excluding legal expenses of the agency or local government incurred as a result of participation by the state agency or local government as a party in a contested case conducted by the council pursuant to ORS 469.370 (5).

      (3) Compensation for consultation expenses under subsection (2)(a) of this section shall be limited to the expenses established in an estimate provided by the council and agreed to by the applicant. The applicant may request that the estimate be revised to allow for additional consultation activities at any time prior to submitting the notice of intent.

      (4) Pursuant to a written agreement, the council may compensate a tribe identified by the Commission on Indian Services as affected by the application for expenses directly related to the tribe’s review of a notice of intent, site certificate application or request for expedited review.

      (5) As part of its evaluation, the council also may commission an independent study by an independent contractor, state agency, local government or any other person, of any aspect of the proposed facility within its statutory authority to review. The council may commission an independent study under this subsection only after the council makes a determination that the council is unable to fully evaluate the application without assistance and identifies specific issues to be addressed and only pursuant to a written contract or agreement with the independent contractor, state agency, local government or other person. The council shall compensate the independent contractor, state agency, local government or other person only to the extent the costs are directly related to issues identified by the council.

      (6) The council shall provide funding to state agencies, cities or counties required to contract with another entity to complete comments and recommendations pursuant to ORS 469.350.

      (7) In addition to compensating state agencies, tribes and local governments pursuant to this section, the council may provide funding to the Department of Environmental Quality for the department to conduct modeling and provide technical assistance to expedite preparation, submission and review of applications for permits under ORS 468A.040 required for energy facilities. [Formerly 453.355; 1987 c.450 §1; 1989 c.88 §3; 1993 c.569 §7; 1995 c.505 §10; 2001 c.683 §11; 2015 c.488 §1]

 

      469.370 Draft proposed order for hearing; issues raised; final order; expedited processing. (1) Based on its review of the application and the comments and recommendations on the application from state agencies and local governments, the State Department of Energy shall prepare and issue a draft proposed order on the application.

      (2) Following issuance of the draft proposed order, the Energy Facility Siting Council shall hold one or more public hearings on the application for a site certificate in the affected area and elsewhere, as the council considers necessary. Notice of the hearing shall be mailed at least 20 days before the hearing. The notice shall, at a minimum:

      (a) Comply with the requirements of ORS 197.797 (2), with respect to the persons notified;

      (b) Include a description of the facility and the facility’s general location;

      (c) Include the name of an agency representative to contact and the telephone number where additional information may be obtained;

      (d) State that copies of the application and draft proposed order are available for inspection at no cost and will be provided at a reasonable cost; and

      (e) State that failure to raise an issue in person or in writing prior to the close of the record of the public hearing with sufficient specificity to afford the decision maker an opportunity to respond to the issue precludes consideration of the issue in a contested case.

      (3) Any issue that may be the basis for a contested case shall be raised not later than the close of the record at or following the final public hearing prior to issuance of the department’s proposed order. Such issues shall be raised with sufficient specificity to afford the council, the department and the applicant an adequate opportunity to respond to each issue. A statement of this requirement shall be made at the commencement of any public hearing on the application.

      (4) After reviewing the application, the draft proposed order and any testimony given at the public hearing and after consulting with other agencies, the department shall issue a proposed order recommending approval or rejection of the application. The department shall issue public notice of the proposed order, that shall include notice of a contested case hearing specifying a deadline for requests to participate as a party or limited party and a date for the prehearing conference.

      (5) Following receipt of the proposed order from the department, the council shall conduct a contested case hearing on the application for a site certificate in accordance with the applicable provisions of ORS chapter 183 and any procedures adopted by the council. The applicant shall be a party to the contested case. The council may permit any other person to become a party to the contested case in support of or in opposition to the application only if the person appeared in person or in writing at the public hearing on the site certificate application. Issues that may be the basis for a contested case shall be limited to those raised on the record of the public hearing under subsection (3) of this section, unless:

      (a) The department failed to follow the requirements of subsection (2) or (3) of this section; or

      (b) The action recommended in the proposed order, including any recommended conditions of the approval, differs materially from that described in the draft proposed order, in which case only new issues related to such differences may be raised.

      (6) If no person requests party status to challenge the department’s proposed order, the proposed order shall be forwarded to the council and the contested case hearing shall be concluded.

      (7) At the conclusion of the contested case, the council shall issue a final order, either approving or rejecting the application based upon the standards adopted under ORS 469.501 and any additional statutes, rules or local ordinances determined to be applicable to the facility by the project order, as amended. The council shall make its decision by the affirmative vote of at least four members approving or rejecting any application for a site certificate. The council may amend or reject the proposed order, so long as the council provides public notice of its hearing to adopt a final order, and provides an opportunity for the applicant and any party to the contested case to comment on material changes to the proposed order, including material changes to conditions of approval resulting from the council’s review. The council’s order shall be considered a final order for purposes of appeal.

      (8) Rejection or approval of an application, together with any conditions that may be attached to the certificate, shall be subject to judicial review as provided in ORS 469.403.

      (9) The council shall either approve or reject an application for a site certificate:

      (a) Within 24 months after filing an application for a nuclear installation, or for a thermal power plant, other than that described in paragraph (b) of this subsection, with a nameplate rating of more than 200,000 kilowatts;

      (b) Within nine months after filing of an application for a site certificate for a combustion turbine power plant, a geothermal-fueled power plant or an underground storage facility for natural gas;

      (c) Within six months after filing an application for a site certificate for an energy facility, if the application is:

      (A) To expand an existing industrial facility to include an energy facility;

      (B) To expand an existing energy facility to achieve a nominal electric generating capacity of between 25 and 50 megawatts; or

      (C) To add injection or withdrawal capacity to an existing underground gas storage facility; or

      (d) Within 12 months after filing an application for a site certificate for any other energy facility.

      (10) At the request of the applicant, the council shall allow expedited processing of an application for a site certificate for an energy facility with an average electric generating capacity of less than 100 megawatts. No notice of intent shall be required. Following approval of a request for expedited review, the department shall issue a project order, which may be amended at any time. The council shall either approve or reject an application for a site certificate within six months after filing the site certificate application if there are no intervenors in the contested case conducted under subsection (5) of this section. If there are intervenors in the contested case, the council shall either approve or reject an application within nine months after filing the site certificate application. For purposes of this subsection, the generating capacity of a thermal power plant is the nameplate rating of the electrical generator proposed to be installed in the plant.

      (11) Failure of the council to comply with the deadlines set forth in subsection (9) or (10) of this section shall not result in the automatic issuance or denial of a site certificate.

      (12) The council shall specify in the site certificate a date by which construction of the facility must begin.

      (13) For a facility that is subject to and has been or will be reviewed by a federal agency under the National Environmental Policy Act, 42 U.S.C. Section 4321, et seq., the council shall conduct its site certificate review, to the maximum extent feasible, in a manner that is consistent with and does not duplicate the federal agency review. Such coordination shall include, but need not be limited to:

      (a) Elimination of duplicative application, study and reporting requirements;

      (b) Council use of information generated and documents prepared for the federal agency review;

      (c) Development with the federal agency and reliance on a joint record to address applicable council standards;

      (d) Whenever feasible, joint hearings and issuance of a site certificate decision in a time frame consistent with the federal agency review; and

      (e) To the extent consistent with applicable state standards, establishment of conditions in any site certificate that are consistent with the conditions established by the federal agency. [Formerly 453.365; 1977 c.296 §14; 1977 c.794 §11; 1977 c.895 §1; 1985 c.569 §17; 1993 c.544 §4; 1993 c.569 §8; 1995 c.79 §288; 1995 c.505 §11; 1997 c.428 §2; 2001 c.134 §6]

 

      469.371 [1985 c.569 §5; 1991 c.480 §6; repealed by 1993 c.544 §9]

 

      469.372 [1985 c.569 §14; 1985 c.673 §196; repealed by 1993 c.544 §9]

 

      469.373 Expedited processing for certain natural gas energy facilities. (1) Notwithstanding the expedited review process established pursuant to ORS 469.370, an applicant may apply under the provisions of this section for expedited review of an application for a site certificate for an energy facility if the energy facility:

      (a) Is a combustion turbine energy facility fueled by natural gas or is a reciprocating engine fueled by natural gas, including an energy facility that uses petroleum distillate fuels for backup power generation;

      (b) Is a permitted or conditional use allowed under an applicable local acknowledged comprehensive plan, land use regulation or federal land use plan, and is located:

      (A) At or adjacent to an existing energy facility; or

      (B)(i) At, adjacent to or in close proximity to an existing industrial use; and

      (ii) In an area currently zoned or designated for industrial use;

      (c)(A) Requires no more than three miles of associated transmission lines or three miles of new natural gas pipelines outside of existing rights of way for transmission lines or natural gas pipelines; or

      (B) Imposes, in the determination of the Energy Facility Siting Council, no significant impact in the locating of associated transmission lines or new natural gas pipelines outside of existing rights of way;

      (d) Requires no new water right or water right transfer;

      (e) Provides funds to a qualified organization in an amount determined by the council to be sufficient to produce any required reduction in emissions as specified in ORS 469.503 (2)(c)(C) and in rules adopted under ORS 469.503 for the total carbon dioxide emissions produced by the energy facility for the life of the energy facility; and

      (f)(A) Discharges process wastewater to a wastewater treatment facility that has an existing National Pollutant Discharge Elimination System permit, can obtain an industrial pretreatment permit, if needed, within the expedited review process time frame and has written confirmation from the wastewater facility permit holder that the additional wastewater load will be accommodated by the facility without resulting in a significant thermal increase in the facility effluent or without requiring any changes to the wastewater facility National Pollutant Discharge Elimination System permit;

      (B) Plans to discharge process wastewater to a wastewater treatment facility owned by a municipal corporation that will accommodate the wastewater from the energy facility and supplies evidence from the municipal corporation that:

      (i) The municipal corporation has included, or intends to include, the process wastewater load from the energy facility in an application for a National Pollutant Discharge Elimination System permit; and

      (ii) All conditions required of the energy facility to allow the discharge of process wastewater from the energy facility will be satisfied; or

      (C) Obtains a National Pollutant Discharge Elimination System or water pollution control facility permit for process wastewater disposal, supplies evidence to support a finding that the discharge can likely be permitted within the expedited review process time frame and that the discharge will not require:

      (i) A new National Pollutant Discharge Elimination System permit, except for a storm water general permit for construction activities; or

      (ii) A change in any effluent limit or discharge location under an existing National Pollutant Discharge Elimination System or water pollution control facility permit.

      (2) An applicant seeking expedited review under this section shall submit documentation to the State Department of Energy, prior to the submission of an application for a site certificate, that demonstrates that the energy facility meets the qualifications set forth in subsection (1) of this section. The department shall determine, within 14 days of receipt of the documentation, on a preliminary, nonbinding basis, whether the energy facility qualifies for expedited review.

      (3) If the department determines that the energy facility preliminarily qualifies for expedited review, the applicant may submit an application for expedited review. Within 30 days after the date that the application for expedited review is submitted, the department shall determine whether the application is complete. If the department determines that the application is complete, the application shall be deemed filed on the date that the department sends the applicant notice of its determination. If the department determines that the application is not complete, the department shall notify the applicant of the deficiencies in the application and shall deem the application filed on the date that the department determines that the application is complete. The department or the council may request additional information from the applicant at any time.

      (4) The State Department of Energy shall send a copy of a filed application to the Department of Environmental Quality, the Water Resources Department, the State Department of Fish and Wildlife, the State Department of Geology and Mineral Industries, the State Department of Agriculture, the Department of Land Conservation and Development, the Public Utility Commission and any other state agency, city, county or political subdivision of the state that has regulatory or advisory responsibility with respect to the proposed energy facility. The State Department of Energy shall send with the copy of the filed application a notice specifying that:

      (a) In the event the council issues a site certificate for the energy facility, the site certificate will bind the state and all counties, cities and political subdivisions in the state as to the approval of the site, the construction of the energy facility and the operation of the energy facility, and that after the issuance of a site certificate, all permits, licenses and certificates addressed in the site certificate must be issued as required by ORS 469.401 (3); and

      (b) The comments and recommendations of state agencies, counties, cities and political subdivisions concerning whether the proposed energy facility complies with any statute, rule or local ordinance that the state agency, county, city or political subdivision would normally administer in determining whether a permit, license or certificate required for the construction or operation of the energy facility should be approved will be considered only if the comments and recommendations are received by the department within a reasonable time after the date the application and notice of the application are sent by the department.

      (5) Within 90 days after the date that the application was filed, the department shall issue a draft proposed order setting forth:

      (a) A description of the proposed energy facility;

      (b) A list of the permits, licenses and certificates that are addressed in the application and that are required for the construction or operation of the proposed energy facility;

      (c) A list of the statutes, rules and local ordinances that are the standards and criteria for approval of any permit, license or certificate addressed in the application and that are required for the construction or operation of the proposed energy facility; and

      (d) Proposed findings specifying how the proposed energy facility complies with the applicable standards and criteria for approval of a site certificate.

      (6) The council shall review the application for site certification in the manner set forth in subsections (7) to (10) of this section and shall issue a site certificate for the facility if the council determines that the facility, with any required conditions to the site certificate, will comply with:

      (a) The requirements for expedited review as specified in this section;

      (b) The standards adopted by the council pursuant to ORS 469.501 (1)(a), (c) to (e), (g), (h) and (L) to (o);

      (c) The requirements of ORS 469.503 (3); and

      (d) The requirements of ORS 469.504 (1)(b).

      (7) Following submission of an application for a site certificate, the council shall hold a public informational meeting on the application. Following the issuance of the proposed order, the council shall hold at least one public hearing on the application. The public hearing shall be held in the area affected by the energy facility. The council shall mail notice of the hearing at least 20 days prior to the hearing. The notice shall comply with the notice requirements of ORS 197.797 (2) and shall include, but need not be limited to, the following:

      (a) A description of the energy facility and the general location of the energy facility;

      (b) The name of a department representative to contact and the telephone number at which people may obtain additional information;

      (c) A statement that copies of the application and proposed order are available for inspection at no cost and will be provided at reasonable cost; and

      (d) A statement that the record for public comment on the application will close at the conclusion of the hearing and that failure to raise an issue in person or in writing prior to the close of the record, with sufficient specificity to afford the decision maker an opportunity to respond to the issue, will preclude consideration of the issue, by the council or by a court on judicial review of the council’s decision.

      (8) Prior to the conclusion of the hearing, the applicant may request an opportunity to present additional written evidence, arguments or testimony regarding the application. In the alternative, prior to the conclusion of the hearing, the applicant may request a contested case hearing on the application. If the applicant requests an opportunity to present written evidence, arguments or testimony, the council shall leave the record open for that purpose only for a period not to exceed 14 days after the date of the hearing. Following the close of the record, the department shall prepare a draft final order for the council. If the applicant requests a contested case hearing, the council may grant the request if the applicant has shown good cause for a contested case hearing. If a request for a contested case hearing is granted, subsections (9) to (11) of this section do not apply, and the application shall be considered under the same contested case procedures used for a nonexpedited application for a site certificate.

      (9) The council shall make its decision based on the record and the draft final order prepared by the department. The council shall, within six months of the date that the application is deemed filed:

      (a) Grant the application;

      (b) Grant the application with conditions;

      (c) Deny the application; or

      (d) Return the application to the site certification process required by ORS 469.320.

      (10) If the application is granted, the council shall issue a site certificate pursuant to ORS 469.401 and 469.402. Notwithstanding subsection (6) of this section, the council may impose conditions based on standards adopted under ORS 469.501 (1)(b), (f) and (i) to (k), but may not deny an application based on those standards.

      (11) Judicial review of the approval or rejection of a site certificate by the council under this section shall be as provided in ORS 469.403. [2001 c.683 §15; 2011 c.298 §1]

 

      Note: 469.373 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.

 

      469.374 [1985 c.569 §15; repealed by 1993 c.544 §9]

 

      469.375 Required findings for radioactive waste disposal facility certificate. The Energy Facility Siting Council shall not issue a site certificate for a waste disposal facility for uranium mine overburden or uranium mill tailings, mill wastes or mill by-product or for radioactive waste or radioactively contaminated containers or receptacles used in the transportation, storage, use or application of radioactive material, unless, accompanying its decision it finds:

      (1) The site is:

      (a) Suitable for disposal of such wastes, and the amount of the wastes, intended for disposal at the site;

      (b) Not located in or adjacent to:

      (A) An area determined to be potentially subject to river or creek erosion within the lifetime of the facility;

      (B) Within the 500-year floodplain of a river, taking into consideration the area determined to be potentially subject to river or creek erosion within the lifetime of the facility;

      (C) An active fault or an active fault zone;

      (D) An area of ancient, recent or active mass movement including land sliding, flow or creep;

      (E) An area subject to ocean erosion; or

      (F) An area having experienced volcanic activity within the last two million years.

      (2) There is no available disposal technology and no available alternative site for disposal of such wastes that would better protect the health, safety and welfare of the public and the environment;

      (3) The disposal of such wastes and the amount of the wastes, at the site will be compatible with the regulatory programs of federal government for disposal of such wastes;

      (4) The disposal of such wastes, and the amount of the wastes, at the site will be coordinated with the regulatory programs of adjacent states for disposal of such wastes;

      (5) That following closure of the site, there will be no release of radioactive materials or radiation from the waste;

      (6) That suitable deed restrictions have been placed on the site recognizing the hazard of the material; and

      (7) That, where federal funding for remedial actions is not available, a surety bond in the name of the state has been provided in an amount determined by the State Department of Energy to be sufficient to cover any costs of closing the site and monitoring it or providing for its security after closure and to secure performance of any site certificate conditions. The bond may be withdrawn when the council finds that:

      (a) The radioactive waste has been disposed of at a waste disposal facility for which a site certificate has been issued; and

      (b) A fee has been paid to the State of Oregon sufficient for monitoring the site after closure.

      (8) If any section, portion, clause or phrase of this section is for any reason held to be invalid or unconstitutional the remaining sections, portions, clauses and phrases shall not be affected but shall remain in full force or effect, and to this end the provisions of this section are severable. [Formerly 459.625; 1979 c.283 §3; 1981 c.587 §3; 1985 c.4]

 

      469.378 Land use compatibility statement for energy facility. Notwithstanding ORS 197.180, when a state agency action or recommendation concerning an energy facility requires a land use compatibility statement prior to the action being completed, the state agency shall satisfy any applicable requirement of ORS 197.180 by conditioning the agency action or recommendation on a determination by either the Energy Facility Siting Council or the applicable city or county that the energy facility as affected by the state agency action satisfies, or will continue to satisfy, the applicable requirements of ORS 197.180. [2001 c.683 §17]

 

      Note: 469.378 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.

 

      469.380 [Formerly 453.375; 1977 c.794 §12; 1977 c.895 §2; 1993 c.569 §9; repealed by 1995 c.505 §32]

 

      469.390 [Formerly 453.385; repealed by 1993 c.569 §31]

 

      469.400 [Formerly 453.395; 1977 c.794 §13; 1977 c.895 §3; repealed by 1993 c.569 §10 (469.401 and 469.403 enacted in lieu of 469.400)]

 

      469.401 Energy facility site certificate; conditions; effect of issuance on state and local government agencies. (1) Upon approval, the site certificate or any amended site certificate with any conditions prescribed by the Energy Facility Siting Council shall be executed by the chairperson of the council and by the applicant. The certificate or amended certificate shall authorize the applicant to construct, operate and retire the facility subject to the conditions set forth in the site certificate or amended site certificate. The duration of the site certificate or amended site certificate shall be the life of the facility.

      (2) The site certificate or amended site certificate shall contain conditions for the protection of the public health and safety, for the time for completion of construction, and to ensure compliance with the standards, statutes and rules described in ORS 469.501 and 469.503. The site certificate or amended site certificate shall require both parties to abide by local ordinances and state law and the rules of the council in effect on the date the site certificate or amended site certificate is executed, except that upon a clear showing of a significant threat to the public health, safety or the environment that requires application of later-adopted laws or rules, the council may require compliance with such later-adopted laws or rules. For a permit addressed in the site certificate or amended site certificate, the site certificate or amended site certificate shall provide for facility compliance with applicable state and federal laws adopted in the future to the extent that such compliance is required under the respective state agency statutes and rules.

      (3) Subject to the conditions set forth in the site certificate or amended site certificate, any certificate or amended certificate signed by the chairperson of the council shall bind the state and all counties and cities and political subdivisions in this state as to the approval of the site and the construction and operation of the facility. After issuance of the site certificate or amended site certificate, any affected state agency, county, city and political subdivision shall, upon submission by the applicant of the proper applications and payment of the proper fees, but without hearings or other proceedings, promptly issue the permits, licenses and certificates addressed in the site certificate or amended site certificate, subject only to conditions set forth in the site certificate or amended site certificate. After the site certificate or amended site certificate is issued, the only issue to be decided in an administrative or judicial review of a state agency or local government permit for which compliance with governing law was considered and determined in the site certificate or amended site certificate proceeding shall be whether the permit is consistent with the terms of the site certificate or amended site certificate. Each state or local government agency that issues a permit, license or certificate shall continue to exercise enforcement authority over the permit, license or certificate.

      (4) Nothing in ORS chapter 469 shall be construed to preempt the jurisdiction of any state agency or local government over matters that are not included in and governed by the site certificate or amended site certificate. Such matters include but are not limited to employee health and safety, building code compliance, wage and hour or other labor regulations, local government fees and charges or other design or operational issues that do not relate to siting the facility. [1993 c.569 §11 (469.401 and 469.403 enacted in lieu of 469.400); 1995 c.505 §12; 1999 c.385 §2]

 

      469.402 Delegation of review of future action required by site certificate. If the Energy Facility Siting Council elects to impose conditions on a site certificate or an amended site certificate, that require subsequent review and approval of a future action, the council may delegate the future review and approval to the State Department of Energy if, in the council’s discretion, the delegation is warranted under the circumstances of the case. [1995 c.505 §27; 1999 c.385 §3]

 

      Note: 469.402 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.

 

      469.403 Rehearing on approval or rejection of application for site certificate or amendment; appeal; judicial review vested in Supreme Court; stay of order. (1) Any party to a contested case proceeding may apply for rehearing within 30 days from the date the approval or rejection is served. The date of service shall be the date on which the Energy Facility Siting Council delivered or mailed its approval or rejection in accordance with ORS 183.470. The application for rehearing shall set forth specifically the ground upon which the application is based. No objection to the council’s approval or rejection of an application for a site certificate or a site certificate amendment shall be considered on rehearing without good cause shown unless the basis for the objection is urged with reasonable specificity before the council in the site certificate or amended site certificate process. Upon such application, the council shall have the power to grant or deny rehearing or to abrogate or modify its order without further hearing. Unless the council acts upon the application for rehearing within 30 days after the application is filed, the application shall be considered denied. The filing of an application for rehearing shall not, unless specifically ordered by the council, operate as a stay of the site certificate or amended site certificate for the facility.

      (2) Any party to a contested case proceeding on a site certificate or amended site certificate application may appeal the council’s approval or rejection of the site certificate or amended site certificate application. Issues on appeal shall be limited to those raised by the parties to the contested case proceeding before the council.

      (3) Jurisdiction for judicial review of the council’s approval or rejection of an application for a site certificate or amended site certificate is conferred upon the Supreme Court. Proceedings for review shall be instituted by filing a petition in the Supreme Court. The petition shall be filed within 60 days after the date of service of the council’s final order or within 30 days after the date the petition for rehearing is denied or deemed denied. Date of service shall be the date on which the council delivered or mailed its order in accordance with ORS 183.470.

      (4) The filing of a petition for judicial review may not stay the order, except that a party to the contested case may apply to the Supreme Court for a stay upon a showing that there is a colorable claim of error and that:

      (a) The petitioner will suffer irreparable injury; or

      (b) Construction of the energy facility will result in irreparable harm to resources protected by applicable council standards or applicable agency or local government standards.

      (5) If the Supreme Court grants a stay pursuant to subsection (4) of this section, the court:

      (a) Shall require the petitioner requesting the stay to give an undertaking in the amount of $5,000.

      (b) May grant a stay in whole or in part.

      (c) May impose other reasonable conditions on the stay.

      (6) Except as otherwise provided in ORS 469.320 and this section, the review by the Supreme Court shall be the same as the review by the Court of Appeals described in ORS 183.482. The Supreme Court shall give priority on its docket to such a petition for review and shall render a decision within six months of the filing of the petition for review.

      (7) The following periods of delay shall be excluded from the six-month period within which the court must render a decision under subsection (6) of this section:

      (a) Any period of delay resulting from a motion properly before the court; or

      (b) Any reasonable period of delay resulting from a continuance granted by the court on the court’s own motion or at the request of one of the parties, if the court granted the continuance on the basis of findings that the ends of justice served by granting the continuance outweigh the best interests of the public and the other parties in having a decision within six months.

      (8) No period of delay resulting from a continuance granted by the Supreme Court under subsection (7)(b) of this section shall be excluded from the six-month period unless the court sets forth, in the record, either orally or in writing, its reasons for finding that the ends of justice served by granting the continuance outweigh the best interests of the public and the other parties in having a decision within six months. The factors the court shall consider in determining whether to grant a continuance under subsection (7)(b) of this section are:

      (a) Whether the failure to grant a continuance in the proceeding would be likely to make a continuation of the proceeding impossible or result in a miscarriage of justice; or

      (b) Whether the case is so unusual or so complex, due to the number of parties involved or the existence of novel questions of fact or law, that it is unreasonable to expect adequate consideration of the issues within the six-month period.

      (9) No continuance under subsection (7)(b) of this section shall be granted because of general congestion of the court calendar or lack of diligent preparation or attention to the case by any member of the court or any party. [1993 c.569 §12 (469.401 and 469.403 enacted in lieu of 469.400); 1995 c.505 §13; 1999 c.385 §4; 2001 c.683 §12]

 

      469.405 Amendment of site certificate; judicial review; exemption; rules. (1) A site certificate may be amended with the approval of the Energy Facility Siting Council. The council may establish by rule the type of amendment that must be considered in a contested case proceeding. Judicial review of an amendment to a site certificate shall be as provided in ORS 469.403.

      (2) Notwithstanding ORS 34.020 or 197.825, or any other provision of law, the land use approval by an affected local government of a proposed amendment to a facility and the recommendation of the special advisory group of applicable substantive criteria shall be subject to judicial review only as provided in ORS 469.403. If the applicant elects to show compliance with the statewide planning goals by demonstrating that the facility has received local land use approval, the provisions of this section shall apply only to proposed projects for which the land use approval by the local government occurs after the date an application for amendment is submitted to the State Department of Energy.

      (3) An amendment to a site certificate is not required for a pipeline less than 16 inches in diameter and less than five miles in length that is proposed to be constructed to test or maintain an underground gas storage reservoir. If the proposed pipeline will connect to a council certified surface facility related to an underground gas storage reservoir or to a council certified gas pipeline, whether the proposed pipeline is to be located inside or outside the site of a council certified facility, the certificate holder must obtain, prior to construction, the approval of the department for the construction, operation and retirement of the proposed pipeline. The department shall approve such a proposed pipeline if the pipeline meets applicable council substantive standards. Notwithstanding ORS 469.503 (3), the department may not review the proposed pipeline for compliance with other state standards. Notwithstanding ORS 469.503 (4), or any council rule addressing compliance with land use standards, the department shall not review such a proposed pipeline for compliance with land use requirements. Notwithstanding ORS 469.401 (3), the approval by the department of such pipeline shall not bind any state or local agency. The council may adopt appropriate procedural rules for the department review. The department shall issue an order approving or rejecting the proposed pipeline. Judicial review of a department order under this section shall be as provided in ORS 469.403. [1995 c.505 §2; 1999 c.385 §5]

 

      Note: 469.405 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.

 

      469.407 Amendment of application to increase capacity of facility. (1) A recipient may by amendment of its application for a site certificate or by amendment of its site certificate increase the capacity of the facility if the Energy Facility Siting Council finds that:

      (a) The facility will satisfy the conditions of the 500-megawatt exemption, unless modified by the council;

      (b) The enlarged facility does not exceed 500 megawatts and meets the applicable carbon dioxide standard provided for in ORS 469.503 (2) for any increase in capacity beyond the capacity of the 500-megawatt exemption; and

      (c) The enlarged facility meets all other applicable council standards.

      (2) A recipient is deemed to meet any applicable need standard and carbon dioxide emissions standard for the nominal generating capacity of the 500-megawatt exemption provided that the recipient satisfies the conditions of the 500-megawatt exemption, unless the council modifies the conditions.

      (3) As used in this section:

      (a) “Recipient” means any base load gas plant, as defined in ORS 469.503, determined by the council to have the lowest net monetized air emissions among the applicants participating in a contested case proceeding.

      (b) “500-megawatt exemption” means the council order in which a recipient was determined to have the lowest net monetized air emissions. [1997 c.428 §8]

 

      Note: 469.407 and 469.409 were added to and made a part of 469.300 to 469.563 by legislative action but were not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.

 

      469.409 Amendment of site certificate to demonstrate compliance with carbon dioxide emissions standard; binding arbitration to resolve disputes. Any site certificate holder that is required by its site certificate or by law to demonstrate need for the facility shall instead demonstrate compliance with the carbon dioxide emissions standard applicable to the type of facility subject to the site certificate before beginning construction. Such a demonstration shall be made as an amendment to the site certificate. Notwithstanding ORS 469.405 or any council rule, if the site certificate holder proceeds pursuant to ORS 469.503 (2)(c)(A) or (C), or both, the Energy Facility Siting Council shall not conduct a contested case hearing on such amendment and the council’s order shall not be subject to judicial review. Any dispute about the site certificate holder’s demonstration of compliance with the applicable carbon dioxide emissions standard shall be settled through binding arbitration. [1997 c.428 §7]

 

      Note: See note under 469.407.

 

      469.410 Energy facility site certificate applications filed or under construction prior to July 2, 1975; conditions of site certificate; monitoring programs. (1) Any applicant for a site certificate for an energy facility shall be deemed to have met all the requirements of ORS 176.820, 192.338, 192.345, 192.355, 192.690, 469.010 to 469.155, 469.300 to 469.563, 469.990, 757.710 and 757.720 relating to eligibility for a site certificate and a site certificate shall be issued by the Energy Facility Siting Council for:

      (a) Any transmission lines for which application has been filed with the federal government and the Public Utility Commission of Oregon prior to July 2, 1975; and

      (b) Any energy facility under construction on July 2, 1975.

      (2) Each applicant for a site certificate under this section shall pay the fees required by ORS 469.421 (2) to (9), if applicable, and shall execute a site certificate in which the applicant agrees:

      (a) To abide by the conditions of all licenses, permits and certificates required by the State of Oregon or any subdivision in the state to operate the energy facility and issued prior to July 2, 1975; and

      (b) On and after July 2, 1975, to abide by the rules of the Director of the State Department of Energy adopted pursuant to ORS 469.040 (1)(d) and rules of the council adopted pursuant to ORS 469.300 to 469.563, 469.590 to 469.619 and 469.930.

      (3) The council has continuing authority over the site for which the site certificate is issued and may inspect, or direct the State Department of Energy to inspect, or request another state agency or local government to inspect, the site at any time in order to ensure that the facility is being operated consistently with the terms and conditions of the site certificate and any applicable health or safety standards.

      (4) The council shall establish programs for monitoring the environmental and ecological effects of the operation and the decommissioning of energy facilities subject to site certificates issued prior to July 2, 1975, to ensure continued compliance with the terms and conditions of the site certificate and any applicable health or safety standards.

      (5) Site certificates executed by the Governor under ORS 469.400 (1991 Edition) prior to July 2, 1975, shall bind successor agencies created hereunder in accordance with the terms of such site certificates. Any holder of a site certificate issued prior to July 2, 1975, shall abide by the rules of the director adopted pursuant to ORS 469.040 (1)(d) and rules of the council adopted pursuant to ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992. [1975 c.606 §24; 1983 c.740 §184; 1989 c.88 §5; 1993 c.569 §13; 1995 c.505 §15]

 

      469.413 Power generation from fossil fuels; requirements for new and amended site certificates. Notwithstanding ORS 469.320 and 469.405, the Energy Facility Siting Council may not:

      (1) Issue a site certificate for a new generating facility that produces electric power from fossil fuels, including natural gas, petroleum, coal or any form of solid, liquid or gaseous fuel derived from such material, unless the council determines that a new generating facility will generate only nonemitting electricity as defined in ORS 469A.400; or

      (2) Approve the amendment of a site certificate for an energy facility described under subsection (1) of this section that was granted prior to September 25, 2021, in a manner that would significantly increase the gross carbon dioxide emissions that are reasonably likely to result from the operation of the energy facility. [2021 c.508 §28]

 

      Note: 469.413 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.420 [Formerly 453.405; 1977 c.813 §1; 1979 c.234 §1; 1981 c.792 §3; repealed by 1981 c.792 §4 (469.421 enacted in lieu of 469.420)]

 

      469.421 Fees; exemptions; assessment of certain utilities and suppliers; penalty. (1) Subject to the provisions of ORS 469.441, any person submitting a notice of intent, a request for exemption under ORS 469.320, a request for an expedited review under ORS 469.370, a request for an expedited review under ORS 469.373, a request for the State Department of Energy to approve a pipeline under ORS 469.405 (3), an application for a site certificate or a request to amend a site certificate shall pay all expenses incurred by the Energy Facility Siting Council and the department related to the review and decision of the council. Expenses under this subsection may include:

      (a) Legal expenses;

      (b) Expenses incurred in processing and evaluating the application;

      (c) Expenses incurred in issuing a final order or site certificate;

      (d) Expenses incurred in commissioning an independent study under ORS 469.360;

      (e) Compensation paid to a state agency, a tribe or a local government pursuant to a written contract or agreement relating to compensation as provided for in ORS 469.360; or

      (f) Expenses incurred by the council in making rule changes that are specifically required and related to the particular site certificate.

      (2) Every person submitting a notice of intent to file for a site certificate, a request for exemption or a request for expedited review shall pay the fee required under the fee schedule established under ORS 469.441 to the department prior to submitting the notice or request to the council. To the extent possible, the full cost of the evaluation shall be paid from the fee paid under this subsection. However, if costs of the evaluation exceed the fee, the person submitting the notice or request shall pay any excess costs shown in an itemized statement prepared by the council. In no event shall the council incur evaluation expenses in excess of 110 percent of the fee initially paid unless the council provides prior notification to the applicant and a detailed projected budget the council believes necessary to complete the project. If costs are less than the fee paid, the excess shall be refunded to the person submitting the notice or request.

      (3) Before submitting a site certificate application, the applicant shall request from the department an estimate of the costs expected to be incurred in processing the application. The department shall inform the applicant of that amount and require the applicant to make periodic payments of the costs pursuant to a cost reimbursement agreement. The cost reimbursement agreement shall provide for payment of 25 percent of the estimated costs when the applicant submits the application. If costs of the evaluation exceed the estimate, the applicant shall pay any excess costs shown in an itemized statement prepared by the council. In no event shall the council incur evaluation expenses in excess of 110 percent of the fee initially estimated unless the council provided prior notification to the applicant and a detailed projected budget the council believes is necessary to complete the project. If costs are less than the fee paid, the council shall refund the excess to the applicant.

      (4) Any person who is delinquent in the payment of fees under subsections (1) to (3) of this section shall be subject to the provisions of subsection (11) of this section.

      (5) Subject to the provisions of ORS 469.441, each holder of a certificate shall pay an annual fee, due every July 1 following issuance of a site certificate. For each fiscal year, upon approval of the department’s budget authorization by an odd-numbered year regular session of the Legislative Assembly or as revised by the Emergency Board meeting in an interim period or by the Legislative Assembly meeting in special session or in an even-numbered year regular session, the Director of the State Department of Energy promptly shall enter an order establishing an annual fee based on the amount of revenues that the director estimates is needed to fund the cost of ensuring that the facility is being operated consistently with the terms and conditions of the site certificate, any order issued by the department under ORS 469.405 (3) and any applicable health or safety standards. In determining this cost, the director shall include both the actual direct cost to be incurred by the council and the department to ensure that the facility is being operated consistently with the terms and conditions of the site certificate, any order issued by the department under ORS 469.405 (3) and any applicable health or safety standards, and the general costs to be incurred by the council and the department to ensure that all certificated facilities are being operated consistently with the terms and conditions of the site certificates, any orders issued by the department under ORS 469.405 (3) and any applicable health or safety standards that cannot be allocated to an individual, licensed facility. Not more than 35 percent of the annual fee charged each facility shall be for the recovery of these general costs. The fees for direct costs shall reflect the size and complexity of the facility, the anticipated costs of ensuring compliance with site certificate conditions, the anticipated costs of conducting site inspections and compliance reviews as described in ORS 469.430, and the anticipated costs of compensating state agencies and local governments for participating in site inspection and compliance enforcement activities at the request of the council.

      (6) Each holder of a site certificate executed after July 1 of any fiscal year shall pay a fee for the remaining portion of the year. The amount of the fee shall be set at the cost of regulating the facility during the remaining portion of the year determined in the same manner as the annual fee.

      (7) When the actual costs of regulation incurred by the council and the department for the year, including that portion of the general regulation costs that have been allocated to a particular facility, are less than the annual fees for that facility, the unexpended balance shall be refunded to the site certificate holder. When the actual regulation costs incurred by the council and the department for the year, including that portion of the general regulation costs that have been allocated to a particular facility, are projected to exceed the annual fee for that facility, the director may issue an order revising the annual fee.

      (8)(a) In addition to any other fees required by law, each energy resource supplier shall pay to the department annually its share of an assessment to fund the programs and activities of the council and the department.

      (b) Prior to filing an agency request budget under ORS 291.208 for purposes related to the compilation and preparation of the Governor’s budget under ORS 291.216, the director shall determine the projected aggregate amount of revenue to be collected from energy resource suppliers under this subsection that will be necessary to fund the programs and activities of the council and the department for each fiscal year of the upcoming biennium. After making that determination, the director shall convene a public meeting with representatives of energy resource suppliers and other interested parties for the purpose of providing energy resource suppliers with a full accounting of:

      (A) The projected revenue needed to fund each department program or activity; and

      (B) The projected allocation of moneys derived from the assessment imposed under this subsection to each department program or activity.

      (c) Upon approval of the budget authorization of the council and the department by an odd-numbered year regular session of the Legislative Assembly, the director shall promptly enter an order establishing the amount of revenues required to be derived from an assessment pursuant to this subsection in order to fund programs and activities that the council and the department are charged with administering and authorized to conduct under the laws of this state, including those enumerated in ORS 469.030, for the first fiscal year of the forthcoming biennium. On or before June 1 of each even-numbered year, the director shall enter an order establishing the amount of revenues required to be derived from an assessment pursuant to this subsection in order to fund the programs and activities that the council and the department are charged with administering and authorized to conduct under the laws of this state, including those enumerated in ORS 469.030, for the second fiscal year of the biennium. The order shall take into account any revisions to the biennial budget of the council and the department made by the Emergency Board meeting in an interim period or by the Legislative Assembly meeting in special session or in an even-numbered year regular session.

      (d) Each order issued by the director pursuant to paragraph (c) of this subsection shall allocate the aggregate assessment set forth in the order to energy resource suppliers in accordance with paragraph (e) of this subsection.

      (e) The amount assessed to an energy resource supplier shall be based on the ratio which that supplier’s annual gross operating revenue derived within this state in the preceding calendar year bears to the total gross operating revenue derived within this state during that year by all energy resource suppliers. The assessment against an energy resource supplier shall not exceed 0.375 percent of the supplier’s gross operating revenue derived within this state in the preceding calendar year. The director shall exempt from payment of an assessment any individual energy resource supplier whose calculated share of the annual assessment is less than $250.

      (f) The director shall send each energy resource supplier subject to assessment pursuant to this subsection a copy of each order issued by registered or certified mail or through use of an electronic medium with electronic receipt verification. The amount assessed to the energy resource supplier pursuant to the order shall be considered to the extent otherwise permitted by law a government-imposed cost and recoverable by the energy resource supplier as a cost included within the price of the service or product supplied.

      (g) The amounts assessed to individual energy resource suppliers pursuant to paragraph (e) of this subsection shall be paid to the department as follows:

      (A) Amounts assessed for the first fiscal year of a biennium shall be paid not later than 90 days following adjournment sine die of the odd-numbered year regular session of the Legislative Assembly; and

      (B) Amounts assessed for the second fiscal year of a biennium shall be paid not later than July 1 of each even-numbered year or 90 days following adjournment sine die of the even-numbered year regular session of the Legislative Assembly, whichever is later.

      (h) An energy resource supplier shall provide the director, on or before May 1 of each year, a verified statement showing its gross operating revenues derived within the state for the calendar or fiscal year that was used by the energy resource supplier for the purpose of reporting federal income taxes for the preceding calendar or fiscal year. The statement must be in the form prescribed by the director and is subject to audit by the director. The statement must include an entry showing the total operating revenue derived by petroleum suppliers from fuels sold that are subject to the requirements of Article IX, section 3a, of the Oregon Constitution, and ORS 319.020 with reference to aircraft fuel and motor vehicle fuel, and ORS 319.530. The director may grant an extension of not more than 15 days for the requirements of this subsection if:

      (A) The energy supplier makes a showing of hardship caused by the deadline;

      (B) The energy supplier provides reasonable assurance that the energy supplier can comply with the revised deadline; and

      (C) The extension of time does not prevent the council or the department from fulfilling its statutory responsibilities.

      (i) As used in this section:

      (A) “Energy resource supplier” means an electric utility, natural gas utility or petroleum supplier supplying, generating, transmitting or distributing electricity, natural gas or petroleum products in Oregon.

      (B) “Gross operating revenue” means gross receipts from sales or service made or provided within this state during the regular course of the energy supplier’s business, but does not include either revenue derived from interutility sales within the state or revenue received by a petroleum supplier from the sale of fuels that are subject to the requirements of Article IX, section 3a, of the Oregon Constitution, or ORS 319.020 or 319.530.

      (C) “Petroleum supplier” has the meaning given that term in ORS 469.020.

      (j) In determining the amount of revenues that must be derived from any class of energy resource suppliers by assessment pursuant to this subsection, the director shall take into account all other known or readily ascertainable sources of revenue to the council and department, including, but not limited to, fees imposed under this section and federal funds, and may take into account any funds previously assessed pursuant to ORS 469.420 (1979 Replacement Part) or section 7, chapter 792, Oregon Laws 1981.

      (k) Orders issued by the director pursuant to this section shall be subject to judicial review under ORS 183.484. The taking of judicial review shall not operate to stay the obligation of an energy resource supplier to pay amounts assessed to it on or before the statutory deadline.

      (9)(a) In addition to any other fees required by law, each operator of a nuclear fueled thermal power plant or nuclear installation within this state shall pay to the department annually on July 1 an assessment in an amount determined by the director to be necessary to fund the activities of the state and the counties associated with emergency preparedness for a nuclear fueled thermal power plant or nuclear installation. The assessment shall not exceed $461,250 per year. Moneys collected as assessments under this subsection are continuously appropriated to the department for this purpose.

      (b) The department shall maintain and cause other state agencies and counties to maintain time and billing records for the expenditure of any fees collected from an operator of a nuclear fueled thermal power plant under paragraph (a) of this subsection.

      (10) Reactors operated by a college, university or graduate center for research purposes and electric utilities not connected to the Northwest Power Grid are exempt from the fee requirements of subsections (5), (8) and (9) of this section.

      (11)(a) All fees assessed by the director against holders of site certificates for facilities that have an installed capacity of 500 megawatts or greater may be paid in several installments, the schedule for which shall be negotiated between the director and the site certificate holder.

      (b) Energy resource suppliers or applicants or holders of a site certificate who fail to pay a fee provided under subsections (1) to (9) of this section after it is due and payable shall pay, in addition to that fee, a penalty of two percent of the fee a month for the period that the fee is past due. Any payment made according to the terms of a schedule negotiated under paragraph (a) of this subsection shall not be considered past due. The director may bring an action to collect an unpaid fee or penalty in the name of the State of Oregon in a court of competent jurisdiction. The court may award reasonable attorney fees to the director if the director prevails in an action under this subsection. The court may award reasonable attorney fees to a defendant who prevails in an action under this subsection if the court determines that the director had no objectively reasonable basis for asserting the claim or no reasonable basis for appealing an adverse decision of the trial court. [1981 c.792 §5 (enacted in lieu of 469.420); 1983 c.273 §5; 1987 c.450 §2; 1989 c.88 §4; 1993 c.569 §14; 1995 c.505 §14; 1995 c.542 §1; 1995 c.551 §11; 1995 c.618 §74a; 1995 c.696 §22; 1997 c.249 §166; 1999 c.385 §6; 2001 c.683 §13; 2003 c.186 §30; 2009 c.11 §67; 2009 c.753 §76; 2011 c.545 §26; 2013 c.656 §1; 2015 c.488 §2; 2016 c.117 §71]

 

      469.424 Energy resource suppliers; notice regarding comments in proceedings; rules. (1) As used in this section, “energy resource supplier” has the meaning given that term in ORS 469.421.

      (2)(a) If the State Department of Energy submits comments or written or oral testimony in a rulemaking, contested case, ratemaking or other proceeding conducted by another agency, as defined in ORS 183.310, and if the comment or testimony is about a substantive matter at issue in the proceeding, the department shall provide, once for each proceeding, notice to energy resource suppliers as described in this section.

      (b) If the department submits written comments or intervenes in a proceeding conducted by a federal agency, the department shall provide, once for each proceeding, notice to energy resource suppliers as described in this section.

      (c) This section does not apply to:

      (A) The department’s participation in a procedural matter related to a proceeding described in paragraph (a) or (b) of this subsection;

      (B) The department’s participation in a federal facility siting proceeding;

      (C) The department’s work with the Energy Facility Siting Council;

      (D) The department’s work on nuclear safety and emergency preparedness; or

      (E) Federal judicial or legislative proceedings.

      (3) The department shall create and maintain a list of energy resource suppliers that request to receive notice described in subsection (2) of this section. The department may create separate lists for the different types of proceedings.

      (4) Notice provided under this section may be provided by electronic mail and must include a description of the department’s interest in the proceeding.

      (5) Except as provided in subsection (6) of this section, notice must be provided under this section:

      (a) No later than seven days before submitting initial comments on a substantive matter at issue in a rulemaking proceeding described in subsection (2)(a) of this section or a proceeding involving the adoption of federal regulations;

      (b) No later than 15 days before submitting initial comments or written or oral testimony on a substantive matter at issue in a contested case, ratemaking or other proceeding described in subsection (2)(a) of this section; or

      (c) No later than 15 days before submitting initial written comments or written testimony on a substantive matter at issue in a proceeding conducted by a federal agency other than a proceeding involving the adoption of federal regulations.

      (6) If providing notice in accordance with subsection (5) of this section is prejudicial to the department’s ability to participate in a rulemaking, contested case, ratemaking or other proceeding described in subsection (2) of this section, the department may provide notice as soon as it is practicable to provide notice. If the department provides notice as described in this subsection, the department shall include in the notice an explanation of why providing notice in accordance with subsection (5) of this section is prejudicial to the department.

      (7) The department may adopt rules as necessary to implement this section. [2013 c.656 §6]

 

      Note: 469.424 was added to and made a part of 469.300 to 469.563 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.

 

      469.426 Advisory group; energy resource suppliers. (1) The Director of the State Department of Energy shall convene an advisory work group composed of stakeholders representing energy resource suppliers, the customers who ultimately pay for the energy supplier assessment imposed under ORS 469.421 (8) through their energy bills and other groups that have an interest in the provision and regulation of energy in this state.

      (2) The advisory work group shall review and make recommendations on the State Department of Energy’s proposals related to:

      (a) Planning, policy and technical analysis;

      (b) Legislative concepts; and

      (c) The department’s requested budget.

      (3) The work group shall meet at least two times per year at the call of the director. [2013 c.656 §3]

 

      Note: 469.426 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.430 Site inspections; compliance reviews. (1) The Energy Facility Siting Council has continuing authority over the site for which the site certificate is issued, including but not limited to the authority to:

      (a) Inspect, or direct the State Department of Energy to inspect, or request another state agency or local government to inspect, the site at any time in order to ensure that the facility is being operated consistently with the terms and conditions of the site certificate or any order issued by the department under ORS 469.405 (3); and

      (b) Periodically review documents, reports and other materials, or direct the State Department of Energy or request another state agency or local government to review documents, reports or other materials, to ensure that the facility continues to comply with all terms and conditions of the site certificate or any order issued by the department under ORS 469.405 (3).

      (2) The council shall avoid duplication of effort with site inspections and compliance reviews by other state and federal agencies and local governments that have issued permits or licenses for the facility.

      (3) If the council requests that another state agency or local government conduct a site inspection or compliance review under this section, the council may compensate that state agency or local government for expenses related to the site inspection or compliance review. [Formerly 453.415; 1993 c.569 §15; 1995 c.505 §16; 1999 c.385 §7; 2015 c.488 §3]

 

      469.440 Grounds for revocation or suspension of certificates. Pursuant to the procedures for contested cases in ORS chapter 183, a site certificate or an amended site certificate may be revoked or suspended:

      (1) For failure to comply with the terms or conditions of the site certificate or amended site certificate;

      (2) For violation of the provisions of ORS 469.525 to 469.563, 469.590 to 469.619, 469.930 and 469.992 or rules adopted pursuant to ORS 469.525 to 469.563, 469.590 to 469.619, 469.930 and 469.992; or

      (3) If the site certificate was executed prior to July 2, 1975, for violation of the provisions of ORS 469.300 to 469.520 or rules adopted pursuant to ORS 469.300 to 469.520 or for failure to comply with applicable health or safety standards. [Formerly 453.425; 1993 c.569 §16; 1995 c.505 §17; 1999 c.385 §8]

 

      469.441 Justification of fees charged; judicial review. (1) All expenses incurred by the Energy Facility Siting Council and the State Department of Energy under ORS 469.360 and 469.421 that are charged to or allocated to the fee paid by an applicant or the holder of a site certificate shall be necessary, just and reasonable. Upon request, the department or the council shall provide a detailed justification for all charges to the applicant or site certificate holder. Not later than January 1 of each odd-numbered year, the council by order shall establish a schedule of fees which those persons submitting a notice of intent, a request for an exemption, a request for a pipeline described in ORS 469.405 (3) or a request for an expedited review must submit under ORS 469.421 prior to submitting the notice of intent, request for exemption, request for pipeline or request for expedited review. The fee schedule shall be designed to recover the council’s actual costs of evaluating the notice of intent, request for exemption, request for pipeline or request for expedited review subject to any applicable expenditure limitation in the council’s budget. Fees shall be based upon actual, historical costs incurred by the council and department to the extent historical costs are available. The fees established by the schedule shall reflect the size and complexity of the project for which a notice of intent, request for exemption, request for pipeline or request for expedited review is submitted, whether the notice of intent, request for exemption, request for pipeline or request for expedited review is for a new or existing facility and other appropriate variables having an effect on the expense of evaluation.

      (2) If a dispute arises regarding the necessity or reasonableness of expenses charged to or allocated to the fee paid by an applicant or site certificate holder, the applicant or holder may seek judicial review for the amount of expenses charged or allocated in circuit court as provided in ORS 183.480, 183.484, 183.490 and 183.500. If the applicant or holder establishes that any of the charges or allocations are unnecessary or unreasonable, the council or the department shall refund the amount found to be unnecessary or unreasonable. The applicant or holder shall not waive the right to judicial review by paying the portion of the fee or expense in dispute. [1989 c.88 §8; 1993 c.569 §17; 1999 c.385 §9; 2015 c.488 §4]

 

(High Voltage Transmission Lines)

 

      469.442 Procedure prior to construction of transmission line in excess of 230,000 volts; review committee. (1) Any person who proposes to construct a transmission line in excess of 230,000 volts capacity that is not otherwise under the jurisdiction of the Energy Facility Siting Council shall:

      (a) Give public notice of the proposed action at least six months before beginning any process to obtain local permits required for the proposed transmission line. Notification shall be given:

      (A) By publication once a week for four consecutive weeks in a newspaper of general circulation in the county or counties in which the transmission line is to be constructed; and

      (B) To the governing bodies and planning directors of cities and counties which are within or partially within the project study area.

      (b) Provide an opportunity for public comment on the proposed transmission line and conduct public meetings to review the proposal.

      (c) Respond specifically and in writing to local concerns and recommendations regarding the proposed transmission line.

      (2) The Director of the State Department of Energy shall establish a committee to include technical experts and members of the public to coordinate public review of a proposed transmission line under subsection (1) of this section when requested to do so by ordinance or resolution of the affected governing body.

      (3) At the conclusion of the public review, the committee shall make a summary report to the affected governing body including public concerns and recommendations concerning the proposed transmission line.

      (4) The scope of work and cost of conducting the review shall be negotiated between the State Department of Energy and the project sponsor. The negotiated cost shall be paid by the project sponsor.

      (5) Subsections (1) to (4) of this section shall not apply to a person who proposes to construct transmission lines entirely within 500 feet of an existing corridor occupied by transmission lines with a capacity in excess of 230,000 volts. [1987 c.200 §2; 1993 c.569 §18]

 

      469.445 [1987 c.200 §3; repealed by 1993 c.569 §31]

 

(Administration)

 

      469.450 Energy Facility Siting Council; appointment; confirmation; term; restrictions. (1) There is established in the State Department of Energy an Energy Facility Siting Council, consisting of seven public members, who shall be appointed by the Governor, subject to confirmation by the Senate in the manner prescribed in ORS 171.562 and 171.565.

      (2) The term of office of each member is four years, but a member serves at the pleasure of the Governor. Before the expiration of the term of a member, the Governor shall appoint a successor whose term begins on July 1 next following. A member is eligible for reappointment, but no member shall serve more than two full terms. If there is a vacancy for any cause, the Governor shall make an appointment to become immediately effective for the unexpired term.

      (3) No member of the council shall be an employee, director or retired employee or director of, or a consultant to, or have any pecuniary interest, other than an incidental interest which is disclosed and made a matter of public record at the time of the appointment to the council, in:

      (a) Any corporation or utility operating or interested in establishing an energy facility in this state; or

      (b) Any manufacturer of equipment related to the operation or establishment of an energy facility in this state.

      (4) No member shall for two years after the expiration of the term of the member accept employment with an owner or operator of an energy facility that is subject to ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992.

      (5) Employment of a person in violation of this section shall be grounds for revocation of any license issued by this state or an agency of this state that is held by the owner or operator of the energy facility that employs the person.

      (6) The State Department of Energy shall provide clerical and staff support to the council and fund the activities of the council through fees collected under ORS 469.421. [Formerly 453.435; 1995 c.551 §12; 2013 c.656 §10]

 

      469.460 Officers; meetings; compensation and expenses. (1) The Energy Facility Siting Council shall annually elect from among its members a chairperson and vice chairperson with such powers and duties as the council imposes in accordance with ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992. The council may meet as often as it requires at a time and place determined by the council. A majority of the members of the council constitutes a quorum. The Governor or the chairperson of the council may call a special meeting, to be held at any place in this state designated by the person calling the meeting, upon 24 hours’ notice to each member and to the public.

      (2) Council members shall be entitled to compensation and expenses as provided in ORS 292.495. [Formerly 453.445; 2021 c.110 §1]

 

      469.470 Powers and duties; rules. The Energy Facility Siting Council shall:

      (1) Conduct and prepare, independently or in cooperation with others, studies, investigations, research and programs relating to all aspects of site selection.

      (2) In accordance with the applicable provisions of ORS chapter 183, and subject to the provisions of ORS 469.501 (3), adopt standards and rules to perform the functions vested by law in the council including the adoption of standards and rules for the siting of energy facilities pursuant to ORS 469.501, and implementation of the energy policy of the State of Oregon set forth in ORS 469.010 and 469.310.

      (3) Encourage voluntary cooperation by the people, municipalities, counties, industries, agriculture, and other pursuits, in performing the functions vested by law in the council.

      (4) Advise, consult, and cooperate with other agencies of the state, political subdivisions, industries, other states, the federal government and affected groups, in furtherance of the purposes of ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992.

      (5) Consult with the Water Resources Commission on the need for power and other areas within the expertise of the council when the Water Resources Commission is determining whether to allocate water for hydroelectric development.

      (6) Perform such other and further acts as may be necessary, proper or desirable to carry out effectively the duties, powers and responsibilities of the council described in ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992. [Formerly 453.455; 1991 c.480 §7; 1993 c.544 §5; 1993 c.569 §19; 1995 c.505 §18]

 

      469.480 Local government advisory group; special advisory groups; compensation and expenses; Electric and Magnetic Field Committee; rules. (1) The Energy Facility Siting Council shall designate as a special advisory group the governing body of any local government within whose jurisdiction the facility is proposed to be located.

      (2) In addition to advisory groups required by subsection (1) of this section the council may establish such special advisory groups as are considered necessary. Such advisory groups shall include membership as determined by the council to represent interests and disciplines as needed to carry out the responsibility assigned to such advisory groups, which shall report findings, recommendations and decisions to the council.

      (3) Subject to applicable laws regulating travel and other expenses of state officers and employees, members of any advisory committee appointed under subsection (1) of this section shall receive no compensation but may receive their actual and necessary travel and other expenses incurred in the performance of their official duties.

      (4) The council by rule shall form an Electric and Magnetic Field Committee which shall meet at the call of the council chair. The committee shall include representatives of the public, utilities, manufacturers and state agencies. The committee shall monitor information being developed on electric and magnetic fields and report the committee’s findings to the council. The council shall report the findings of the Electric and Magnetic Field Committee to the Legislative Assembly. [Formerly 453.475; 1991 c.491 §1; 1993 c.569 §20; 1995 c.551 §17]

 

(Rules; Standards; Compliance)

 

      469.490 Adoption of rules; determination of validity. All rules adopted by the Energy Facility Siting Council pursuant to ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992 shall be adopted in the manner required by ORS chapter 183. The validity of any rule adopted by the council may be determined only upon a petition by any person to the Supreme Court. The petition must be filed within 60 days after the date the rule becomes effective under ORS 183.355. The review by the Supreme Court of the validity of any rule adopted by the council shall otherwise be according to ORS 183.400. The Supreme Court shall give priority on its docket to such a petition for review. [Formerly 453.495; 1995 c.505 §19]

 

      469.500 [Formerly 453.505; repealed by 1993 c.569 §21 (469.501, 469.503, 469.505 and 469.507 enacted in lieu of 469.500 and 469.510)]

 

      469.501 Energy facility siting, construction, operation and retirement standards; exemptions; rules. (1) The Energy Facility Siting Council shall adopt standards for the siting, construction, operation and retirement of facilities. The standards may address but need not be limited to the following subjects:

      (a) The organizational, managerial and technical expertise of the applicant to construct and operate the proposed facility.

      (b) Seismic hazards.

      (c) Areas designated for protection by the state or federal government, including but not limited to monuments, wilderness areas, wildlife refuges, scenic waterways and similar areas.

      (d) The financial ability and qualifications of the applicant.

      (e) Effects of the facility, taking into account mitigation, on fish and wildlife, including threatened and endangered fish, wildlife or plant species.

      (f) Impacts of the facility on historic, cultural or archaeological resources listed on, or determined by the State Historic Preservation Officer to be eligible for listing on, the National Register of Historic Places or the Oregon State Register of Historic Properties.

      (g) Protection of public health and safety, including necessary safety devices and procedures.

      (h) The accumulation, storage, disposal and transportation of nuclear waste.

      (i) Impacts of the facility on recreation, scenic and aesthetic values.

      (j) Reduction of solid waste and wastewater generation to the extent reasonably practicable.

      (k) Ability of the communities in the affected area to provide sewers and sewage treatment, water, storm water drainage, solid waste management, housing, traffic safety, police and fire protection, health care and schools.

      (L) The need for proposed nongenerating facilities as defined in ORS 469.503, consistent with the state energy policy set forth in ORS 469.010 and 469.310. The council may consider least-cost plans when adopting a need standard or in determining whether an applicable need standard has been met. The council shall not adopt a standard requiring a showing of need or cost-effectiveness for generating facilities as defined in ORS 469.503.

      (m) Compliance with the statewide planning goals adopted by the Land Conservation and Development Commission as specified by ORS 469.503.

      (n) Soil protection.

      (o) For energy facilities that emit carbon dioxide, the impacts of those emissions on climate change. For fossil-fueled power plants, as defined in ORS 469.503, the council shall apply a standard as provided for by ORS 469.503 (2).

      (2) The council may adopt exemptions from any need standard adopted under subsection (1)(L) of this section if the exemption is consistent with the state’s energy policy set forth in ORS 469.010 and 469.310.

      (3)(a) The council may issue a site certificate for a facility that does not meet one or more of the applicable standards adopted under subsection (1) of this section if the council determines that the overall public benefits of the facility outweigh any adverse effects on a resource or interest protected by the applicable standards the facility does not meet.

      (b) The council by rule shall specify the criteria by which the council makes the determination described in paragraph (a) of this subsection.

      (4) Notwithstanding subsection (1) of this section, the council may not impose any standard developed under subsection (1)(b), (f), (j) or (k) of this section to approve or deny an application for an energy facility producing power from wind, solar or geothermal energy. However, the council may, to the extent it determines appropriate, apply any standards adopted under subsection (1)(b), (f), (j) or (k) of this section to impose conditions on any site certificate issued for any energy facility. [1993 c.569 §22 (469.501, 469.503, 469.505 and 469.507 enacted in lieu of 469.500 and 469.510); 1995 c.505 §20; 1997 c.428 §3; 2001 c.134 §7; 2013 c.263 §1]

 

      469.503 Requirements for approval of energy facility site certificate; carbon dioxide emissions standard; offset funds; use of offset funds by qualifying organization; rules. In order to issue a site certificate, the Energy Facility Siting Council shall determine that the preponderance of the evidence on the record supports the following conclusions:

      (1) The facility complies with the applicable standards adopted by the council pursuant to ORS 469.501 or the overall public benefits of the facility outweigh any adverse effects on a resource or interest protected by the applicable standards the facility does not meet.

      (2) If the energy facility is a fossil-fueled power plant, the energy facility complies with any applicable carbon dioxide emissions standard adopted by the council or enacted by statute. Base load gas plants shall comply with the standard set forth in subsection (2)(a) of this section. Other fossil-fueled power plants shall comply with any applicable standard adopted by the council by rule pursuant to subsection (2)(b) of this section. Subsections (2)(c) and (d) of this section prescribe the means by which an applicant may comply with the applicable standard.

      (a) The net carbon dioxide emissions rate of the proposed base load gas plant shall not exceed 0.70 pounds of carbon dioxide emissions per kilowatt hour of net electric power output, with carbon dioxide emissions and net electric power output measured on a new and clean basis. Notwithstanding the foregoing, the council may by rule modify the carbon dioxide emissions standard for base load gas plants if the council finds that the most efficient stand-alone combined cycle, combustion turbine, natural gas-fired energy facility that is commercially demonstrated and operating in the United States has a net heat rate of less than 7,200 Btu per kilowatt hour higher heating value adjusted to ISO conditions. In modifying the carbon dioxide emission standard, the council shall determine the rate of carbon dioxide emissions per kilowatt hour of net electric output of such energy facility, adjusted to ISO conditions, and reset the carbon dioxide emissions standard at 17 percent below this rate.

      (b) The council shall adopt carbon dioxide emissions standards for other types of fossil-fueled power plants. Such carbon dioxide emissions standards shall be promulgated by rule. In adopting or amending such carbon dioxide emissions standards, the council shall consider and balance at least the following principles, the findings on which shall be contained in the rulemaking record:

      (A) Promote facility fuel efficiency;

      (B) Promote efficiency in the resource mix;

      (C) Reduce net carbon dioxide emissions;

      (D) Promote cogeneration that reduces net carbon dioxide emissions;

      (E) Promote innovative technologies and creative approaches to mitigating, reducing or avoiding carbon dioxide emissions;

      (F) Minimize transaction costs;

      (G) Include an alternative process that separates decisions on the form and implementation of offsets from the final decision on granting a site certificate;

      (H) Allow either the applicant or third parties to implement offsets;

      (I) Be attainable and economically achievable for various types of power plants;

      (J) Promote public participation in the selection and review of offsets;

      (K) Promote prompt implementation of offset projects;

      (L) Provide for monitoring and evaluation of the performance of offsets; and

      (M) Promote reliability of the regional electric system.

      (c) The council shall determine whether the applicable carbon dioxide emissions standard is met by first determining the gross carbon dioxide emissions that are reasonably likely to result from the operation of the proposed energy facility. Such determination shall be based on the proposed design of the energy facility. The council shall adopt site certificate conditions to ensure that the predicted carbon dioxide emissions are not exceeded on a new and clean basis. For any remaining emissions reduction necessary to meet the applicable standard, the applicant may elect to use any of subparagraphs (A) to (D) of this paragraph, or any combination thereof. The council shall determine the amount of carbon dioxide or other greenhouse gas emissions reduction that is reasonably likely to result from the applicant’s offsets and whether the resulting net carbon dioxide emissions meet the applicable carbon dioxide emissions standard. For purposes of determining the net carbon dioxide emissions, the council shall by rule establish the global warming potential of each greenhouse gas based on a generally accepted scientific method, and convert any greenhouse gas emissions to a carbon dioxide equivalent. Unless otherwise provided by the council by rule, the global warming potential of methane is 23 times that of carbon dioxide, and the global warming potential of nitrous oxide is 296 times that of carbon dioxide. If the council or a court on judicial review concludes that the applicant has not demonstrated compliance with the applicable carbon dioxide emissions standard under subparagraphs (A), (B) or (D) of this paragraph, or any combination thereof, and the applicant has agreed to meet the requirements of subparagraph (C) of this paragraph for any deficiency, the council or a court shall find compliance based on such agreement.

      (A) The facility will sequentially produce electrical and thermal energy from the same fuel source, and the thermal energy will be used to displace another source of carbon dioxide emissions that would have otherwise continued to occur, in which case the council shall adopt site certificate conditions ensuring that the carbon dioxide emissions reduction will be achieved.

      (B) The applicant or a third party will implement particular offsets, in which case the council may adopt site certificate conditions ensuring that the proposed offsets are implemented but shall not require that predicted levels of avoidance, displacement or sequestration of greenhouse gas emissions be achieved. The council shall determine the quantity of greenhouse gas emissions reduction that is reasonably likely to result from each of the proposed offsets based on the criteria in sub-subparagraphs (i) to (iii) of this subparagraph. In making this determination, the council shall not allow credit for offsets that have already been allocated or awarded credit for greenhouse gas emissions reduction in another regulatory setting. In addition, the fact that an applicant or other parties involved with an offset may derive benefits from the offset other than the reduction of greenhouse gas emissions is not, by itself, a basis for withholding credit for an offset.

      (i) The degree of certainty that the predicted quantity of greenhouse gas emissions reduction will be achieved by the offset;

      (ii) The ability of the council to determine the actual quantity of greenhouse gas emissions reduction resulting from the offset, taking into consideration any proposed measurement, monitoring and evaluation of mitigation measure performance; and

      (iii) The extent to which the reduction of greenhouse gas emissions would occur in the absence of the offsets.

      (C) The applicant or a third party agrees to provide funds in an amount deemed sufficient to produce the reduction in greenhouse gas emissions necessary to meet the applicable carbon dioxide emissions standard, in which case the funds shall be used as specified in paragraph (d) of this subsection. Unless modified by the council as provided below, the payment of 57 cents shall be deemed to result in a reduction of one ton of carbon dioxide emissions. The council shall determine the offset funds using the monetary offset rate and the level of emissions reduction required to meet the applicable standard. If a site certificate is approved based on this subparagraph, the council may not adjust the amount of such offset funds based on the actual performance of offsets. After three years from June 26, 1997, the council may by rule increase or decrease the monetary offset rate of 57 cents per ton of carbon dioxide emissions. Any change to the monetary offset rate shall be based on empirical evidence of the cost of offsets and the council’s finding that the standard will be economically achievable with the modified rate for natural gas-fired power plants. Following the initial three-year period, the council may increase or decrease the monetary offset rate no more than 50 percent in any two-year period.

      (D) Any other means that the council adopts by rule for demonstrating compliance with any applicable carbon dioxide emissions standard.

      (d) If the applicant elects to meet the applicable carbon dioxide emissions standard in whole or in part under paragraph (c)(C) of this subsection, the applicant shall identify the qualified organization. The applicant may identify an organization that has applied for, but has not received, an exemption from federal income taxation, but the council may not find that the organization is a qualified organization unless the organization is exempt from federal taxation under section 501(c)(3) of the Internal Revenue Code as amended and in effect on December 31, 1996. The site certificate holder shall provide a bond or comparable security in a form reasonably acceptable to the council to ensure the payment of the offset funds and the amount required under subparagraph (A)(ii) of this paragraph. Such security shall be provided by the date specified in the site certificate, which shall be no later than the commencement of construction of the facility. The site certificate shall require that the offset funds be disbursed as specified in subparagraph (A) of this paragraph, unless the council finds that no qualified organization exists, in which case the site certificate shall require that the offset funds be disbursed as specified in subparagraph (B) of this paragraph.

      (A) The site certificate holder shall disburse the offset funds and any other funds required by sub-subparagraph (ii) of this subparagraph to the qualified organization as follows:

      (i) When the site certificate holder receives written notice from the qualified organization certifying that the qualified organization is contractually obligated to pay any funds to implement offsets using the offset funds, the site certificate holder shall make the requested amount available to the qualified organization unless the total of the amount requested and any amounts previously requested exceeds the offset funds, in which case only the remaining amount of the offset funds shall be made available. The qualified organization shall use at least 80 percent of the offset funds for contracts to implement offsets. The qualified organization shall assess offsets for their potential to qualify in, generate credits in or reduce obligations in other regulatory settings. The qualified organization may use up to 20 percent of the offset funds for monitoring, evaluation, administration and enforcement of contracts to implement offsets.

      (ii) At the request of the qualified organization and in addition to the offset funds, the site certificate holder shall pay the qualified organization an amount equal to 10 percent of the first $500,000 of the offset funds and 4.286 percent of any offset funds in excess of $500,000. This amount shall not be less than $50,000 unless a lesser amount is specified in the site certificate. This amount compensates the qualified organization for its costs of selecting offsets and contracting for the implementation of offsets.

      (iii) Notwithstanding any provision to the contrary, a site certificate holder subject to this subparagraph shall have no obligation with regard to offsets, the offset funds or the funds required by sub-subparagraph (ii) of this subparagraph other than to make available to the qualified organization the total amount required under paragraph (c) of this subsection and sub-subparagraph (ii) of this subparagraph, nor shall any nonperformance, negligence or misconduct on the part of the qualified organization be a basis for revocation of the site certificate or any other enforcement action by the council with respect to the site certificate holder.

      (B) If the council finds there is no qualified organization, the site certificate holder shall select one or more offsets to be implemented pursuant to criteria established by the council. The site certificate holder shall give written notice of its selections to the council and to any person requesting notice. On petition by the State Department of Energy, or by any person adversely affected or aggrieved by the site certificate holder’s selection of offsets, or on the council’s own motion, the council may review such selection. The petition must be received by the council within 30 days of the date the notice of selection is placed in the United States mail, with first-class postage prepaid. The council shall approve the site certificate holder’s selection unless it finds that the selection is not consistent with criteria established by the council. The site certificate holder shall contract to implement the selected offsets within 18 months after commencing construction of the facility unless good cause is shown requiring additional time. The contracts shall obligate the expenditure of at least 85 percent of the offset funds for the implementation of offsets. No more than 15 percent of the offset funds may be spent on monitoring, evaluation and enforcement of the contract to implement the selected offsets. The council’s criteria for selection of offsets shall be based on the criteria set forth in paragraphs (b)(C) and (c)(B) of this subsection and may also consider the costs of particular types of offsets in relation to the expected benefits of such offsets. The council’s criteria shall not require the site certificate holder to select particular offsets, and shall allow the site certificate holder a reasonable range of choices in selecting offsets. In addition, notwithstanding any other provision of this section, the site certificate holder’s financial liability for implementation, monitoring, evaluation and enforcement of offsets pursuant to this subsection shall be limited to the amount of any offset funds not already contractually obligated. Nonperformance, negligence or misconduct by the entity or entities implementing, monitoring or evaluating the selected offset shall not be a basis for revocation of the site certificate or any other enforcement action by the council with respect to the site certificate holder.

      (C) Every qualified organization that has received funds under this paragraph shall, at five-year intervals beginning on the date of receipt of such funds, provide the council with the information the council requests about the qualified organization’s performance. The council shall evaluate the information requested and, based on such information, shall make any recommendations to the Legislative Assembly that the council deems appropriate.

      (e) As used in this subsection:

      (A) “Adjusted to ISO conditions” means carbon dioxide emissions and net electric power output as determined at 59 degrees Fahrenheit, 14.7 pounds per square inch atmospheric pressure and 60 percent humidity.

      (B) “Base load gas plant” means a generating facility that is fueled by natural gas, except for periods during which an alternative fuel may be used and when such alternative fuel use shall not exceed 10 percent of expected fuel use in Btu, higher heating value, on an average annual basis, and where the applicant requests and the council adopts no condition in the site certificate for the generating facility that would limit hours of operation other than restrictions on the use of alternative fuel. The council shall assume a 100 percent capacity factor for such plants and a 30-year life for the plants for purposes of determining gross carbon dioxide emissions.

      (C) “Carbon dioxide equivalent” means the global warming potential of a greenhouse gas reflected in units of carbon dioxide.

      (D) “Fossil-fueled power plant” means a generating facility that produces electric power from natural gas, petroleum, coal or any form of solid, liquid or gaseous fuel derived from such material.

      (E) “Generating facility” means those energy facilities that are defined in ORS 469.300 (11)(a)(A), (B) and (D).

      (F) “Global warming potential” means the determination of the atmospheric warming resulting from the release of a unit mass of a particular greenhouse gas in relation to the warming resulting from the release of the equivalent mass of carbon dioxide.

      (G) “Greenhouse gas” means carbon dioxide, methane and nitrous oxide.

      (H) “Gross carbon dioxide emissions” means the predicted carbon dioxide emissions of the proposed energy facility measured on a new and clean basis.

      (I) “Net carbon dioxide emissions” means gross carbon dioxide emissions of the proposed energy facility, less carbon dioxide or other greenhouse gas emissions avoided, displaced or sequestered by any combination of cogeneration or offsets.

      (J) “New and clean basis” means the average carbon dioxide emissions rate per hour and net electric power output of the energy facility, without degradation, as determined by a 100-hour test at full power completed during the first 12 months of commercial operation of the energy facility, with the results adjusted for the average annual site condition for temperature, barometric pressure and relative humidity and use of alternative fuels, and using a rate of 117 pounds of carbon dioxide per million Btu of natural gas fuel and a rate of 161 pounds of carbon dioxide per million Btu of distillate fuel, if such fuel use is proposed by the applicant. The council may by rule adjust the rate of pounds of carbon dioxide per million Btu for natural gas or distillate fuel. The council may by rule set carbon dioxide emissions rates for other fuels.

      (K) “Nongenerating facility” means those energy facilities that are defined in ORS 469.300 (11)(a)(C) and (E) to (I).

      (L) “Offset” means an action that will be implemented by the applicant, a third party or through the qualified organization to avoid, sequester or displace emissions.

      (M) “Offset funds” means the amount of funds determined by the council to satisfy the applicable carbon dioxide emissions standard pursuant to paragraph (c)(C) of this subsection.

      (N) “Qualified organization” means an entity that:

      (i) Is exempt from federal taxation under section 501(c)(3) of the Internal Revenue Code as amended and in effect on December 31, 1996;

      (ii) Either is incorporated in the State of Oregon or is a foreign corporation authorized to do business in the State of Oregon;

      (iii) Has in effect articles of incorporation that require that offset funds received pursuant to this section are used for offsets that require that decisions on the use of the offset funds are made by a decision-making body composed of seven voting members of which three are appointed by the council, three are Oregon residents appointed by the Bullitt Foundation or an alternative environmental nonprofit organization named by the body, and one is appointed by the applicants for site certificates that are subject to paragraph (d) of this subsection and the holders of such site certificates, and that require nonvoting membership on the body for holders of site certificates that have provided funds not yet disbursed under paragraph (d)(A) of this subsection;

      (iv) Has made available on an annual basis, beginning after the first year of operation, a signed opinion of an independent certified public accountant stating that the qualified organization’s use of funds pursuant to this statute conforms with generally accepted accounting procedures except that the qualified organization shall have one year to conform with generally accepted accounting principles in the event of a nonconforming audit;

      (v) Has to the extent applicable, except for good cause, entered into contracts obligating at least 60 percent of the offset funds to implement offsets within two years after the commencement of construction of the facility; and

      (vi) Has to the extent applicable, except for good cause, complied with paragraph (d)(A)(i) of this subsection.

      (3) Except as provided in ORS 469.504 for land use compliance and except for those statutes and rules for which the decision on compliance has been delegated by the federal government to a state agency other than the council, the facility complies with all other Oregon statutes and administrative rules identified in the project order, as amended, as applicable to the issuance of a site certificate for the proposed facility. If compliance with applicable Oregon statutes and administrative rules, other than those involving federally delegated programs, would result in conflicting conditions in the site certificate, the council may resolve the conflict consistent with the public interest. A resolution may not result in the waiver of any applicable state statute.

      (4) The facility complies with the statewide planning goals adopted by the Land Conservation and Development Commission. [1993 c.569 §23 (469.501, 469.503, 469.505 and 469.507 enacted in lieu of 469.500 and 469.510); 1995 c.505 §21; 1997 c.428 §4; 1999 c.365 §11; 2001 c.134 §10; 2003 c.186 §78; 2011 c.298 §2; 2013 c.263 §2]

 

      469.504 Facility compliance with statewide planning goals; exception; amendment of local plan and land use regulations; conflicts; technical assistance; rules. (1) A proposed facility shall be found in compliance with the statewide planning goals under ORS 469.503 (4) if:

      (a) The facility has received local land use approval under the acknowledged comprehensive plan and land use regulations of the affected local government; or

      (b) The Energy Facility Siting Council determines that:

      (A) The facility complies with applicable substantive criteria from the affected local government’s acknowledged comprehensive plan and land use regulations that are required by the statewide planning goals and in effect on the date the application is submitted, and with any Land Conservation and Development Commission administrative rules and goals and any land use statutes that apply directly to the facility under ORS 197.646;

      (B) For an energy facility or a related or supporting facility that must be evaluated against the applicable substantive criteria pursuant to subsection (5) of this section, that the proposed facility does not comply with one or more of the applicable substantive criteria but does otherwise comply with the applicable statewide planning goals, or that an exception to any applicable statewide planning goal is justified under subsection (2) of this section; or

      (C) For a facility that the council elects to evaluate against the statewide planning goals pursuant to subsection (5) of this section, that the proposed facility complies with the applicable statewide planning goals or that an exception to any applicable statewide planning goal is justified under subsection (2) of this section.

      (2) The council may find goal compliance for a facility that does not otherwise comply with one or more statewide planning goals by taking an exception to the applicable goal. Notwithstanding the requirements of ORS 197.732, the statewide planning goal pertaining to the exception process or any rules of the Land Conservation and Development Commission pertaining to an exception process goal, the council may take an exception to a goal if the council finds:

      (a) The land subject to the exception is physically developed to the extent that the land is no longer available for uses allowed by the applicable goal;

      (b) The land subject to the exception is irrevocably committed as described by the rules of the Land Conservation and Development Commission to uses not allowed by the applicable goal because existing adjacent uses and other relevant factors make uses allowed by the applicable goal impracticable; or

      (c) The following standards are met:

      (A) Reasons justify why the state policy embodied in the applicable goal should not apply;

      (B) The significant environmental, economic, social and energy consequences anticipated as a result of the proposed facility have been identified and adverse impacts will be mitigated in accordance with rules of the council applicable to the siting of the proposed facility; and

      (C) The proposed facility is compatible with other adjacent uses or will be made compatible through measures designed to reduce adverse impacts.

      (3) If compliance with applicable substantive local criteria and applicable statutes and state administrative rules would result in conflicting conditions in the site certificate or amended site certificate, the council shall resolve the conflict consistent with the public interest. A resolution may not result in a waiver of any applicable state statute.

      (4) An applicant for a site certificate shall elect whether to demonstrate compliance with the statewide planning goals under subsection (1)(a) or (b) of this section. The applicant shall make the election on or before the date specified by the council by rule.

      (5) Upon request by the State Department of Energy, the special advisory group established under ORS 469.480 shall recommend to the council, within the time stated in the request, the applicable substantive criteria under subsection (1)(b)(A) of this section. If the special advisory group does not recommend applicable substantive criteria within the time established in the department’s request, the council may either determine and apply the applicable substantive criteria under subsection (1)(b) of this section or determine compliance with the statewide planning goals under subsection (1)(b)(B) or (C) of this section. If the special advisory group recommends applicable substantive criteria for an energy facility described in ORS 469.300 or a related or supporting facility that does not pass through more than one local government jurisdiction or more than three zones in any one jurisdiction, the council shall apply the criteria recommended by the special advisory group. If the special advisory group recommends applicable substantive criteria for an energy facility as defined in ORS 469.300 (11)(a)(C) to (E) or a related or supporting facility that passes through more than one jurisdiction or more than three zones in any one jurisdiction, the council shall review the recommended criteria and determine whether to evaluate the proposed facility against the applicable substantive criteria recommended by the special advisory group, against the statewide planning goals or against a combination of the applicable substantive criteria and statewide planning goals. In making its determination, the council shall consult with the special advisory group and shall consider:

      (a) The number of jurisdictions and zones in question;

      (b) The degree to which the applicable substantive criteria reflect local government consideration of energy facilities in the planning process; and

      (c) The level of consistency of the applicable substantive criteria from the various zones and jurisdictions.

      (6) The council is not subject to ORS 197.180 and a state agency may not require an applicant for a site certificate to comply with any rules or programs adopted under ORS 197.180.

      (7) On or before its next periodic review, each affected local government shall amend its comprehensive plan and land use regulations as necessary to reflect the decision of the council pertaining to a site certificate or amended site certificate.

      (8) Notwithstanding ORS 34.020 or 197.825 or any other provision of law, the affected local government’s land use approval of a proposed facility under subsection (1)(a) of this section and the special advisory group’s recommendation of applicable substantive criteria under subsection (5) of this section shall be subject to judicial review only as provided in ORS 469.403. If the applicant elects to comply with subsection (1)(a) of this section, the provisions of this subsection shall apply only to proposed projects for which the land use approval of the local government occurs after the date a notice of intent or an application for expedited processing is submitted to the State Department of Energy.

      (9) The State Department of Energy, in cooperation with other state agencies, shall provide, to the extent possible, technical assistance and information about the siting process to local governments that request such assistance or that anticipate having a facility proposed in their jurisdiction. [1997 c.428 §5; 1999 c.385 §10; 2001 c.134 §11; 2003 c.186 §79; 2005 c.829 §12]

 

      Note: 469.504 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.505 Consultation with other agencies. (1) In making a determination regarding compliance with statutes, rules and ordinances administered by another agency or compliance with requirements of ORS 469.300 to 469.563 and 469.590 to 469.619 where another agency has special expertise, consultation with the other agency shall occur during the notice of intent and site certificate application process. Any permit application for which the permitting decision has been delegated by the federal government to a state agency other than the Energy Facility Siting Council shall be reviewed, whenever feasible, simultaneously with the council’s review of the site certificate application. Any hearings required on such permit applications shall be consolidated, whenever feasible, with hearings under ORS 469.300 to 469.563 and 469.590 to 469.619.

      (2) Before resolving any conflicting conditions in site certificates or amended site certificates under ORS 469.503 (3) and 469.504, the council shall notify and consult with the agencies and local governments responsible for administering the statutes, administrative rules or substantive local criteria that result in the conflicting conditions regarding potential conflict resolution. [1993 c.569 §24 (469.501, 469.503, 469.505 and 469.507 enacted in lieu of 469.500 and 469.510); 1997 c.428 §9; 1999 c.385 §11]

 

      469.507 Monitoring environmental and ecological effects of construction and operation of energy facilities. (1) The site certificate holder shall establish programs for monitoring the environmental and ecological effects of the construction and operation of facilities subject to site certificates to assure continued compliance with the terms and conditions of the certificate. The programs shall be subject to review and approval by the Energy Facility Siting Council.

      (2) The site certificate holder shall perform the testing and sampling necessary for the monitoring program or require the operator of the plant to perform the necessary testing or sampling pursuant to guidelines established by the Energy Facility Siting Council or its designee. The council and the Director of the State Department of Energy shall have access to operating logs, records and reprints of the certificate holder, including those required by federal agencies.

      (3) The monitoring program may be conducted in cooperation with any federally operated program if the information available from the federal program is acceptable to the council, but no federal program shall be substituted totally for monitoring supervised by the council or its designee.

      (4) The monitoring program shall include monitoring of the transportation process for all radioactive material removed from any nuclear fueled thermal power plant or nuclear installation. [1993 c.569 §25 (469.501, 469.503, 469.505 and 469.507 enacted in lieu of 469.500 and 469.510); 1995 c.505 §22]

 

      469.510 [Formerly 453.515; 1977 c.794 §15; repealed by 1993 c.569 §21 (469.501, 469.503, 469.505 and 469.507 enacted in lieu of 469.500 and 469.510)]

 

      469.520 Cooperation of state governmental bodies; adoption of rules by state agencies on energy facility development. (1) Each state agency and political subdivision in this state that is concerned with energy facilities shall inform the State Department of Energy, promptly of its activities and programs relating to energy and radiation.

      (2) Each state agency proposing to adopt, amend or rescind a rule relating to energy facility development first shall file a copy of its proposal with the council, which may order such changes as it considers necessary to conform to state policy as stated in ORS 469.010 and 469.310.

      (3) The effective date of a rule relating to energy facility development, or an amendment or rescission thereof, shall not be sooner than 10 days subsequent to the filing of a copy of such proposal with the council. [Formerly 453.525]

 

(Plant Operations; Radioactive Wastes)

 

      469.525 Prohibitions on radioactive waste disposal, arrangements for disposal, transportation for disposal and disposal facilities; exceptions; rules. (1) Notwithstanding any other provision of this chapter, no radioactive waste shall be disposed of within this state, no person may arrange for disposal of radioactive waste within this state, no person may transport radioactive waste for disposal in this state and no waste disposal facility for any radioactive waste shall be established, operated or licensed within this state, except as follows:

      (a) Wastes generated before June 1, 1981, through industrial or manufacturing processes which contain only naturally occurring radioactive isotopes which are disposed of at sites approved by the Energy Facility Siting Council in accordance with ORS 469.375.

      (b) Medical, industrial and research laboratory wastes contained in small, sealed, discrete containers in which the radioactive material is dissolved or dispersed in an organic solvent or biological fluid for the purpose of liquid scintillation counting and experimental animal carcasses shall be disposed of or treated at a hazardous waste disposal facility licensed by the Department of Environmental Quality and in a manner consistent with rules adopted by the Department of Environmental Quality after consultation with and approval by the Oregon Health Authority.

      (c) Maintenance of radioactive coal ash at the site of a thermal power plant for which a site certificate has been issued pursuant to this chapter shall not constitute operation of a waste disposal facility so long as such coal ash is maintained in accordance with the terms of the site certificate as amended from time to time as necessary to protect the public health and safety.

      (2) The Energy Facility Siting Council shall, in accordance with the applicable provisions of ORS chapter 183, adopt standards and rules as necessary to prevent the disposal of radioactive waste within this state.

      (3) For purposes of this section, disposal does not include the temporary storage of:

      (a) Radioactive waste used or generated pursuant to a license granted under ORS 453.635;

      (b) Radioactive waste from a nuclear-fueled thermal power plant for which a site certificate has been issued pursuant to this chapter, on the site of that plant, until a permanent storage site is made available by the federal government; or

      (c) Radioactive waste from a reactor for which a site certificate has been issued pursuant to this chapter that is operated by a college, university or graduate center for research purposes and is not connected to the Northwest Power Grid. [Formerly 459.630; 1979 c.283 §2; 1981 c.587 §2; 2009 c.595 §953; 2021 c.38 §2]

 

      469.530 Review and approval of security programs. The Energy Facility Siting Council and the Director of the State Department of Energy shall review and approve all security programs attendant to a nuclear-fueled thermal power plant, a nuclear installation and the transportation of radioactive material derived from or destined for a nuclear-fueled thermal power plant or a nuclear installation. The council shall provide reasonable public notice of a meeting of the council held for purposes of such review and approval. [Formerly 453.535; 1981 c.707 §3; 1989 c.6 §1]

 

      469.533 State Department of Energy rules for health protection and evacuation procedures in nuclear emergency. Notwithstanding ORS chapter 401, the State Department of Energy in cooperation with the Oregon Health Authority and the Oregon Department of Emergency Management shall establish rules for the protection of health and procedures for the evacuation of people and communities who would be affected by radiation in the event of an accident or a catastrophe in the operation of a nuclear power plant or nuclear installation. [Formerly 453.765; 1983 c.586 §43; 2009 c.595 §954; 2009 c.718 §49; 2021 c.539 §88a]

 

      469.534 County procedures. Each county in this state that has a nuclear-fueled thermal power plant located within county boundaries and each county within this state that has any portion of its area located within 50 miles of a site within this state of a nuclear-fueled thermal power plant shall develop written procedures that are compatible with the rules adopted by the State Department of Energy under ORS 469.533. The department shall review the county procedures to determine whether they are compatible with the rules of the department. [1983 c.586 §46]

 

      469.535 Governor may assume control of emergency operations during nuclear accident or catastrophe. Notwithstanding ORS chapter 401, when an emergency exists because of an accident or catastrophe in the operation of a nuclear power plant or nuclear installation or in the transportation of radioactive material, the Governor, for the duration of the emergency, may:

      (1) Assume complete control of all emergency operations in the area affected by the accident or catastrophe, direct all rescue and salvage work and do all things deemed advisable and necessary to alleviate the immediate conditions.

      (2) Assume control of all police and law enforcement activities in such area, including the activities of all local police and peace officers.

      (3) Close all roads and highways in such area to traffic or by order of the Director of the State Department of Energy limit the travel on such roads to such extent as the director deems necessary and expedient.

      (4) Designate persons to coordinate the work of public and private relief agencies operating in such area and exclude from such area any person or agency refusing to cooperate with other agencies engaged in emergency work.

      (5) Require the aid and assistance of any state or other public or quasi-public agencies in the performance of duties and work attendant upon the emergency conditions in such area. [1983 c.586 §47; 2009 c.718 §50]

 

      469.536 Public utility to disseminate information under ORS 469.533. A public utility which operates a nuclear power plant or nuclear installation shall disseminate to the governing bodies of cities and counties that may be affected information approved by the State Department of Energy which explains rules or procedures adopted under ORS 469.533. [Formerly 453.770]

 

      469.540 Reductions or curtailment of operations for violation of safety standards; notice; time period for repairs; transport and disposal of radioactive materials. (1) In instances where the Director of the State Department of Energy determines either from the monitoring or surveillance of the director that there is danger of violation of a safety standard adopted under ORS 469.501 from the continued operation of a plant or installation, the director may order temporary reductions or curtailment of operations until such time as proper safety precautions can be taken.

      (2) An order of reduction or curtailment shall be entered only after notice to the thermal power plant or installation and only after a reasonable time, considering the extent of the danger, has been allowed for repairs or other alterations that would bring the plant or installation into conformity with applicable safety standards.

      (3) The director may order compliance or impose other safety conditions on the transport or disposal of radioactive materials or wastes if the director believes that ORS 469.300 to 469.619 and 469.930 or rules adopted pursuant thereto are being violated or are in danger of being violated. [Formerly 453.545; 1989 c.6 §2; 1993 c.569 §26; 2003 c.186 §31]

 

      469.550 Order for halt of plant operations or activities with radioactive material; notice. (1) Whenever in the judgment of the Director of the State Department of Energy from the results of monitoring or surveillance of operation of any nuclear-fueled thermal power plant or nuclear installation or based upon information from the Energy Facility Siting Council there is cause to believe that there is clear and immediate danger to the public health and safety from continued operation of the plant or installation, the director shall, in cooperation with appropriate state and federal agencies, without hearing or prior notice, order the operation of the plant halted by service of the order on the plant superintendent or other person charged with the operation thereof. Within 24 hours after such order, the director must appear in the appropriate circuit court to petition for the relief afforded under ORS 469.563 and may commence proceedings for revocation of the site certificate if grounds therefor exist.

      (2) Whenever, in the judgment of the director based upon monitoring or surveillance by the director, or based upon information from the council, there is cause to believe that there is clear and immediate danger to the public health and safety from the accumulation or storage of radioactive material located at a nuclear-fueled thermal power plant or a nuclear installation, the director shall in cooperation with appropriate state and federal agencies, without hearing or prior notice, order such accumulation, storage, disposal or transportation halted or immediately impose safety precautions by service of the order on the officer responsible for the accumulation, storage, disposal or transportation. Within 24 hours after such an order, the director must appear in the appropriate circuit court to petition for the relief afforded under ORS 469.563.

      (3)(a) If the director believes there is a clear and immediate danger to public health or safety, the director shall halt the transportation or disposal of radioactive material or waste.

      (b) The director shall serve an order to halt the transportation or disposal of radioactive material on the person responsible for the transport or disposal. The order may be served without prior hearing or notice.

      (c) Within 24 hours after the director serves an order under paragraph (b) of this subsection, the director shall petition the appropriate circuit court for relief under ORS 469.563.

      (4) The Governor, in the absence of the director, may issue orders and petition for judicial relief as provided in this section. [Formerly 453.555; 1977 c.794 §16; 1989 c.6 §3; 2003 c.186 §32]

 

      469.553 Active uranium mill or mill tailings disposal facility site certification required; procedure for review; fees. (1) Any person desiring to construct or operate an active uranium mill or uranium mill tailings disposal facility after June 25, 1979, shall file with the Energy Facility Siting Council a site certificate application.

      (2) The Energy Facility Siting Council shall review an application for a site certificate under this section using the procedure prescribed in ORS 469.350, 469.360, 469.370, 469.375, 469.401 and 469.403, for energy facilities. The council is authorized to assess fees in accordance with ORS 469.421 in connection with site certificates applied for or issued under this section. [1979 c.283 §7; 1987 c.633 §1; 1993 c.569 §27; 1995 c.505 §25]

 

      469.556 Rules governing uranium-related activities. The Energy Facility Siting Council shall adopt rules governing the location, construction and operation of uranium mills and uranium mill tailings disposal facilities and the treatment, storage and disposal of uranium mine overburden for the protection of the public health and safety and the environment. [1979 c.283 §8]

 

      469.559 Cooperative agreements authorized between council and federal officials and agencies; rules; powers of Governor; exception for inactive or abandoned site. (1) Notwithstanding the authority of the Oregon Health Authority pursuant to ORS 453.605 to 453.800 to regulate radiation sources or the requirements of ORS 469.525, the Energy Facility Siting Council may enter into and carry out cooperative agreements with the Secretary of Energy pursuant to Title I and the Nuclear Regulatory Commission pursuant to Title II of the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, and perform or cause to be performed any and all acts necessary to be performed by the state, including the acquisition by condemnation or otherwise, retention and disposition of land or interests therein, in order to implement that Act and rules, standards and guidelines adopted pursuant thereto. The Energy Facility Siting Council may adopt, amend or repeal rules in accordance with ORS chapter 183 and may receive and disburse funds in connection with the implementation and administration of this section.

      (2) The Energy Facility Siting Council and the State Department of Energy may enter into and carry out cooperative agreements and arrangements with any agency of the federal government implementing the Comprehensive Environmental Response, Compensation, and Liability Act, as amended, 42 U.S.C. section 9601 et seq., to clean up wastes and contaminated material, including overburden, created by uranium mining before June 29, 1989. Any such project need not obtain a site certificate from the council, but shall nevertheless comply with all applicable, relevant or appropriate state standards including but not limited to those set forth in ORS 469.375 and rules adopted by the council and other state agencies to implement such standards.

      (3) The Governor may do any and all things necessary to implement the requirements of the federal Acts referred to in subsections (1) and (2) of this section.

      (4) Notwithstanding ORS 469.553, after June 25, 1979, no site certificate is required for the cleanup and disposal of an inactive or abandoned uranium mill tailings site as authorized under subsection (1) of this section and Title I of the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604. [1979 c.283 §9; 1987 c.633 §2; 1989 c.496 §1; 2009 c.595 §955]

 

(Records)

 

      469.560 Records; public inspection; confidential information. (1) Except as provided in subsection (2) of this section and ORS 192.338, 192.345 and 192.355, any information filed or submitted pursuant to ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992 shall be made available for public inspection and copying during regular office hours of the State Department of Energy at the expense of any person requesting copies.

      (2) Any information, other than that relating to the public safety, relating to secret process, device, or method of manufacturing or production obtained in the course of inspection, investigation or activities under ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992 shall be kept confidential and shall not be made a part of public record of any hearing. [Formerly 453.565]

 

(Insurance)

 

      469.561 Property insurance required; exceptions; filing of policy. (1) A person owning and operating a nuclear power plant in this state under a license issued by the United States Nuclear Regulatory Commission or under a site certificate issued under ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992 shall obtain and maintain property insurance in the maximum insurable amount available for each nuclear incident occurring within this state, as required by this section. The insurance shall cover property damage occurring within a nuclear plant and its related or supporting facilities as a result of the nuclear incident.

      (2) Insurance required under this section does not apply to:

      (a) Any claim of an employee of a person obtaining insurance under this section, if the claim is made under a state or federal workers’ compensation Act and if the employee is employed at the site of and in connection with the nuclear power plant at which the nuclear incident occurred; or

      (b) Any claim arising out of an act of war.

      (3) A person obtaining insurance under this section shall maintain insurance for the term of the license issued to the nuclear power plant by the United States Nuclear Regulatory Commission and for any extension of the term, and until all radioactive material has been removed from the nuclear power plant and transportation of the radioactive material from the nuclear power plant has ended.

      (4) A person obtaining insurance under this section shall file a copy of the insurance policy, any amendment to the policy and any superseding insurance policy with the Director of the State Department of Energy.

      (5) Property insurance required under this section is in addition to and not in lieu of insurance coverage provided under the Price-Anderson Act (42 U.S.C. 2210).

      (6) Property insurance required by subsections (1) to (5) of this section may include private insurance, self-insurance, utility industry association self-assurance pooling programs, or a combination of all three.

      (7) A person may fulfill the requirements for an insurance policy under subsections (1) to (5) of this section by obtaining policies of one or more insurance carriers if the policies together meet the requirements of subsections (1) to (5) of this section. [Formerly 469.565]

 

      469.562 Eligible insurers. (1) In order to provide the private insurance specified under ORS 469.561, an insurer must be authorized to provide or transact insurance in this state.

      (2) An insurer providing property insurance required under ORS 469.561 (1) to (5) may obtain reinsurance as defined in ORS 731.126. [Formerly 469.567]

 

(Enforcement)

 

      469.563 Court orders for enforcement. Without prior administrative proceedings, a circuit court may issue such restraining orders, and such temporary and permanent injunctive relief as is necessary to secure compliance with ORS 469.320, 469.405 (3), 469.410, 469.421, 469.430, 469.440, 469.442, 469.507, 469.525 to 469.559, 469.560, 469.561, 469.562, 469.590 to 469.619, 469.930 and 469.992 or with the terms and conditions of a site certificate. [Formerly 469.570; 1999 c.385 §12]

 

      469.564 Records or information for enforcement; correction of violation; determination of compliance; costs. (1) The Director of the State Department of Energy or the Energy Facility Siting Council may obtain from any persons all records or information needed to carry out and enforce ORS 469.525, 469.550 (3) and 469.607. In obtaining records or information under this subsection, the director or the council, with the written consent of the Governor, may subpoena witnesses, material and relevant books, papers, accounts, records and memoranda, may administer oaths and may cause the depositions of persons residing within or without Oregon to be taken in the manner prescribed for depositions in civil actions in circuit courts.

      (2) The director or the council may require a person to take actions as necessary to correct a past or ongoing violation of ORS 469.525, 469.550 (3) or 469.607 or to ensure future compliance with ORS 469.525, 469.550 (3) or 469.607 or rules adopted for the purposes of carrying out ORS 469.525, 469.550 (3) or 469.607. The director or the council shall coordinate with the Department of Environmental Quality prior to ordering any actions under this subsection.

      (3)(a) At any reasonable time, an employee of or a duly authorized and identified representative of the State Department of Energy may enter upon, inspect and obtain samples from any public or private property, premises or place for the purpose of determining compliance with ORS 469.525, 469.550 (3) or 469.607 or rules adopted for the purposes of carrying out ORS 469.525, 469.550 (3) or 469.607.

      (b) If a person refuses to comply with this subsection, the department or a duly authorized and identified representative of the department may obtain a warrant or subpoena to allow the entry, inspection or sampling authorized by this subsection.

      (4)(a) A person found by the director or the council to be in violation of ORS 469.525 shall reimburse the department for all necessary, just and reasonable costs incurred by the department in the investigation of the violation. Department costs may include:

      (A) Legal expenses;

      (B) Expenses incurred in obtaining and inspecting records, information or samples under subsections (1) to (3) of this section; and

      (C) Expenses incurred in issuing any final order or notice of violation.

      (b) Upon request, the department shall provide a detailed justification for all costs charged to a person under this subsection.

      (c) If a dispute arises regarding the necessity or reasonableness of expenses charged to a person under this subsection, the person may seek judicial review of the amount of expenses charged in circuit court as provided in ORS 183.480, 183.484, 183.490 and 183.500. If the person establishes that any of the charges are unnecessary or unreasonable, the department shall refund the amount found to be unnecessary or unreasonable. The person may not waive the right to judicial review by paying the portion of the fee or expense in dispute. [2021 c.38 §4]

 

      Note: 469.564 was added to and made a part of 469.300 to 469.619 by legislative action but was not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.

 

      469.565 [1981 c.866 §§3,4; renumbered 469.561 in 1997]

 

(Oregon Hanford Cleanup Board)

 

      469.566 Legislative findings. (1) The Legislative Assembly finds and declares that Oregon is not assured that the United States Department of Energy will:

      (a) Consider the unique features of Oregon and the needs of the people of Oregon when assessing the Hanford Nuclear Reservation as a potentially suitable location for the long-term disposal of high-level radioactive waste; or

      (b) Ensure adequate opportunity for public participation in the assessment process.

      (2) Over the past 45 years, the United States has developed and produced nuclear weapons at the Hanford Nuclear Reservation and during this period large quantities of radioactive hazardous and chemical wastes have accumulated at the Hanford Nuclear Reservation, and the waste sites pose an immediate and serious long-term threat to the environment and to public health and safety.

      (3) Therefore, the Legislative Assembly declares that it is in the best interests of the State of Oregon to establish an Oregon Hanford Cleanup Board to serve as a focus for the State of Oregon in the development of a state policy to be presented to the federal government, to ensure a maximum of public participation in the assessment and cleanup process. [1987 c.514 §1; 1991 c.562 §3; 2001 c.104 §204; 2003 c.186 §33]

 

      Note: 469.566 to 469.583 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.567 [1981 c.866 §5; renumbered 469.562 in 1997]

 

      469.568 Construction of ORS 469.566 to 469.583. Nothing in ORS 469.566 to 469.583 shall be interpreted by the federal government or the United States Department of Energy as an expression by the people of Oregon to accept the Hanford Nuclear Reservation as the site for the long-term disposal of high-level radioactive waste. [1987 c.514 §2; 2001 c.104 §205]

 

      Note: See note under 469.566.

 

      469.569 Definitions for ORS 469.566 to 469.583. As used in ORS 469.566 to 469.583:

      (1) “Board” means the Oregon Hanford Cleanup Board.

      (2) “High-level radioactive waste” means fuel or fission products from a commercial nuclear reactor after irradiation that is packaged and prepared for disposal.

      (3) “United States Department of Energy” means the federal Department of Energy established under 42 U.S.C.A. 7131 or any successor agency assigned responsibility for the long-term disposal of high-level radioactive waste. [1987 c.514 §3; 2003 c.186 §34]

 

      Note: See note under 469.566.

 

      469.570 [Formerly 453.575; 1995 c.505 §23; renumbered 469.563 in 1997]

 

      469.571 Oregon Hanford Cleanup Board; members; appointment. There is created an Oregon Hanford Cleanup Board that shall consist of the following members:

      (1) The Director of the State Department of Energy or designee;

      (2) The Water Resources Director or designee;

      (3) A representative of the Governor;

      (4) One member representing the Confederated Tribes of the Umatilla Indian Reservation;

      (5) Ten members of the public, appointed by the Governor, one of whom shall be a representative of a local emergency response organization in eastern Oregon and one of whom shall serve as chairperson; and

      (6) Three members of the Senate, appointed by the President of the Senate, and three members of the House of Representatives, appointed by the Speaker of the House of Representatives who shall serve as advisory members without vote. [1987 c.514 §4; 1991 c.562 §1; 1997 c.249 §271; 2003 c.186 §5]

 

      Note: See note under 469.566.

 

      469.572 Compensation of board members. (1) Each member of the Oregon Hanford Cleanup Board shall serve at the pleasure of the appointing authority. For purposes of this subsection, for those members of the board selected by the public advisory committee, the appointing authority shall be the public advisory committee.

      (2) Each public member of the board shall receive compensation and expenses as provided in ORS 292.495. Each legislative member shall receive compensation and expenses as provided in ORS 171.072.

      (3) The board shall be under the supervision of the chairperson. [1987 c.514 §5]

 

      Note: See note under 469.566.

 

      469.573 Purpose of Oregon Hanford Cleanup Board. The Oregon Hanford Cleanup Board:

      (1) Shall serve as the focal point for all policy discussions within the state government concerning the disposal of high-level radioactive waste in the northwest region.

      (2) Shall recommend a state policy to the Governor and to the Legislative Assembly.

      (3) After consultation with the Governor, may make policy recommendations on other issues related to the Hanford Nuclear Reservation at Richland, Washington, including but not limited to defense wastes, disposal and treatment of chemical waste and plutonium production. [1987 c.514 §6; 2001 c.104 §206]

 

      Note: See note under 469.566.

 

      469.574 Duties of Oregon Hanford Cleanup Board; coordination with Washington. In carrying out its purpose as set forth in ORS 469.573, the Oregon Hanford Cleanup Board shall:

      (1) Serve as the initial agency in this state to be contacted by the United States Department of Energy or any other federal agency on any matter related to the long-term disposal of high-level radioactive waste and other issues related to the Hanford Nuclear Reservation.

      (2) Serve as the initial agency in this state to receive any report, study, document, information or notification of proposed plans from the federal government on any matter related to the long-term disposal of high-level radioactive waste or other issues related to the Hanford Nuclear Reservation. Notification of proposed plans includes notification of proposals to conduct field work, on-site evaluation or on-site testing.

      (3) Disseminate or arrange with the United States Department of Energy or other federal agency to disseminate the information received under subsection (2) of this section to appropriate state agencies, local governments, regional planning commissions, American Indian tribal governing bodies, the general public and interested citizen groups who have requested in writing to receive this information.

      (4) Recommend to the Governor and Legislative Assembly appropriate responses to contacts under subsection (1) of this section and information received under subsection (2) of this section if a response is appropriate. The board shall consult with the appropriate state agency, local government, regional planning commission, American Indian tribal governing body, the general public and interested citizen groups in preparing this response.

      (5) Promote and coordinate educational programs which provide information on the nature of high-level radioactive waste, the long-term disposal of this waste, the activities of the board, the activities of the United States Department of Energy and any other federal agency related to the long-term disposal of high-level radioactive waste or other issues related to the Hanford Nuclear Reservation and the opportunities of the public to participate in procedures and decisions related to this waste.

      (6) Review any application to the United States Department of Energy or other federal agency by a state agency, local government or regional planning commission for funds for any program related to the long-term disposal of high-level radioactive waste or other issues related to the Hanford Nuclear Reservation. If the board finds that the application is not consistent with the state’s policy related to such issue or that the application is not in the best interest of the state, the board shall forward its findings to the Governor and the appropriate legislative committee. If the board finds that the application of a state agency is not consistent with the state’s policy related to long-term disposal of high-level radioactive waste or that the application of a state agency is not in the best interest of the state, the findings forwarded to the Governor and legislative committee shall include a recommendation that the Governor act to stipulate conditions for the acceptance of the funds which are necessary to safeguard the interests of the state.

      (7) Monitor activity in Congress and the federal government related to the long-term disposal of high-level radioactive waste and other issues related to the Hanford Nuclear Reservation.

      (8) If appropriate, advise the Governor and the Legislative Assembly to request the Attorney General to intervene in federal proceedings to protect the state’s interests and present the state’s point of view on matters related to the long-term disposal of high-level radioactive waste or other issues related to the Hanford Nuclear Reservation.

      (9) Coordinate with appropriate counterparts and agencies in the State of Washington. [1987 c.514 §7; 1991 c.562 §4; 2001 c.104 §207]

 

      Note: See note under 469.566.

 

      469.575 Duties of chairperson of Oregon Hanford Cleanup Board. The chairperson of the Oregon Hanford Cleanup Board shall:

      (1) Supervise the day-to-day functions of the board;

      (2) Hire, assign, reassign and coordinate the administrative personnel of the board, prescribe their duties and fix their compensation, subject to the State Personnel Relations Law; and

      (3) Request technical assistance from any other state agency. [1987 c.514 §8]

 

      Note: See note under 469.566.

 

      469.576 Review of Hanford as site selected for long-term disposal of high-level radioactive waste. (1) If the United States Department of Energy selects the Hanford Nuclear Reservation as the site for the construction of a repository for the long-term disposal of high-level radioactive waste, the Oregon Hanford Cleanup Board shall review the selected site and the site plan prepared by the United States Department of Energy. In conducting its review the board shall:

      (a) Include a full scientific review of the adequacy of the selected site and of the site plan;

      (b) Use recognized experts;

      (c) Conduct one or more public hearings on the site plan;

      (d) Make available to the public arguments and evidence for and against the site plan; and

      (e) Solicit comments from appropriate state agencies, local governments, regional planning commissions, American Indian tribal governing bodies, the general public and interested citizen groups on the adequacy of the Hanford site and the site plan.

      (2) After completing the review under subsection (1) of this section, the board shall submit a recommendation to the Speaker of the House of Representatives, the President of the Senate and the Governor on whether the state should accept the Hanford site. [1987 c.514 §10; 2001 c.104 §208]

 

      Note: See note under 469.566.

 

      469.577 Lead agency; agreements with federal agencies related to long-term disposal of high-level radioactive waste. (1) In addition to any other duty prescribed by law and subject to the policy direction of the board, a lead agency designated by the Governor shall negotiate written agreements and modifications to those agreements, with the United States Department of Energy or any other federal agency or state on any matter related to the long-term disposal of high-level radioactive waste.

      (2) Any agreement or modification to an agreement negotiated by the agency designated by the Governor under subsection (1) of this section shall be consistent with the policy expressed by the Governor and the Legislative Assembly as developed by the Oregon Hanford Cleanup Board.

      (3) The Oregon Hanford Cleanup Board shall make recommendations to the agency designated by the Governor under subsection (1) of this section concerning the terms of agreements or modifications to agreements negotiated under subsection (1) of this section or other issues related to the Hanford Nuclear Reservation. [1987 c.514 §11; 1991 c.562 §5; 2001 c.104 §209]

 

      Note: See note under 469.566.

 

      469.578 Oregon Hanford Cleanup Board to implement agreements with federal agencies. The Oregon Hanford Cleanup Board shall implement agreements, modifications and technical revisions approved by the agency designated by the Governor under ORS 469.577. In implementing these agreements, modifications and revisions, the board may solicit the views of any appropriate state agency, local government, regional planning commission, American Indian tribal governing body, the general public and interested citizen groups. [1987 c.514 §12]

 

      Note: See note under 469.566.

 

      469.579 Authority to accept moneys; disbursement of funds; rules. The Oregon Hanford Cleanup Board may accept moneys from the United States Department of Energy, other federal agencies, the State of Washington and from gifts and grants received from any other person. Such moneys are continuously appropriated to the board for the purpose of carrying out the provisions of ORS 469.566 to 469.583. The board shall establish by rule a method for disbursing such funds as necessary to carry out the provisions of ORS 469.566 to 469.583, including but not limited to awarding contracts for studies pertaining to the long-term disposal of radioactive waste or other issues related to the Hanford Nuclear Reservation. Any disbursement of funds by the board or the lead agency shall be consistent with the policy established by the board under ORS 469.573. [1987 c.514 §13; 1991 c.562 §6; 2001 c.104 §210; 2003 c.186 §35]

 

      Note: See note under 469.566.

 

      469.580 [1977 c.296 §13; repealed by 1993 c.569 §31]

 

      469.581 Advisory and technical committees. The Oregon Hanford Cleanup Board may establish any advisory and technical committee it considers necessary. Members of any advisory or technical committee established under this section may receive reimbursement for travel expenses incurred in the performance of their duties in accordance with ORS 292.495. [1987 c.514 §14; 1991 c.562 §2]

 

      Note: See note under 469.566.

 

      469.582 Cooperation with Oregon Hanford Cleanup Board; technical assistance from other state agencies. All departments, agencies and officers of this state and its political subdivisions shall cooperate with the Oregon Hanford Cleanup Board in carrying out any of its activities under ORS 469.566 to 469.583 and, at the request of the chairperson, provide technical assistance to the board. [1987 c.514 §15]

 

      Note: See note under 469.566.

 

      469.583 Rules. In accordance with the applicable provisions of ORS chapter 183, the Oregon Hanford Cleanup Board shall adopt rules and standards to carry out the requirements of ORS 469.566 to 469.583. [1987 c.514 §16]

 

      Note: See note under 469.566.

 

(Federal Site Selection)

 

      469.584 Findings. The Legislative Assembly and the people of the State of Oregon find that:

      (1) In order to solve the problem of high-level radioactive waste disposal, Congress established a process for selecting two sites for the safe, permanent and regionally equitable disposal of such waste.

      (2) The process of selecting three sites as final candidates, including the Hanford Nuclear Reservation in the State of Washington, for a first high-level nuclear waste repository by the United States Department of Energy violated the intent and the mandate of Congress.

      (3) The United States Department of Energy has prematurely deferred consideration of numerous potential sites and disposal media that its own research indicates are more appropriate, safer and less expensive.

      (4) Placement of a repository at Hanford without methodical and independently verified scientific evaluation threatens the health and safety of the people and the environment of this state.

      (5) The selection process is flawed and not credible because it did not include independent experts in the selection of the sites and in the review of the selected sites, as recommended by the National Academy of Sciences.

      (6) By postponing indefinitely all site specific work for an eastern repository, the United States Department of Energy has not complied with the intent of Congress expressed in the Nuclear Waste Policy Act, Public Law 97-425, and the fundamental compromise which enabled its enactment. [1987 c.13 §1; 2001 c.104 §211]

 

      Note: 469.584 and 469.585 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.585 Activities of state related to selection of high-level radioactive waste disposal site. In order to achieve complete compliance with federal law and protect the health, safety and welfare of the people of the State of Oregon, the Legislative Assembly, other statewide officials and state agencies shall use all legal means necessary to:

      (1) Suspend the preliminary site selection process for a high-level nuclear waste repository, including the process of site characterization, until there is compliance with the intent of the Nuclear Waste Policy Act;

      (2) Reverse the Secretary of Energy’s decision to postpone indefinitely all site specific work on locating and developing an eastern repository for high-level nuclear waste;

      (3) Insist that the United States Department of Energy’s site selection process, when resumed, considers all acceptable geologic media and results in safe, scientifically justified and regionally and geographically equitable high-level nuclear waste disposal;

      (4) Demand that federal budget actions fully and completely follow the intent of the Nuclear Waste Policy Act;

      (5) Continue to pursue alliances with other states and interested parties, particularly with Pacific Northwest Governors, legislatures and other parties, affected by the site selection process and transportation of high-level nuclear waste; and

      (6) Ensure that Oregon, because of its close geographic and geologic proximity to the proposed Hanford Nuclear Reservation site, be accorded the same status under federal law as a state in which a high-level nuclear repository is proposed to be located. [1987 c.13 §2; 2001 c.104 §212]

 

      Note: See note under 469.584.

 

(Hanford Nuclear Reservation)

 

      469.586 Findings. The Legislative Assembly and the people of the State of Oregon find that:

      (1) The maintenance of healthy, unpolluted river systems, airsheds and land are essential to the economic vitality and well-being of the citizens of the State of Oregon and the Pacific Northwest.

      (2) Radioactive waste stored at the Hanford Nuclear Reservation is already leaking into and contaminating the water table and watershed of the Columbia River and radioactive materials and toxic compounds have been found in plants, animals and waters downstream from the Hanford Nuclear Reservation and constitute a present and potential threat to the health, safety and welfare of the people of the State of Oregon.

      (3) The Hanford Nuclear Reservation is now one of the most radioactively contaminated sites in the world, according to government studies, and will require billions of dollars in costs for cleanup and the ongoing assessment of health effects.

      (4) In November 1980, the people of the State of Oregon, by direct vote in a statewide election, enacted a moratorium on the construction of nuclear power plants, and no nuclear power plants are presently operating in the State of Oregon.

      (5) In May 1987, the people of the State of Oregon, by direct vote in a statewide election, enacted Ballot Measure 1, opposing the disposal of highly radioactive spent fuel from commercial power plants at the Hanford Nuclear Reservation.

      (6) In 1995, the Legislative Assembly resolved that Oregon should have all legal rights in matters affecting the Hanford Nuclear Reservation, including party status in the Hanford tri-party agreement that governs the cleanup of the reservation.

      (7) Throughout the administrations of Presidents Ford, Carter, Reagan and Bush, the policy of the federal government banned the use of plutonium in commercial nuclear power plants due to the risk that the plutonium could be diverted to terrorists and to nations that have not renounced the use of nuclear weapons.

      (8) The federal government has announced that it will process plutonium from weapons with uranium to produce mixed oxide fuel for commercial nuclear power plants and other nuclear facilities. The Hanford Nuclear Reservation, located on the Columbia River, is a primary candidate site being considered for the production facilities.

      (9) The production of mixed oxide fuel will result in enormous new quantities of radioactive and chemical wastes that will present significant additional disposal problems and unknown costs. [1997 c.617 §1]

 

      Note: 469.586 and 469.587 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.587 Position of State of Oregon related to operation of Hanford Nuclear Reservation. The Legislative Assembly and the people of the State of Oregon:

      (1) Declare that the State of Oregon is unalterably opposed to the use of the Hanford Nuclear Reservation for operations that create more contamination at the Hanford Nuclear Reservation, divert resources from cleanup at the Hanford Nuclear Reservation and make the Hanford Nuclear Reservation cleanup more difficult, such as the processing of plutonium to fuel nuclear power plants, reactors or any other facilities, and further declare that vitrification in a safe manner is the preferred means to dispose of excess plutonium, in order to protect human health and the environment.

      (2) Request that the President of the United States and the Secretary of Energy continue their previous policy of banning the use of plutonium to fuel commercial power plants and nuclear facilities.

      (3) Request that the federal government honor the federal government’s original mandate to implement and complete the cleanup and restoration of the Hanford Nuclear Reservation. [1997 c.617 §2]

 

      Note: See note under 469.586.

 

(Siting of Nuclear-Fueled Thermal Power Plants)

 

      469.590 Definitions for ORS 469.590 to 469.595. As used in ORS 469.590 to 469.595:

      (1) “High-level radioactive waste” means spent nuclear fuel or the radioactive by-products from the reprocessing of spent nuclear fuel.

      (2) “Spent nuclear fuel” means nuclear fuel rods or assemblies which have been irradiated in a power reactor and subsequently removed from that reactor. [1981 c.1 §2]

 

      469.593 Findings. The people of this state find that if no permanent repository for high-level radioactive waste is provided by the federal government, the residents of the state may face the undue financial burden of paying for construction of a repository for such wastes. Therefore, the people of this state enact ORS 469.590 to 469.601. [1981 c.1 §1]

 

      469.594 Storage of high-level radioactive waste after expiration of license prohibited; continuing responsibility for storage; implementation agreements. (1) Notwithstanding the definition of a “waste disposal facility” under ORS 469.300, no high-level radioactive waste should be stored at the site of a nuclear-fueled thermal power plant after the expiration of the operating license issued to the nuclear power plant by the United States Nuclear Regulatory Commission.

      (2) Notwithstanding subsection (1) of this section, a person operating a nuclear power plant under a license issued by the United States Nuclear Regulatory Commission shall remain responsible for proper temporary storage of high-level radioactive materials at the site of the nuclear power plant after termination of a license and until such materials are removed from the site for permanent storage.

      (3) The State Department of Energy and the operators of nuclear-fueled thermal plants shall pursue agreements with the United States Department of Energy and the United States Nuclear Regulatory Commission to fulfill the provisions of this section. [1985 c.434 §2; 1991 c.480 §11; 1993 c.569 §28; 1995 c.505 §24; 2001 c.134 §12]

 

      469.595 Condition to site certificate for nuclear-fueled thermal power plant. Before issuing a site certificate for a nuclear-fueled thermal power plant, the Energy Facility Siting Council must find that an adequate repository for the disposal of the high-level radioactive waste produced by the plant has been licensed to operate by the appropriate agency of the federal government. The repository must provide for the terminal disposition of such waste, with or without provision for retrieval for reprocessing. [1981 c.1 §3]

 

      469.597 Election procedure; elector approval required. (1) Notwithstanding the provisions of ORS 469.370, if the Energy Facility Siting Council finds that the requirements of ORS 469.595 have been satisfied and proposes to issue a site certificate for a nuclear-fueled thermal power plant, the proposal shall be submitted to the electors of this state for their approval or rejection at the next available statewide general election. The procedures for submitting a proposal to the electors under this section shall conform, as nearly as possible to those for state measures, including but not limited to procedures for printing related material in the voters’ pamphlet.

      (2) A site certificate for a nuclear-fueled thermal power plant shall not be issued until the electors of this state have approved the issuance of the certificate at an election held pursuant to subsection (1) of this section. [1981 c.1 §§4,5]

 

      469.599 Public Utility Commission’s duty. The Public Utility Commission shall not authorize the issuance of stocks, bonds or other evidences of indebtedness to finance any nuclear-fueled thermal power plant pursuant to ORS 757.400 to 757.463 until the Energy Facility Siting Council has made the finding required under ORS 469.595. [1981 c.1 §6]

 

      469.601 Effect of ORS 469.595 on applications and applicants. ORS 469.595 does not prohibit:

      (1) The Energy Facility Siting Council from receiving and processing applications for site certificates for nuclear-fueled thermal power plants under ORS 469.300 to 469.563, 469.590 to 469.619 and 469.930; or

      (2) An applicant for a site certificate under ORS 469.300 to 469.563, 469.590 to 469.619 and 469.930 from obtaining any other necessary licenses, permits or approvals for the planning or siting of a nuclear-fueled thermal power plant. [1981 c.1 §8]

 

(Transportation of Radioactive Material)

 

      469.603 Intent to regulate transportation of radioactive material. It is the intention of the Legislative Assembly that the state shall regulate the transportation of radioactive material to the full extent allowable under and consistent with federal laws and regulations. [1981 c.707 §2]

 

      469.605 Permit to transport required; application; delegation of authority to issue permits; fees; rules. (1) No person shall ship or transport radioactive material identified by the Energy Facility Siting Council by rule as posing a significant hazard to public health and safety or the environment if improperly transported into or within the State of Oregon without first obtaining a permit from the State Department of Energy.

      (2) Such permit shall be issued for a period not to exceed one year and shall be valid for all shipments within that period of time unless specifically limited by permit conditions.

      (3) Application for a permit under this section shall be made in a form and manner prescribed by the Director of the State Department of Energy and may include:

      (a) A description of the kind, quantity and radioactivity of the material to be transported;

      (b) A description of the route or routes proposed to be taken and the transport schedule;

      (c) A description of any mode of transportation; and

      (d) Other information required by the director to evaluate the application.

      (4) The director shall collect a fee from all applicants for permits under this section in an amount reasonably calculated to provide for the costs to the department of performing the duties of the department under ORS 469.550 (3), 469.563, 469.603 to 469.619 and 469.992. Fees collected under this subsection shall be deposited in the State Department of Energy Account established under ORS 469.120.

      (5) The director shall issue a permit only if the application demonstrates that the proposed transportation will comply with all applicable rules adopted under ORS 469.603 to 469.619 and if the proposed route complies with federal law as provided in ORS 469.606.

      (6) The director may delegate the authority to issue permits for the transportation of radioactive material to the Department of Transportation. In exercising such authority, the Department of Transportation shall comply with the applicable provisions of ORS 469.603 to 469.619 and rules adopted by the director or the Energy Facility Siting Council under ORS 469.603 to 469.619. Permits issued by the Department of Transportation under this subsection shall be enforced according to the provisions of ORS 825.258. The director also may delegate other authority granted under ORS 469.605 to 469.619 to other state agencies if the delegation will maintain or enhance the quality of the transportation safety program. [1981 c.707 §5; 1989 c.6 §4; 1991 c.233 §3; 2003 c.186 §36]

 

      469.606 Determination of best and safest route. (1) Upon receipt of an application required under ORS 469.605 for which radioactive material is proposed to be transported by highway, the State Department of Energy shall confer with the following persons to determine whether the proposed route is safe, and complies with applicable routing requirements of the United States Department of Transportation and the United States Nuclear Regulatory Commission:

      (a) The Oregon Department of Transportation, or a designee of the Oregon Department of Transportation;

      (b) The Energy Facility Siting Council, or a designee of the Energy Facility Siting Council; and

      (c) The Oregon Transportation Commission, or a designee of the Oregon Transportation Commission.

      (2) If, after consultation with the persons set forth in subsection (1) of this section, a determination is made that the proposed route is not the best and safest route for transporting the material, the Director of the State Department of Energy shall deny the application except as provided in subsection (3) of this section.

      (3) If the applicant is prohibited by a statute, rule or other action of an adjacent state or a political subdivision in an adjacent state from using the route that complies with federal law, the director:

      (a) Shall petition the United States Department of Transportation for an administrative determination of preemption of the ban, pursuant to section 13 of the Hazardous Materials Transportation Uniform Safety Act of 1990, P.L. 101-615.

      (b) May issue a permit as provided under ORS 469.605 (5) with conditions necessary to ensure safe transport over a route available to the applicant, until the United States Department of Transportation determines whether the prohibition by the other state or political subdivision is preempted. [1991 c.233 §2; 2003 c.186 §37]

 

      469.607 Authority of council; rules. (1) After consultation with the Department of Transportation and other appropriate state, local and federal agencies, the Energy Facility Siting Council by rule:

      (a) May fix requirements for notification, record keeping, reporting, packaging and emergency response;

      (b) May designate those routes by highway, railroad, waterway and air where transportation of radioactive material can be accomplished safely;

      (c) May specify conditions of transportation for certain classes of radioactive material, including but not limited to, specific routes, permitted hours of movement, requirements for communications capabilities between carriers and emergency response agencies, speed limits, police escorts, checkpoints, operator or crew training or other operational requirements to enhance public health and safety; and

      (d) May establish requirements for insurance, bonding or other indemnification on the part of any person transporting radioactive material into or within the State of Oregon under ORS 469.603 to 469.619 and 469.992.

      (2) The requirements imposed by subsection (1) of this section must be consistent with federal Department of Transportation and Nuclear Regulatory Commission rules.

      (3) Rules adopted under this section shall be adopted in accordance with the provisions of ORS chapter 183. [1981 c.707 §6; 1989 c.6 §5; 1995 c.733 §45]

 

      469.609 Annual report to state agencies and local governments on shipment of radioactive wastes. Annually, the Director of the State Department of Energy shall report to interested state agencies and all local government agencies trained under ORS 469.611 on shipment of radioactive material made during the preceding year. The director’s report shall include:

      (1) The type and quantity of material transported;

      (2) Any mode of transportation used;

      (3) The route or routes taken; and

      (4) Any other information at the discretion of the director. [1981 c.707 §8; 1989 c.6 §6; 2003 c.186 §38]

 

      469.611 Emergency preparedness and response program; radiation emergency response team; training. Notwithstanding ORS chapter 401:

      (1) The Director of the State Department of Energy shall coordinate emergency preparedness and response with appropriate agencies of government at the local, state and national levels to ensure that the response to a radioactive material transportation accident is swift and appropriate to minimize damage to any person, property or wildlife. This program shall include the preparation of localized plans setting forth agency responsibilities for on-scene response.

      (2) The director shall:

      (a) Apply for federal funds as available to train, equip and maintain an appropriate response capability at the state and local level; and

      (b) Request all available training and planning materials.

      (3) The Oregon Health Authority shall maintain a trained and equipped radiation emergency response team available at all times for dispatch to any radiological emergency. Before arrival of the team at the scene of a radiological accident, the director may designate other technical advisors to work with the local response agencies.

      (4) The authority shall assist the director to ensure that all emergency services organizations along major transport routes for radioactive materials are offered training and retraining in the proper procedures for identifying and dealing with a radiological accident pending the arrival of persons with technical expertise. The authority shall report annually to the director on training of emergency response personnel. [1981 c.707 §9; 1983 c.586 §44; 1989 c.6 §7; 2003 c.186 §39; 2007 c.71 §151; 2009 c.595 §956; 2009 c.718 §51]

 

      469.613 Records; inspection; rules. (1) Any person obtaining a permit under ORS 469.605 shall establish and maintain any records, make any reports and provide any information as the Energy Facility Siting Council may by rule or order require to assure compliance with the conditions of the permit or other rules affecting the transportation of radioactive materials and submit the reports and make the records and information available at the request of the Director of the State Department of Energy. Any requirement imposed by the council under this subsection shall be consistent with regulations of the United States Department of Transportation and the United States Nuclear Regulatory Commission.

      (2) The director may authorize any employee or agent of the director to enter upon, inspect and examine, at reasonable times and in a reasonable manner for the purpose of administration or enforcement of the provisions of ORS 469.550, 469.563, 469.603 to 469.619 and 469.992 or rules adopted thereunder, the records and property of persons within this state who have applied for permits under ORS 469.605.

      (3) The director shall provide for:

      (a) The inspection of each highway route controlled shipment prior to or upon entry of the shipment into this state or at the point of origin for the transportation of highway route controlled shipments within the state; and

      (b) Inspection of a representative sample of shipments containing material required to bear a radioactive placard as specified by federal regulations. [1981 c.707 §10; 1989 c.6 §8; 2003 c.186 §40]

 

      469.615 Indemnity for claims against state insurance coverage certification; reimbursement for costs incurred in nuclear incident. (1) A person transporting radioactive materials in this state shall indemnify the State of Oregon and its political subdivisions and agents for any claims arising from the release of radioactive material during that transportation and pay for the cost of response to an accident involving the radioactive material.

      (2) With respect to radioactive materials, the Director of the State Department of Energy shall ascertain and certify that insurance coverage required under 42 U.S.C. 2210 is in force and effect at the time the permit is issued under ORS 469.605.

      (3) A person who owns, designs or maintains facilities, structures, vehicles or equipment used for handling, transportation, shipment, storage or disposal of nuclear material shall reimburse the state for all expenses reasonably incurred by the state or a political subdivision of the state, in protecting the public health and safety and the environment from a nuclear incident or the imminent danger of a nuclear incident caused by the person’s acts or omissions. These expenses include but need not be limited to, costs incurred for precautionary evacuations, emergency response measures and decontamination or other cleanup measures. As used in this subsection “nuclear incident” has the meaning given that term in 42 U.S.C. 2014(q).

      (4) Nothing in subsection (3) of this section shall affect any provision of subsection (1) or (2) of this section. [1981 c.707 §11; 1987 c.705 §9; 1989 c.6 §9]

 

      469.617 Report to legislature; content. The Director of the State Department of Energy shall prepare and submit to the Governor for transmittal to the Legislative Assembly, on or before the beginning of each odd-numbered year regular legislative session, a comprehensive report on the transportation of radioactive material in Oregon and provide an evaluation of the adequacy of the state’s emergency response agencies. The report shall include, but need not be limited to:

      (1) A brief description and compilation of any accidents and casualties involving the transportation of radioactive material in Oregon;

      (2) An evaluation of the effectiveness of enforcement activities and the degree of compliance with applicable rules;

      (3) A summary of outstanding problems confronting the State Department of Energy in administering ORS 469.550, 469.563, 469.603 to 469.619 and 469.992; and

      (4) Such recommendations for additional legislation as the Energy Facility Siting Council considers necessary and appropriate. [1981 c.707 §12; 1989 c.6 §10; 2011 c.545 §58]

 

      469.619 State Department of Energy to make federal regulations available. The State Department of Energy shall maintain and make available copies of all federal regulation and federal code provisions referred to in ORS 469.300, 469.550, 469.563, 469.603 to 469.619 and 469.992. [1981 c.707 §14; 1989 c.6 §11]

 

      469.621 [1981 c.707 §7; repealed by 1993 c.742 §101]

 

RESIDENTIAL ENERGY CONSERVATION ACT

 

(Investor-Owned Utilities)

 

      469.631 Definitions for ORS 469.631 to 469.645. As used in ORS 469.631 to 469.645:

      (1) “Cash payment” means a payment made by the investor-owned utility to the dwelling owner or to the contractor on behalf of the dwelling owner for energy conservation measures.

      (2) “Commercial lending institution” means any bank, mortgage banking company, trust company, savings bank, savings and loan association, credit union, national banking association, federal savings and loan association or federal credit union maintaining an office in this state.

      (3) “Commission” means the Public Utility Commission of Oregon.

      (4) “Cost-effective” means that an energy conservation measure that provides or saves a specific amount of energy during its life cycle results in the lowest present value of delivered energy costs of any available alternative. However, the present value of the delivered energy costs of an energy conservation measure shall not be treated as greater than that of a nonconservation energy resource or facility unless that cost is greater than 110 percent of the present value of the delivered energy cost of the nonconservation energy resource or facility.

      (5) “Dwelling” means real or personal property within the state inhabited as the principal residence of a dwelling owner or a tenant. “Dwelling” includes a manufactured dwelling as defined in ORS 446.003, a floating home as defined in ORS 830.700 and a single unit in multiple-unit residential housing. “Dwelling” does not include a recreational vehicle as defined in ORS 174.101.

      (6) “Dwelling owner” means the person:

      (a) Who has legal title to a dwelling, including the mortgagor under a duly recorded mortgage of real property, the trustor under a duly recorded deed of trust or a purchaser under a duly recorded contract for the purchase of real property; and

      (b) Whose dwelling receives space heating from the investor-owned utility.

      (7) “Energy audit” means:

      (a) The measurement and analysis of the heat loss and energy utilization efficiency of a dwelling;

      (b) An analysis of the energy savings and dollar savings potential that would result from providing energy conservation measures for the dwelling;

      (c) An estimate of the cost of the energy conservation measures that includes:

      (A) Labor for the installation of items designed to improve the space heating and energy utilization efficiency of the dwelling; and

      (B) The items installed; and

      (d) A preliminary assessment, including feasibility and a range of costs, of the potential and opportunity for installation of:

      (A) Passive solar space heating and solar domestic water heating in the dwelling; and

      (B) Solar swimming pool heating, if applicable.

      (8) “Energy conservation measures” means measures that include the installation of items and the items installed to improve the space heating and energy utilization efficiency of a dwelling. These items include, but are not limited to, caulking, weatherstripping and other infiltration preventative materials, ceiling and wall insulation, crawl space insulation, vapor barrier materials, timed thermostats, insulation of heating ducts, hot water pipes and water heaters in unheated spaces, storm doors and windows, double glazed windows and dehumidifiers. “Energy conservation measures” does not include the dwelling owner’s own labor.

      (9) “Investor-owned utility” means an electric or gas utility regulated by the commission as a public utility under ORS chapter 757.

      (10) “Residential customer” means a dwelling owner or tenant who, either directly or indirectly, pays a share of the cost for service billed by an investor-owned utility for electric or natural gas service received at the dwelling.

      (11) “Space heating” means the heating of living space within a dwelling.

      (12) “Tenant” means a tenant as defined in ORS 90.100 or any other tenant. [1981 c.778 §2; 1989 c.233 §1; 1989 c.648 §66; 1995 c.551 §13; 2003 c.186 §41; 2019 c.422 §34]

 

      469.633 Investor-owned utility program. Each investor-owned utility shall have an approved residential energy conservation program that, to the Public Utility Commission’s satisfaction:

      (1) Makes available to all residential customers of the utility information about:

      (a) Energy conservation measures; and

      (b) Energy conservation measure financing available to dwelling owners.

      (2) Provides within 60 days of a request by a residential customer or a dwelling owner, assistance and technical advice concerning various methods of saving energy in that customer’s or dwelling owner’s dwelling including, but not limited to, an energy audit of the customer’s or dwelling owner’s dwelling.

      (3) Provides financing for cost-effective energy conservation measures approved by the commission to a dwelling owner who occupies the dwelling as a residential customer or rents the dwelling to a tenant who is a residential customer. The minimum financing program shall give the dwelling owner a choice between a cash payment and a loan. The dwelling owner may not receive both a cash payment and a loan. Completion of an energy audit of the dwelling offered under the program required by this section or described in ORS 469.685 shall be a condition of eligibility for either a cash payment or a loan. Unless the commission approves higher levels of assistance, the financing program shall provide:

      (a) The following minimum levels of assistance:

      (A) A loan for a dwelling owner with approved credit upon the following terms approved by the commission:

      (i) A principal amount of up to $5,000;

      (ii) For an electric utility, an interest rate that does not exceed six and one-half percent annually or, for a gas utility, an annual interest rate 10 percentage points lower than the rate published by the Federal Housing Administration for Title I property improvement loans (24 C.F.R. 201.4 (a)) on the date of the loan application, but not lower than six and one-half percent or higher than 12 percent; and

      (iii) A reasonable repayment period that does not exceed 10 years; and

      (B) A cash payment to a dwelling owner eligible under ORS 469.641 for the lesser of:

      (i) Twenty-five percent of the cost of the energy conservation measures provided in the dwelling; or

      (ii) $350.

      (b) That an otherwise eligible dwelling owner may obtain up to $5,000 in loans or $350 in cash payments for each dwelling.

      (c) That there may be up to two loans or cash payments provided for each dwelling.

      (d) That a dwelling owner who acquires a dwelling for which a previous loan was obtained under this section and ORS 469.631 may obtain a loan or a cash payment for energy conservation measures for the newly acquired dwelling under circumstances including, but not necessarily limited to, when:

      (A) The new dwelling owner chooses the same financing option chosen by the previous dwelling owner who obtained financing under ORS 469.631 to 469.645; and

      (B) There remain cost-effective energy conservation measures to be undertaken with regard to the dwelling.

      (e) If the commission so determines, that energy conservation measures for any of the following building and improvement activities may not be financed under the financing program:

      (A) Construction of a new dwelling; or

      (B) If the construction increases or otherwise changes the living space in the dwelling:

      (i) An addition or substantial alteration; or

      (ii) Remodeling.

      (f) If the investor-owned utility so determines, that no cash payment shall be allowed or paid for the cost of energy conservation measures provided more than one year before the date of the application for payment.

      (4) Provides for verification through a reasonable number of inspections that energy conservation measures financed by the investor-owned utility are installed. The verification provisions of the residential energy conservation program shall further provide that:

      (a) An installation shall be performed in such a workmanlike manner and with such materials as to satisfy prevailing industry standards; and

      (b) The investor-owned utility shall provide a post-installation inspection upon the dwelling owner’s request.

      (5) For an electric utility, provides, upon the dwelling owner’s request, information relevant to the specific site of a dwelling with access to:

      (a) Water resources that have hydroelectric potential;

      (b) Wind, which means the natural movement of air at an annual average speed of at least eight miles an hour; or

      (c) A resource area known to have geothermal space heating potential.

      (6) Provides that the investor-owned utility will mail to a dwelling owner an offer to provide energy conservation measures in accordance with ORS 469.631 to 469.645 when a tenant who is the residential customer:

      (a) Requests that the offer be mailed to the dwelling owner; and

      (b) Furnishes the dwelling owner’s name and address with the request. [1981 c.778 §3; 1985 c.745 §6; 1989 c.233 §2; 1991 c.67 §141; 1991 c.78 §1]

 

      469.634 Contributions for urban and community forest activities by customers of investor-owned utilities; rules; uses. (1) The Public Utility Commission of Oregon by rule shall establish a system to allow customers of investor-owned utilities to voluntarily contribute an amount that is to be used for urban and community forest activities within the area served by the utility. The amount shall be in addition to the customer’s utility bill. Investor-owned utilities may choose to use the system established by the commission.

      (2) The utility shall pay to the State Forester the amount designated under subsection (1) of this section. The State Forester shall deposit the moneys collected under this section into the Urban and Community Forestry Subaccount established under ORS 526.060.

      (3) The State Forester shall use the moneys collected under this section for urban and community forest activities. The State Forester by rule, in consultation with the Public Utility Commission of Oregon and local utilities, shall establish guidelines to distribute moneys collected under this section through the Urban and Community Forestry Assistance Program. The guidelines shall include a requirement that moneys are distributed for energy conservation, by means of tree plantings, care and maintenance.

      (4) A utility shall not use more than 16 percent of the moneys collected under this section for administrative expenses. The State Forester shall not use more than 16 percent of the moneys collected under this section for administrative expenses.

      (5) As used in this section, “urban and community forest activities” means activities that promote cost-effective energy conservation. These activities may include the planting, managing and maintaining of residential, street and park trees on public and private land. [1993 c.388 §2]

 

      469.635 Alternative program of investor-owned utilities. (1) An investor-owned utility may meet the program submission requirements of ORS 469.633 by submitting only the portions of its residential energy conservation program that are added to or revised in its program approved under section 4, chapter 889, Oregon Laws 1977, in order to make that earlier program fulfill the requirements of ORS 469.633.

      (2) An investor-owned utility shall offer a dwelling owner a financing program for cost-effective energy conservation measures that includes the option of a cash payment or a loan unless the investor-owned utility offers another financing program determined by the Public Utility Commission to meet or exceed the program required in ORS 469.633 (3). A program shall be considered to meet or exceed the program required in ORS 469.633 (3) if it includes a financial incentive to the residential customer with a present value on November 1, 1981, that is equal to or greater than the present value of the larger of:

      (a) The loan subsidy pursuant to ORS 469.633 (3)(a)(A); or

      (b) The cash payment pursuant to ORS 469.633 (3)(a)(B).

      (3) An investor-owned utility that has adopted an approved residential energy conservation services program under the National Energy Conservation Policy Act (Public Law 95-619, as amended on November 1, 1981) or signed an energy conservation agreement with the Bonneville Power Administration of the United States Department of Energy for a residential weatherization program under section 6(a) of the Pacific Northwest Electric Power Planning and Conservation Act (Public Law 96-501, as adopted December 5, 1980) that is determined by the commission to meet or exceed the requirements in ORS 469.633 and 469.641 shall not be required to submit a separate program. However, the provisions of ORS 469.637, 469.639, 469.643 and 469.645 nevertheless shall be applicable.

      (4) In addition to the residential energy conservation program required in ORS 469.633, an investor-owned utility may offer other energy conservation programs if the commission determines the programs will promote cost-effective energy conservation. [1981 c.778 §7; 1991 c.78 §2]

 

      469.636 Additional financing program by investor-owned utility for rental dwelling. In addition to the residential energy conservation program approved under ORS 469.633, an investor-owned utility may offer an additional financing program for energy conservation measures for a dwelling owner who rents the dwelling to a tenant whose dwelling unit receives energy for space heating from the investor-owned utility. The financing program may consist, at a minimum, of either of the following:

      (1) Offering low-interest loans to fund the entire cost of installed energy conservation measures up to $5,000 per dwelling unit. In addition to the loan subsidy provided under ORS 469.633 (3), the loan shall be further subsidized by applying the present value to the public utility of the tax credit received under ORS 469B.130 to 469B.169. Any portion of the present value of the tax credit shall accrue to the dwelling owner rather than to the investor-owned utility.

      (2) Offering cash payments in addition to the cash payments required in ORS 469.633 (3). The additional cash payment shall be equal to the present value of the tax credit received under ORS 469B.130 to 469B.169. [1985 c.745 §11; 1989 c.765 §9]

 

      469.637 Energy conservation part of utility service of investor-owned utility. The provision of energy conservation measures to a dwelling shall be considered part of the utility service rendered by the investor-owned utility. [1981 c.778 §4]

 

      469.639 Billing for energy conservation measures. (1) Except as provided in subsection (2) of this section, the Public Utility Commission may require as part of an investor-owned utility residential energy conservation program that, for dwelling owners with approved credit, the utility add to the periodic utility bill for the owner-occupied dwelling for which energy conservation measures have been provided pursuant to ORS 469.631 to 469.645 an amount agreed to between the dwelling owner and the investor-owned utility.

      (2) The commission shall allow an investor-owned utility to charge or bill a dwelling owner separately from the periodic utility bill for energy conservation measures provided pursuant to ORS 469.631 to 469.645 if that utility wishes to do so. [1981 c.778 §5]

 

      469.641 Conditions for cash payments to dwelling owner by investor-owned utility. Except as provided in section 31, chapter 778, Oregon Laws 1981, an investor-owned utility shall not make a cash payment to a dwelling owner for energy conservation measures unless:

      (1) The measures were provided in the dwelling on or after November 1, 1981; and

      (2) The measures will not be paid for with other investor-owned utility grants or loans. [1981 c.778 §6; 1991 c.877 §39]

 

      469.643 Formula for customer charges; rules. The Public Utility Commission shall adopt by rule a formula under which the investor-owned utility shall charge all customers to recover:

      (1) The cost to the investor-owned utility of the services required to be provided under ORS 469.633; and

      (2) Any bad debts, including casualty losses, attributable to dwelling owner default on a loan for energy conservation measures. [1981 c.778 §8]

 

      469.645 Implementation of program by investor-owned utility. After the Public Utility Commission has approved the residential energy conservation program of an investor-owned utility required by ORS 469.633, the investor-owned utility promptly shall implement that program. [1981 c.778 §9]

 

(Publicly Owned Utilities)

 

      469.649 Definitions for ORS 469.649 to 469.659. As used in ORS 469.649 to 469.659:

      (1) “Cash payment” means a payment made by the publicly owned utility to the dwelling owner or to the contractor on behalf of the dwelling owner for energy conservation measures.

      (2) “Commercial lending institution” means any bank, mortgage banking company, trust company, savings bank, savings and loan association, credit union, national banking association, federal savings and loan association or federal credit union maintaining an office in this state.

      (3) “Cost-effective” means that an energy conservation measure that provides or saves a specific amount of energy during its life cycle results in the lowest present value of delivered energy costs of any available alternative. However, the present value of the delivered energy costs of an energy conservation measure shall not be treated as greater than that of a nonconservation energy resource or facility unless that cost is greater than 110 percent of the present value of the delivered energy cost of the nonconservation energy resource or facility.

      (4) “Dwelling” means real or personal property within the state inhabited as the principal residence of a dwelling owner or a tenant. “Dwelling” includes a manufactured dwelling as defined in ORS 446.003, a floating home as defined in ORS 830.700 and a single unit in multiple-unit residential housing. “Dwelling” does not include a recreational vehicle as defined in ORS 174.101.

      (5) “Dwelling owner” means the person:

      (a) Who has legal title to a dwelling, including the mortgagor under a duly recorded mortgage of real property, the trustor under a duly recorded deed of trust or a purchaser under a duly recorded contract for the purchase of real property; and

      (b) Whose dwelling receives space heating from the publicly owned utility.

      (6) “Energy audit” means:

      (a) The measurement and analysis of the heat loss and energy utilization efficiency of a dwelling;

      (b) An analysis of the energy savings and dollar savings potential that would result from providing energy conservation measures for the dwelling;

      (c) An estimate of the cost of the energy conservation measures that includes:

      (A) Labor for the installation of items designed to improve the space heating and energy utilization efficiency of the dwelling; and

      (B) The items installed; and

      (d) A preliminary assessment, including feasibility and a range of costs, of the potential and opportunity for installation of:

      (A) Passive solar space heating and solar domestic water heating in the dwelling; and

      (B) Solar swimming pool heating, if applicable.

      (7) “Energy conservation measures” means measures that include the installation of items and the items installed to improve the space heating and energy utilization efficiency of a dwelling. These items include, but are not limited to, caulking, weatherstripping and other infiltration preventative materials, ceiling and wall insulation, crawl space insulation, vapor barrier materials, timed thermostats, insulation of heating ducts, hot water pipes and water heaters in unheated spaces, storm doors and windows, double glazed windows and dehumidifiers. “Energy conservation measures” does not include the dwelling owner’s own labor.

      (8) “Publicly owned utility” means a utility that:

      (a) Is owned or operated in whole or in part, by a municipality, cooperative association or people’s utility district; and

      (b) Distributes electricity.

      (9) “Residential customer” means a dwelling owner or tenant who is billed by a publicly owned utility for electric service received at the dwelling.

      (10) “Space heating” means the heating of living space within a dwelling.

      (11) “Tenant” means a tenant as defined in ORS 90.100 or any other tenant. [1981 c.778 §10; 1989 c.648 §67; 1995 c.551 §14; 2003 c.186 §42; 2019 c.422 §35]

 

      469.651 Publicly owned utility program. Within 30 days after November 1, 1981, each publicly owned utility shall submit to the Director of the State Department of Energy a residential energy conservation program that:

      (1) Makes available to all residential customers of the utility information about:

      (a) Energy conservation measures; and

      (b) Energy conservation measure financing available to dwelling owners.

      (2) Provides within 60 days of a request by a residential customer of the publicly owned utility or a dwelling owner, assistance and technical advice concerning various methods of saving energy in that customer’s or dwelling owner’s dwelling including, but not limited to, an energy audit of the customer’s or dwelling owner’s dwelling.

      (3) Provides financing for cost-effective energy conservation measures at the request of a dwelling owner who occupies the dwelling as a residential customer or rents the dwelling to a tenant who is a residential customer. The financing program shall give the dwelling owner a choice between a cash payment and a loan. The dwelling owner may not receive both a cash payment and a loan. Completion of an energy audit of the dwelling offered under the program required by this section or described in ORS 469.685 shall be a condition of eligibility for either a cash payment or a loan. The financing program shall provide:

      (a) The following minimum levels of assistance:

      (A) A loan for a dwelling owner with approved credit upon the following terms:

      (i) A principal amount of up to $4,000; or

      (ii) An interest rate that does not exceed six and one-half percent annually; and

      (iii) A reasonable repayment period that does not exceed 10 years; and

      (B) A cash payment to a dwelling owner eligible under ORS 469.657 for the lesser of:

      (i) Twenty-five percent of the cost of the energy conservation measures provided in the dwelling; or

      (ii) $350;

      (b) That an otherwise eligible dwelling owner may obtain up to $4,000 in loans or $350 in cash payments for each dwelling;

      (c) That there may be up to $4,000 in loans or $350 in cash payments for each dwelling;

      (d) That a change in ownership of a dwelling shall not prevent the new dwelling owner from obtaining a loan or a cash payment for energy conservation measures for the newly acquired dwelling under circumstances including, but not necessarily limited to, when:

      (A) The new dwelling owner chooses the same financing option chosen by the previous dwelling owner who obtained financing under ORS 469.649 to 469.659; and

      (B) The amount of the financing is within the limit for that dwelling prescribed in paragraph (c) of this subsection;

      (e) If the publicly owned utility so determines, that energy conservation measures for any of the following building and improvement activities may not be financed under the financing program:

      (A) Construction of a new dwelling; or

      (B) If the construction increases or otherwise changes the living space in the dwelling:

      (i) An addition or substantial alteration; or

      (ii) Remodeling; and

      (f) If the publicly owned utility so determines, that no cash payment shall be allowed or paid for the cost of energy conservation measures provided more than one year before the date of the application for payment.

      (4) Provides for verification through a reasonable number of inspections that energy conservation measures financed by the publicly owned utility are installed. The verification provisions of the residential energy conservation program shall further provide that:

      (a) An installation shall be performed in such a workmanlike manner and with such materials as to satisfy prevailing industry standards; and

      (b) The publicly owned utility shall provide a post-installation inspection upon the dwelling owner’s request.

      (5) Provides, upon the dwelling owner’s request, information relevant to the specific site of a dwelling with access to:

      (a) Water resources that have hydroelectric potential;

      (b) Wind, which means the natural movement of air at an annual average speed of at least eight miles an hour; or

      (c) A resource area known to have geothermal space-heating potential.

      (6) Provides that the publicly owned utility will mail to a dwelling owner an offer to provide energy conservation measures in accordance with ORS 469.649 to 469.659 when a tenant who is the residential customer:

      (a) Requests that the offer be mailed to the dwelling owner; and

      (b) Furnishes the dwelling owner’s name and address with the request. [1981 c.778 §11]

 

      469.652 Contributions for urban and community forest activities by customers of publicly owned utilities; rules; uses. (1) Publicly owned utilities may establish a system to allow customers of publicly owned utilities to voluntarily contribute an amount that is to be used for urban and community forest activities within the area served by the utility. The amount shall be in addition to the customer’s utility bill.

      (2) The utility shall pay to the State Forester the amount designated under subsection (1) of this section. The State Forester shall deposit the moneys collected under this section into the Urban and Community Forestry Subaccount established under ORS 526.060.

      (3) The State Forester shall use the moneys collected under this section for urban and community forest activities. The State Forester by rule, in consultation with local utilities, shall establish guidelines to distribute moneys collected under this section through the Urban and Community Forestry Assistance Program. The guidelines shall include a requirement that moneys are distributed for energy conservation, by means of tree plantings, care and maintenance.

      (4) A utility shall not use more than 16 percent of the moneys collected under this section for administrative expenses. The State Forester shall not use more than 16 percent of the moneys collected under this section for administrative expenses.

      (5) As used in this section, “urban and community forest activities” means activities that promote cost-effective energy conservation. These activities may include the planting, managing and maintaining of residential, street and park trees on public and private land. [1993 c.388 §4]

 

      469.653 Alternative program of publicly owned utility. (1) A publicly owned utility may meet the program submission requirements of ORS 469.651 by submitting only the portions of its residential energy conservation program that are added to or revised in its program approved under section 4, chapter 887, Oregon Laws 1977, in order to make that earlier program fulfill the requirements of ORS 469.651.

      (2) A publicly owned utility shall offer a dwelling owner a financing program for cost-effective energy conservation measures that includes the option of a cash payment or a loan unless the publicly owned utility offers another financing program that meets or exceeds the program required in ORS 469.651 (3). A program shall be considered to meet or exceed the program required in ORS 469.651 (3) when it includes a financial incentive to the residential customer with a present value on November 1, 1981, that is equal to or greater than the present value of the larger of:

      (a) The loan subsidy pursuant to ORS 469.651 (3)(a)(A); or

      (b) The cash payment pursuant to ORS 469.651 (3)(a)(B).

      (3) A publicly owned utility whose governing body has adopted an approved residential energy conservation services program under the National Energy Conservation Policy Act (Public Law 95-619, as amended on November 1, 1981) or signed an energy conservation agreement with the Bonneville Power Administration of the United States Department of Energy for a residential weatherization program under section 6(a) of the Pacific Northwest Electric Power Planning and Conservation Act (Public Law 96-501, as adopted December 5, 1980) that meets or exceeds the requirements of ORS 469.651 and 469.657 shall not be required to submit a separate program. However, the provisions of ORS 469.655 and 469.659 nevertheless shall be applicable. [1981 c.778 §14]

 

      469.655 Energy conservation as part of utility service of publicly owned utility. The provision of energy conservation measures to a dwelling shall be considered part of the utility service rendered by the publicly owned utility. [1981 c.778 §12]

 

      469.657 Conditions for cash payments to dwelling owner by publicly owned utility. Except as provided in section 31, chapter 778, Oregon Laws 1981, a publicly owned utility shall not make a cash payment to a dwelling owner for energy conservation measures unless:

      (1) The measures were provided in the dwelling on or after November 1, 1981.

      (2) The measures will not be paid for with other publicly owned utility grants or loans. [1981 c.778 §13; 1991 c.877 §40]

 

      469.659 Implementation of program by publicly owned utility. After the publicly owned utility has submitted to the Director of the State Department of Energy the residential energy conservation program required by ORS 469.651, the publicly owned utility promptly shall implement that program. [1981 c.778 §15]

 

      469.673 [1981 c.778 §16; 1987 c.749 §8; 1989 c.648 §68; 1995 c.551 §15; 2003 c.186 §43; 2017 c.727 §9; renumbered 456.594 in 2017]

 

      469.675 [1981 c.778 §17; repealed by 2017 c.727 §8]

 

      469.677 [1981 c.778 §18; 2003 c.186 §44; repealed by 2017 c.727 §8]

 

      469.679 [1981 c.778 §19; repealed by 2017 c.727 §8]

 

      469.681 [1981 c.778 §23; 1983 c.273 §3; 1987 c.450 §3; 1989 c.88 §6; 1993 c.434 §1; 1993 c.569 §29; 1995 c.79 §289; 2003 c.186 §45; 2009 c.11 §68; 2017 c.727 §10; renumbered 456.595 in 2017]

 

      469.683 [1981 c.778 §§24,25; 1989 c.966 §55; 1993 c.434 §2; 2003 c.186 §46; 2017 c.727 §11; renumbered 456.597 in 2017]

 

(Miscellaneous)

 

      469.685 Use of earlier energy audit. A dwelling owner served by an investor-owned utility, as defined in ORS 469.631, or a publicly owned utility, as defined in ORS 469.649, who applies for financing under the provisions of ORS 316.744, 317.386, 456.594 to 456.599 and 469.631 to 469.687, may use without obtaining a new energy audit an energy audit obtained from an energy supplier under chapter 887, Oregon Laws 1977, or a public utility under chapter 889, Oregon Laws 1977, before November 1, 1981. [1981 c.778 §30; 2003 c.46 §51]

 

      469.687 Title for ORS 456.594 to 456.599 and 469.631 to 469.687. ORS 316.744, 317.386, 456.594 to 456.599 and 469.631 to 469.687 shall be known as the Oregon Residential Energy Conservation Act. [1981 c.778 §1; 2003 c.46 §52]

 

ENERGY CONSERVATION PROGRAMS

 

(Single Family Residence)

 

      469.700 Energy efficiency ratings; public information; “single family residence” defined. (1) The Residential and Manufactured Structures Board or the Construction Industry Energy Board, after public hearing and subject to the approval of the Director of the Department of Consumer and Business Services, shall adopt a recommended voluntary energy efficiency rating system for single family residences and provide the State Department of Energy with a copy thereof.

      (2) The rating system shall provide a single numerical value or other simple concise means to measure the energy efficiency of any single family residence, taking into account factors including, but not limited to, the heat loss characteristics of ceilings, walls, floors, windows, doors and heating ducts.

      (3) Upon adoption of the rating system under subsections (1) and (2) of this section, the department shall publicize the availability of the system, and encourage its voluntary use in real estate transactions.

      (4) As used in subsections (1) to (3) of this section, “single family residence” means a structure designed as a residence for one family and sharing no common wall with another residence of any type. [1977 c.413 §§1,2,3; 1993 c.744 §113; 2003 c.675 §44; 2009 c.567 §§9,22]

 

(Home Energy Performance Score System)

 

      469.703 Home energy performance score system; home energy assessors; reports; database; rules. (1) As used in this section:

      (a) “Home energy assessor” has the meaning given that term in ORS 701.527.

      (b) “Home energy audit” means the evaluation or testing of components or systems in a residential building for the purpose of identifying options for increasing energy conservation and energy efficiency.

      (c) “Home energy performance score” has the meaning given that term in ORS 701.527.

      (2) In consultation with the Public Utility Commission, the State Department of Energy shall adopt by rule a home energy performance score system by which a person may assign a residential building a home energy performance score for the purpose of evaluating the energy conservation and energy efficiency of the building.

      (3) The department shall designate by rule programs for the training of home energy assessors. Programs designated by the department under this subsection must ensure competency in conducting home energy audits and assigning home energy performance scores.

      (4) Subject to subsection (5) of this section, the department may adopt by rule requirements under which home energy assessors who are certified under ORS 701.532 must report to the department the home energy performance scores assigned by the home energy assessors. The department shall keep and maintain a database of information reported to the department under this subsection.

      (5) Rules adopted under subsection (4) of this section may not allow for the reporting of individual addresses of residential structures or the names of individual homeowners, but may allow for the reporting of information regarding the jurisdiction in which a residential structure is located and the utility services provided, any specific energy efficiency features of the residential structure or other general information that allows the department to make any aggregated evaluations of savings attributable to energy efficiency. [2013 c.383 §12]

 

      Note: 469.703 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

(Low Interest Loans)

 

      469.710 Definitions for ORS 469.710 to 469.720. As used in ORS 469.710 to 469.720, unless the context requires otherwise:

      (1) “Annual rate” means the yearly interest rate specified on the note, and is not the annual percentage rate, if any, disclosed to the applicant to comply with the federal Truth in Lending Act.

      (2) “Commercial lending institution” means any bank, mortgage banking company, trust company, savings bank, savings and loan association, credit union, national banking association, federal savings and loan association or federal credit union maintaining an office in this state.

      (3) “Cost-effective” means that an energy conservation measure that provides or saves a specific amount of energy during its life cycle results in the lowest present value of delivered energy costs of any available alternative. However, the present value of the delivered energy costs of an energy conservation measure may not be treated as greater than that of a nonconservation energy resource or facility unless that cost is greater than 110 percent of the present value of the delivered energy cost of the nonconservation energy resource or facility.

      (4) “Dwelling” means real or personal property within the state inhabited as the principal residence of a dwelling owner or a tenant. “Dwelling” includes a manufactured dwelling as defined in ORS 446.003, a floating home as defined in ORS 830.700 and a single unit in multiple-unit residential housing. “Dwelling” does not include a recreational vehicle as defined in ORS 174.101.

      (5) “Dwelling owner” means the person who has legal title to a dwelling, including the mortgagor under a duly recorded mortgage of real property, the trustor under a duly recorded deed of trust or a purchaser under a duly recorded contract for purchase of real property.

      (6) “Energy audit” means:

      (a) The measurement and analysis of the heat loss and energy utilization efficiency of a dwelling;

      (b) An analysis of the energy savings and dollar savings potential that would result from providing energy conservation measures for the dwelling;

      (c) An estimate of the cost of the energy conservation measures that includes:

      (A) Labor for the installation of items designed to improve the space heating and energy utilization efficiency of the dwelling; and

      (B) The items installed; and

      (d) A preliminary assessment, including feasibility and a range of costs, of the potential and opportunity for installation of:

      (A) Passive solar space heating and solar domestic water heating in the dwelling; and

      (B) Solar swimming pool heating, if applicable.

      (7) “Energy conservation measures” means measures that include the installation of items and the items installed that are primarily designed to improve the space heating and energy utilization efficiency of a dwelling. These items include, but are not limited to, caulking, weatherstripping and other infiltration preventative materials, ceiling and wall insulation, crawl space insulation, vapor barrier materials, timed thermostats, insulation of heating ducts, hot water pipes and water heaters in unheated spaces, storm doors and windows, double glazed windows and dehumidifiers. “Energy conservation measures” does not include the dwelling owner’s own labor.

      (8) “Finance charge” means the total of all interest, loan fees and other charges related to the cost of obtaining credit and includes any interest on any loan fees financed by the lending institution.

      (9) “Fuel oil dealer” means a person, association, corporation or any other form of organization that supplies fuel oil at retail for the space heating of dwellings.

      (10) “Residential fuel oil customer” means a dwelling owner or tenant who is billed by a fuel oil dealer for fuel oil service for space heating received at the dwelling.

      (11) “Space heating” means the heating of living space within a dwelling.

      (12) “Wood heating resident” means a person whose primary space heating is provided by the combustion of wood. [1981 c.894 §22; 1987 c.749 §5; 1989 c.648 §69; 2005 c.22 §342; 2019 c.422 §36]

 

      469.715 Low interest loans for cost-effective energy conservation; rate. (1) Dwelling owners who are or who rent to residential fuel oil customers, or who are or who rent to wood heating residents, shall be eligible for low-interest loans for cost-effective energy conservation measures through commercial lending institutions.

      (2) The annual rate shall not exceed six and one-half percent annually for loans provided by commercial lending institutions to dwelling owners who are or who rent to residential fuel oil customers, or who are or who rent to wood heating residents for the purpose of financing energy conservation measures pursuant to ORS 469.710 to 469.720. [1981 c.894 §§23,24; 1987 c.749 §6]

 

      469.717 When installation to be completed. (1) Installation of the energy conservation measures must be completed within 90 days after receipt of loan funds. The State Department of Energy may provide an inspection at the owner’s request.

      (2) Notwithstanding the provisions of subsection (1) of this section, the department may inspect installation of energy conservation measures to verify that all loan or other state subsidy funds have been used for energy conservation measures recommended in the audit, that installation has been performed in a workmanlike manner and that materials used satisfy prevailing industry standards. If requested to do so by the department, the dwelling owner shall provide the department with copies of receipts and any other documents verifying the cost of energy conservation measures. [1987 c.749 §3]

 

      469.719 Eligibility of lender for tax credit not affected by owner’s failure. Eligibility of the lender for any tax credit under ORS 317.112 shall not be affected by any dwelling owner’s failure to use the loan for qualifying energy conservation measures. [1987 c.749 §4]

 

      469.720 Energy audit required; permission to inspect required; owner not to receive other incentives. (1) A dwelling owner who is or who rents to a residential fuel oil customer, or who is or who rents to a wood heating resident, may not apply for low-interest financing under ORS 469.710 to 469.720 unless:

      (a) The dwelling owner, customer or resident has first requested and obtained an energy audit from a fuel oil dealer, a publicly owned utility or an investor-owned utility or from a person under contract with the State Department of Energy under ORS 316.744, 317.111, 317.386, 456.594 to 456.599 and 469.631 to 469.687;

      (b) The dwelling owner first submits to the department written permission to inspect the installations to verify that installation of energy conservation measures has been made;

      (c) The dwelling owner presents to the lending institution a copy of the energy audit together with certification that the dwelling in question receives space heating from fuel oil or wood and a copy of the written permission to inspect submitted to the department under paragraph (b) of this subsection; and

      (d) The dwelling owner does not receive any other state incentives for that part of the cost of the energy conservation measures to be financed by the loan.

      (2) Any dwelling owner applying for low-interest financing under ORS 469.710 to 469.720 who is or who rents to a residential fuel oil customer, or who is or who rents to a wood heating resident, may use without obtaining a new energy audit any assistance and technical advice obtained from an energy supplier before November 1, 1981, under chapter 887, Oregon Laws 1977, or from a public utility under chapter 889, Oregon Laws 1977, including an estimate of cost for installation of weatherization materials. [1981 c.894 §§25,26; 1987 c.749 §7; 1997 c.249 §167; 2003 c.46 §53]

 

(Public Buildings)

 

      469.730 Declaration of purpose. It is the purpose of ORS 469.730 to 469.745 to promote voluntary measures to conserve energy in public buildings or groups of buildings constructed prior to January 1, 1978, through the adoption of energy conservation standards. [1977 c.853 §1]

 

      469.735 Definitions for ORS 469.730 to 469.745. As used in ORS 469.730 to 469.745, unless the context requires otherwise:

      (1) “Department” means the Department of Consumer and Business Services.

      (2) “Director” means the Director of the Department of Consumer and Business Services.

      (3) “Public building” means any publicly or privately owned building constructed prior to January 1, 1978, including the outdoor areas adjacent thereto, which:

      (a) Is open to and frequented by the public; or

      (b) Serves as a place of employment. [1977 c.853 §2; 1987 c.414 §154; 1993 c.744 §114]

 

      469.740 Rules establishing energy conservation standards for public buildings; bases. In accordance with ORS chapter 183 and after consultation with the Building Codes Structures Board or with the Construction Industry Energy Board, the Director of the Department of Consumer and Business Services shall adopt rules establishing energy conservation standards for public buildings. The standards shall provide means of measuring and reducing total energy consumption and shall take into account:

      (1) The climatic conditions of the areas in which particular buildings are located; and

      (2) The three basic systems comprising any functioning building, which are:

      (a) Energized systems such as those required for heating, cooling, lighting, ventilation, conveyance and business equipment operation.

      (b) Nonenergized systems such as floors, ceilings, walls, roof and windows.

      (c) Human systems such as maintenance, operating and management personnel, tenants and other users. [1977 c.853 §3; 1987 c.414 §154a; 1993 c.744 §115; 2009 c.567 §10]

 

      469.745 Voluntary compliance program. To provide the public with a guide for energy conservation, the Director of the State Department of Energy shall adopt a program for voluntary compliance by the public with the standard adopted by the Director of the Department of Consumer and Business Services under ORS 469.740. [1977 c.853 §4; 1987 c.414 §155]

 

      469.748 State agencies to conduct assessments of energy use and greenhouse gas emissions of state-owned buildings; planning targets in capital projects; state agency reporting. (1) As used in this section, “state agency” has the meaning given that term in ORS 278.005.

      (2)(a) The Oregon Department of Administrative Services, in cooperation with the State Department of Energy, shall develop a methodology and work plan for state agencies to implement a comprehensive assessment of energy use and greenhouse gas emissions of state-owned buildings. At a minimum, the assessments must:

      (A) Examine and quantify each building’s greenhouse gas emissions, using where feasible existing data such as energy use reporting for existing state-owned buildings that state agencies submitted to the State Department of Energy and data from other existing programs and contracts;

      (B) Identify equipment or usage that contributes to greenhouse gas emissions from each building; and

      (C) Determine and quantify the useful life of equipment in each building that contributes to greenhouse gas emissions.

      (b) The Oregon Department of Administrative Services may direct state agencies to conduct the assessments described in paragraph (a) of this subsection in phases or stages and may specify a minimum building size that is subject to an assessment.

      (c) The Oregon Department of Administrative Services may procure and make available to state agencies services from a private contractor to conduct the assessments described in paragraph (a) of this subsection throughout the state.

      (3) All agencies of state government shall cooperate with and assist the Oregon Department of Administrative Services, or the department’s contractor, in conducting the assessments and shall timely provide relevant information to the department, or the department’s contractor, in accordance with methodology the department specifies.

      (4) The Oregon Department of Administrative Services, with support from the State Department of Energy, shall create a searchable and modifiable database with the data that the Oregon Department of Administrative Services, or the department’s contractor, collects from state agency assessments described in subsection (2) of this section. State agencies shall use baseline data from the database as a tool for planning energy use reduction and greenhouse gas emissions reduction targets in capital projects.

      (5)(a) The Oregon Department of Administrative Services, in collaboration with the Department of Environmental Quality and the State Department of Energy, shall oversee all capital projects in which:

      (A) A state agency constructs or performs a major renovation on a state building; and

      (B) The estimated contract price for the capital project exceeds $1 million.

      (b) In performing the oversight described in paragraph (a) of this subsection, the Oregon Department of Administrative Services shall:

      (A) Develop and implement guidelines for sustainable design that:

      (i) Apply to all state agencies and all capital projects described in paragraph (a) of this subsection;

      (ii) Take into account the building’s life cycle and the life cycle of all of the building’s systems, components, materials, operations and maintenance; and

      (iii) Consider each building’s size, cost or purpose;

      (B) Provide guidance and technical expertise to each state agency with respect to construction methods, materials, energy conservation measures, greenhouse gas emissions reduction methods, green building construction and renovation and other techniques and technologies that will aid in achieving the state’s green building, energy efficiency and greenhouse gas emissions reduction goals; and

      (C) Use existing work the State Department of Energy performed in connection with the United States Department of Energy’s Standard Energy Efficiency Data program, data from other existing programs and contracts and, where appropriate, data from the database described in subsection (4) of this section.

      (c) Each state agency shall report regularly to the Oregon Department of Administrative Services concerning progress on a capital project described in paragraph (a) of this subsection, with an emphasis on progress toward meeting the goals described in paragraph (b)(B) of this subsection. A state agency may combine a report under this paragraph with a report from another state agency.

      (6) The Oregon Department of Administrative Services and the State Department of Energy shall participate on behalf of the state in the National Building Performance Standards Coalition. [2023 c.442 §18]

 

      Note: 469.748 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.750 State purchase of alternative fuels. (1) Any state agency, board, commission, department or division that is authorized to purchase or otherwise acquire fuel for the systems providing heating, air conditioning, lighting and the supply of domestic hot water for public buildings and grounds may enter into long-term contracts for the purchase of alternative fuels. Such contracts may be for terms not longer than 20 years.

      (2) As used in this section:

      (a) “Alternative fuels” includes all fuels other than petroleum, natural gas, coal and products derived therefrom. The term includes, but is not limited to, solid wastes or fuels derived from solid wastes.

      (b) “Public buildings and grounds” has the meaning given that term in ORS 276.210. [1981 c.386 §6]

 

      Note: 469.750 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

(State Agency Projects)

 

      469.752 Definitions for ORS 469.752 to 469.756. As used in ORS 469.752 to 469.756, unless the context requires otherwise:

      (1) “Project” means a state agency’s improvement of the efficiency of energy use through conservation, development of cogeneration facilities or use of renewable resources. “Project” does not include a plan of a state agency to improve the efficiency of energy use in a state rented facility if the payback period for the project exceeds the term of the current state lease for that facility.

      (2) “Savings” means any reduction in energy costs or net income derived from the sale of energy generated through a project.

      (3) “State agency” has the meaning given that term in ORS 278.005. [1991 c.487 §1; 1993 c.86 §1; 1995 c.551 §16; 2003 c.186 §47]

 

      Note: 469.752 to 469.756 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.754 Authority of state agencies to establish projects; use of savings. (1) State agencies may enter into such contractual and other arrangements as are necessary or convenient to design, develop, operate and finance projects on-site at state owned or state rented facilities.

      (2)(a) For as long as a project established under ORS 469.752 to 469.756 produces savings:

      (A) A state agency’s budget may not be cut because of savings due to the project; and

      (B) A state agency shall retain 100 percent of the net savings to the state agency after any project debt service.

      (b) Savings from a project must be deposited in a revolving fund administered by the state agency.

      (3) A state agency shall spend the savings under subsection (2) of this section to increase productivity through:

      (a) Energy efficiency projects;

      (b) High-tech improvements, such as the purchase or installation of new desktop or laptop computers or the linkage of computers into systems or networks; or

      (c) Infrastructure improvements.

      (4) The moneys credited to the revolving fund may be invested and reinvested as provided in ORS 293.701 to 293.790. Notwithstanding ORS 293.105 (3) or any other provision of law, interest or other earnings on moneys in the revolving fund must be credited to the revolving fund.

      (5) ORS 469.752 to 469.756 do not authorize a state agency to sell electricity to an entity other than an investor owned utility, a publicly owned utility, an electric cooperative utility or the Bonneville Power Administration.

      (6) ORS 469.752 to 469.756 do not limit the authority of a state agency conferred by any other provision of law, or affect any authority, including the authority of a municipality, to regulate utility service under existing law. [1991 c.487 §2; 1993 c.86 §2; 2023 c.442 §19]

 

      Note: See note under 469.752.

 

      469.756 Rules; technical assistance; evaluations. The State Department of Energy in consultation with other state agencies and utilities shall adopt rules, guidelines and procedures that are necessary to establish savings for projects and to implement other provisions of ORS 469.752 to 469.756. The department may enter into agreements under ORS chapter 190 with state agencies to provide technical assistance in selecting appropriate projects and to evaluate and determine energy and cost savings. [1991 c.487 §3; 2023 c.442 §20]

 

      Note: See note under 469.752.

 

DESIGNATED STATE AGENCY PROGRAMS FOR ENERGY EFFICIENCY IN BUILDINGS

 

      469.760 Legislative findings; state goals related to adoption and use of heat pump technologies. (1) The Legislative Assembly finds that:

      (a) Energy consumption in residential and commercial buildings accounted for 34 percent of annual greenhouse gas emissions in this state in 2021, according to the Department of Environmental Quality;

      (b) Space and water heating account for 64 percent of an average residential building’s energy use;

      (c) Heat pumps provide both heating and cooling benefits that keep people safe during extreme weather events that are becoming more frequent and more intense as a consequence of climate change;

      (d) Electric heat pumps can provide up to three times more heat energy than the electrical energy the heat pumps consume, which makes heat pumps the most energy efficient space heating option available in the market;

      (e) Upgrading space and water heating appliances with contemporary heat pump technologies can help people to save money on household energy bills;

      (f) Existing and forthcoming state and federal incentive programs will assist in energy efficiency improvements in homes and buildings, including adoption of energy efficient heating and cooling appliances;

      (g) Many residents of this state suffer from disproportionately high energy burdens, and environmental justice communities face greater barriers to purchasing and installing heat pumps and other energy efficient appliances; and

      (h) Additional support and innovative solutions are necessary to ensure that all households in this state benefit from energy efficient appliances and heating and cooling upgrades.

      (2) The Legislative Assembly declares as goals for this state:

      (a) That owners, operators or residents of residential or commercial buildings in this state install and use at least 500,000 new heat pumps by 2030;

      (b) That the state provide programs and support for accelerating purchases and installations of heat pump technologies to help meet the state’s greenhouse gas emissions reduction goals;

      (c) That the programs and support described in paragraph (b) of this subsection should prioritize environmental justice communities and individuals who reside in houses and structures that do not have a functioning, adequate or affordable heating or cooling system;

      (d) That the state evaluate the adoption and use of heat pump technologies regularly to determine whether the rate of adoption and use will enable the state to meet greenhouse gas emissions reduction goals; and

      (e) That the agencies of the executive branch of state government lead by example by acquiring, installing and using heat pump technologies. [2023 c.442 §1]

 

      Note: 469.760 to 469.772 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.763 Definitions related to designated state agency programs. (1) As used in this section and ORS 469.766 and 469.769:

      (a) “Designated state agency program” means a program related to the promotion, implementation, incentivization or regulation of energy efficiency in buildings carried out by any of the following state agencies, as determined by the agency by rule or other action:

      (A) The State Department of Energy;

      (B) The Housing and Community Services Department;

      (C) The Public Utility Commission;

      (D) The Department of Environmental Quality;

      (E) The Oregon Health Authority; and

      (F) The Department of Consumer and Business Services.

      (b) “Greenhouse gas emissions reduction goals” means policies and goals for reducing greenhouse gas emissions in this state to achieve, at a minimum, emissions reductions consistent with the greenhouse gas emissions reduction goals specified in ORS 468A.205.

      (c) “Heat pump” means a device that provides indoor space heating and cooling by transferring thermal energy between the interior and exterior of a building.

      (d) “Heat pump technology” means:

      (A) A device that transfers thermal energy between the interior and exterior of a building for the purpose of space heating or cooling;

      (B) A device that transfers thermal energy from the interior or exterior of a building to water for the purpose of heating the water; or

      (C) A device that performs both of the functions described in subparagraphs (A) and (B) of this paragraph.

      (2) In carrying out a designated state agency program, an agency described in subsection (1)(a) of this section shall consider actions to aid in achieving greenhouse gas emissions reduction goals that include, but are not limited to:

      (a) Considering greenhouse gas emissions reduction goals in designated state agency program regulatory decisions.

      (b) Aligning the creation or operation of new or existing designated state agency programs with greenhouse gas emissions reduction goals.

      (c) Working in consultation and aligning efforts with other agencies to simplify and improve access for residents of this state to existing and new programs that relate to energy efficiency and resilience, and, where appropriate, to reduce or eliminate within programs financial or nonfinancial barriers to accessing energy efficiency measures or appliances that will result in the greatest available energy efficiency and reductions of greenhouse gas emissions.

      (d) Consistent with applicable federal and state laws and program requirements, prioritizing actions that help environmental justice communities, as defined in ORS 469A.400:

      (A) Adapt to impacts from climate change; and

      (B) Overcome cost burdens and other barriers to using energy in a way that is efficient and in alignment with greenhouse gas emissions reduction goals.

      (e) Consistent with applicable federal and state laws, consulting with the Oregon Climate Action Commission and the Environmental Justice Council and using, when appropriate, the environmental justice mapping tool developed under ORS 182.555 when considering or evaluating for development or implementation the policies and actions described in this subsection. [2023 c.442 §2]

 

      Note: See note under 469.760.

 

      469.766 Biennial report on adoption of heat pump technologies in this state. (1) The State Department of Energy shall submit to the Governor and an interim committee of the Legislative Assembly related to the environment not later than September 15 of each odd-numbered year, beginning in 2025, a report that evaluates the rate of adoption of heat pump technologies among residents of this state and progress the state is making in achieving the state’s greenhouse gas emissions reduction goals. At a minimum, the report must:

      (a) Review, using existing studies, market reports, polling data and other publicly available information, the nature and state of the market for heat pump technologies, including the size and dollar value of the market and the variety of available technologies, applications and appliances;

      (b) Identify financial and nonfinancial barriers that prevent adoption of heat pump technologies by residents of this state;

      (c) Assess the state’s progress in achieving the goals specified in ORS 469.760 (2); and

      (d) Estimate the date by which the state will achieve the goals specified in ORS 469.760 (2).

      (2) The department shall collaborate with other state agencies described in ORS 469.763 (1)(a) in preparing the report described in subsection (1) of this section and may:

      (a) Contract with a private entity to conduct research for, prepare or assist in preparing the report; and

      (b) Incorporate the findings from this report into the biennial energy report or into other reports to the Legislative Assembly concerning home energy efficiency or heat pump technologies.

      (3) In assessing the state’s progress toward achieving the goal specified in ORS 469.760 (2)(a), the department shall focus on heat pumps that are commercially available and shall, to the extent possible, use existing studies, data and analysis to evaluate:

      (a) Whether reductions in greenhouse gas emissions attributable to new heat pumps installed in homes and buildings in this state contribute to the state’s ability to meet greenhouse gas emissions reduction goals; and

      (b) To the extent possible, whether sales figures, the percentage of newly installed space and water heating systems that are heat pumps and the rate at which residents of this state install new heat pumps indicate that the state will meet the goal specified in ORS 469.760 (2)(a). [2023 c.442 §3]

 

      Note: See note under 469.760.

 

      469.769 Program to reduce barriers to home energy efficiency and resilience. (1) The State Department of Energy shall collaborate with other state agencies described in ORS 469.763 (1)(a) to reduce financial and nonfinancial barriers to home energy efficiency and resilience by:

      (a) Providing initial and continuing technical assistance and training in order to build capacity in developers, builders, community-based organizations, homeowners and tenants to conduct renovations and installations of energy efficient technologies, including heat pumps; and

      (b) Providing education and training to contractors, subcontractors, technicians, community-based organizations and other installers and other workers in industries related to construction and energy appliance installation concerning:

      (A) The availability of moneys, programs, rebates and other incentives for acquiring and installing energy efficient appliances for heating and cooling;

      (B) Methods, techniques, available incentives and funding available for upgrading electrical panels and wiring to accommodate energy efficient appliances for heating and cooling; and

      (C) Planning for, installing and operating heat pumps.

      (2) The program described in subsection (1) of this section must:

      (a) Provide information and assistance that is understandable and usable by developers, builders, community-based organizations and other industry stakeholders with an interest in acquiring, maintaining and using energy efficient technologies for heating and cooling homes and commercial buildings, including heat pump technologies;

      (b) Include information on delivering, installing and using high efficiency heating and cooling appliances in instances where variation exists in funding options for various minimum efficiency requirements;

      (c) Work with locally connected and culturally connected organizations to provide the program’s information, technical assistance, training and support; and

      (d) Allow sufficient flexibility for designated state agencies to contract with private entities to provide needed information, assistance, training and support.

      (3) The department may incorporate the work described in this section with other programs that serve to educate the public on energy efficiency. [2023 c.442 §4]

 

      Note: See note under 469.760.

 

      469.772 Energy Efficient Technologies Information and Training Fund. (1)(a) The Energy Efficient Technologies Information and Training Fund is established in the State Treasury, separate and distinct from the General Fund. Interest that the Energy Efficient Technologies Information and Training Fund earns must be credited to the fund.

      (b) Moneys in the fund may be invested and reinvested as provided in ORS 293.701 to 293.857.

      (2) Moneys in the fund consist of:

      (a) Appropriations to the State Department of Energy for the purposes described in ORS 469.760 to 469.772;

      (b) Moneys from federal sources and other moneys the department receives for the purposes specified in ORS 469.760 to 469.772;

      (c) Interest and other earnings on moneys in the fund; and

      (d) Other amounts the department receives from any source and deposits into the fund.

      (3) Subject to subsection (4) of this section, moneys in the fund are continuously appropriated to the department for the purpose of funding the purposes described in ORS 469.760 to 469.772.

      (4)(a) The department may not during any biennium expend more than 10 percent of the average quarterly balance of the fund to pay the cost of administering the fund or the administrative costs of carrying out the purposes described in ORS 469.760 to 469.772.

      (b) As used in this subsection, “administrative cost” does not include grants or other funds provided to community-based organizations or other contracted entities. [2023 c.442 §5]

 

      Note: See note under 469.760.

 

      469.785 [2007 c.739 §31; renumbered 469B.400 in 2011]

 

      469.790 [2007 c.739 §5; 2011 c.730 §3; renumbered 469B.403 in 2011]

 

      469.800 [1981 c.49 §1; renumbered 469.803 in 1999]

 

PACIFIC NORTHWEST ELECTRIC POWER AND CONSERVATION PLANNING COUNCIL

 

      469.802 Definition for ORS 469.802 to 469.845. As used in ORS 469.802 to 469.845, “council” means the Pacific Northwest Electric Power and Conservation Planning Council. [1999 c.59 §141]

 

      469.803 Oregon participation in Pacific Northwest Electric Power and Conservation Planning Council. The State of Oregon agrees to participate in the formation of the Pacific Northwest Electric Power and Conservation Planning Council pursuant to the Pacific Northwest Electric Power Planning and Conservation Act of 1980, Public Law 96-501. Participation of the State of Oregon in the council is essential to assure adequate representation for the citizens of Oregon in decision making to achieve cost-effective energy conservation, to encourage the development of renewable energy resources, to establish a representative regional power planning process, to assure the Pacific Northwest region of an efficient and adequate power supply and to fulfill the other purposes stated in section 2 of Public Law 96-501. [Formerly 469.800]

 

      469.805 State members of council; confirmation; qualifications. (1) The Governor, subject to Senate confirmation pursuant to section 4, Article III of the Oregon Constitution, shall appoint two persons to serve as members of the Pacific Northwest Electric Power and Conservation Planning Council for terms of three years.

      (2) In making the appointments under subsection (1) of this section, the Governor shall consider but is not limited to:

      (a) Prior experience, training and education as related to the duties and functions of the council and the priorities contained in section 4 of Public Law 96-501.

      (b) General knowledge of the concerns, conditions and problems of the physical, social and economic environment of the State of Oregon.

      (c) The need for diversity of experience and education related to the functions and duties of the council and priorities of Public Law 96-501.

      (3) Of the persons appointed under subsection (1) of this section, not more than one member of the Oregon delegation to the council shall reside within the boundary of an area that includes the First and Third Congressional Districts of this state and the Portland, Oregon, Metropolitan Statistical Area. [1981 c.49 §2; 1995 c.156 §1; 1997 c.249 §168; 2009 c.11 §69; 2013 c.1 §71]

 

      469.810 Conflicts of interest prohibited. (1) A Pacific Northwest Electric Power and Conservation Planning Council member or member of the council member’s household may not own or have any beneficial interest in any stock or indebtedness of any utility or direct service industry.

      (2) A council member or a member of the council member’s household may not be a director, officer, agent or employee of any utility or direct service industry.

      (3) A council member or a member of the council member’s household may not be a director, officer, agent or employee of or hold any proprietary interest in any consulting firm that does business with any utility or direct service industry.

      (4) A council member or a member of the council member’s household may not receive any compensation from any utility or direct service industry arising out of the member’s business, trade or profession.

      (5) A council member is a public official subject to the provisions and reporting requirements of ORS chapter 244.

      (6) A council member must be a citizen of the United States and must have resided in the State of Oregon for at least one year preceding appointment.

      (7) A council member may not hold any other elected or appointed lucrative public office or be principally engaged in any other business or vocation.

      (8) As used in this section:

      (a) “Beneficial interest” does not include an interest in a pension fund, a mutual fund or an insurance fund.

      (b) “Consulting firm” means any corporation, partnership or sole proprietorship whose principal business is providing personal services.

      (c) “Member of the household” means any relative who resides with the council member.

      (d) “Relative” means the spouse of the council member, any children of the council member or of the council member’s spouse, and brothers, sisters or parents of the council member or of the council member’s spouse.

      (e) “Utility or direct service industry” means a utility or direct service industry customer that purchases electrical energy directly from the Bonneville Power Administration. [1981 c.49 §3; 1987 c.566 §23; 2007 c.865 §38]

 

      469.815 Status of members; duties; attendance at public meetings; technical assistance. (1) Persons appointed by the Governor and confirmed by the Senate to serve as Pacific Northwest Electric Power and Conservation Planning Council members shall be considered to be full-time state public officials. Council members shall perform the duties of members of the council as specified in Public Law 96-501, consistently with the priorities contained in section 4 thereof and as otherwise provided in state law.

      (2) If public meetings are held in the State of Oregon, pursuant to section 4(g)(1) of Public Law 96-501, council members must either attend the meeting or otherwise become familiar with the nature and content of the meeting.

      (3) A council member may request, and state agencies shall provide, technical assistance to assist the council member in performing the council member’s duties. [1981 c.49 §4]

 

      469.820 Term; reappointment; vacancy. (1) Each Pacific Northwest Electric Power and Conservation Planning Council member shall serve a term ending January 15 of the third year following appointment. A council member, except upon removal as provided in ORS 469.830 (2), continues to serve as a member of the council until a successor is appointed and confirmed.

      (2) A council member is eligible for reappointment, subject to Senate confirmation, but no member shall serve more than three consecutive terms. A council member who serves 18 months or more of a term shall be considered to have served a full term. However, with respect to the initial term consisting of two years, a council member who serves 12 months or more shall be considered to have served a full term.

      (3) Within 30 days of the creation of a vacancy in the position of a council member, the Governor shall appoint a person to serve the succeeding term or the remainder of the unexpired term. However, the Governor need not appoint a person to serve the remainder of the unexpired term if the vacancy occurs within 30 days or less of the expiration of the term. [1981 c.49 §5]

 

      469.825 Prohibited activities of members. (1) A person who has been a Pacific Northwest Electric Power and Conservation Planning Council member shall not engage in any of the activities prohibited by ORS 469.810 (2) and (3), within one year after ceasing to be a council member.

      (2) A person who has been a council member shall not appear as a representative of any party on any matter before the council within three years after ceasing to be a council member.

      (3) A person who has been a council member shall not represent, aid, counsel, consult or advise for financial gain any person on any matter before the council within three years after ceasing to be a council member.

      (4) A person who has been a council member shall not appear for financial gain as a representative of or aid, counsel or advise any party before the council or the Bonneville Power Administration or communicate with the council or the Bonneville Power Administration with the intent to influence the outcome of any decision on any matter in which the council member was substantially and personally involved while on the council.

      (5) Notwithstanding the status of council members as state officers, the provisions of 18 U.S.C. 207 relating to post-employment activities shall be considered to be state law in so far as they do not conflict therewith, applicable to council members appointed pursuant to ORS 469.802 to 469.845 and 469.990 (3), regardless of the salary paid to the council members.

      (6) Subsections (2) to (5) of this section shall not apply to any appearance, attendance, communication or other action on behalf of the State of Oregon; nor shall subsections (2) to (5) of this section apply to an appearance or communication made in response to a subpoena. [1981 c.49 §6]

 

      469.830 Removal of members; grounds; procedure. (1) Pacific Northwest Electric Power and Conservation Planning Council members shall serve at the pleasure of the Governor, except as provided in subsection (2) of this section.

      (2) The Governor shall remove a council member for the following causes:

      (a) Failure to attend three consecutive council meetings except for good cause.

      (b) Conviction of a felony.

      (c) Violation of ORS chapter 244.

      (d) Violation of ORS 469.810.

      (3) Before removal of a council member by the Governor, the council member shall be given a written statement of the reasons for removal and, upon request by the member, an opportunity to be heard publicly on such reasons before the Governor. A copy of the statement of reasons and a transcript of the record of the hearing shall be filed with the Secretary of State. [1981 c.49 §7]

 

      469.835 Salary of members; staff. (1) Each Pacific Northwest Electric Power and Conservation Planning Council member shall receive a salary not to exceed the salary of a member of the Public Utility Commission, or the maximum salary authorized under section 4(a)(3) of Public Law 96-501.

      (2) Each council member is entitled to appoint one secretarial staff assistant who shall be in the unclassified service. [1981 c.49 §8; 1989 c.171 §64]

 

      469.840 Northwest Regional Power and Conservation Account; uses. (1) There is established a Northwest Regional Power and Conservation Account. Moneys received pursuant to Public Law 96-501 shall be placed in the account.

      (2) The account created by subsection (1) of this section is continuously appropriated for disbursement to state agencies, including but not limited to the Public Utility Commission, the State Department of Energy, the State Department of Fish and Wildlife and the Water Resources Department to carry out the purposes of Public Law 96-501, subject to legislative approval or limitation by law or Emergency Board action. [1981 c.49 §9; 1987 c.158 §99; 2003 c.186 §48]

 

      469.845 Annual report to Governor and legislature. Pacific Northwest Electric Power and Conservation Planning Council members shall prepare a report which shall be presented to the Governor and to the President of the Senate and the Speaker of the House of Representatives of the Legislative Assembly on October 1 of each year. The report shall include a review of the council’s actions during the prior year. [1981 c.49 §10]

 

COMMERCIAL ENERGY CONSERVATION SERVICES PROGRAM

 

      469.860 Definitions for ORS 469.860 to 469.900. (1) As used in ORS 469.865 to 469.875, 469.900 (1) and (2) and subsection (2) of this section:

      (a) “Commercial building” means a public building as defined in ORS 455.560.

      (b) “Commission” means the Public Utility Commission.

      (c) “Conservation services” means providing energy audits or technical assistance for energy conservation measures as part of a program approved under ORS 469.860 to 469.900.

      (d) “Electric utility” means a public utility, as defined in ORS 757.005, which produces, transmits, delivers or furnishes electric power and is regulated by the commission under ORS chapter 757.

      (e) “Energy conservation measure” means a measure primarily designed to improve the efficiency of energy use in a commercial building. “Energy conservation measures” include, but are not limited to, improved operation and maintenance measures, energy use analysis procedures, lighting system improvements, heating, ventilating and air conditioning system modifications, furnace and boiler efficiency improvements, automatic control systems including wide dead band thermostats, heat recovery devices, infiltration controls, envelope weatherization, solar water heaters and water heating heat pumps.

      (2) As used in ORS 469.865 and 469.900 (2), “gas utility” means a public utility, as defined in ORS 757.005, which delivers or furnishes natural gas to customers for heat, light or power.

      (3) As used in ORS 469.880 to 469.895 and 469.900 (3):

      (a) “Commercial building” means a public building as defined in ORS 455.560.

      (b) “Conservation services” has the meaning given in subsection (1) of this section.

      (c) “Energy conservation measure” has the meaning given in subsection (1) of this section.

      (d) “Publicly owned utility” means an electric utility owned or operated, in whole or in part, by a municipality, cooperative association or people’s utility district. [1981 c.708 §§1,7,13]

 

      Note: 469.860 (1) and (2) and 469.863 were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.863 Gas utility to adopt commercial energy audit program; rules. (1) Within 365 days after November 1, 1981, the Public Utility Commission shall adopt rules governing energy conservation programs provided by gas utilities under this section and may provide for coordination among electric utilities and gas utilities that serve the same commercial building.

      (2) Within 180 days after the effective date of the rules adopted by the commission under subsection (1) of this section, each gas utility shall present for the commission’s approval a commercial energy audit program which shall, to the commission’s satisfaction:

      (a) Make information about energy conservation measures available to any commercial building customer of the gas utility, upon request;

      (b) Regularly notify all customers in commercial buildings of the availability of the services described in this section;

      (c) Provide to any commercial building customer of the gas utility, upon request, an on-site energy audit of the customer’s commercial building, including, but not limited to, an estimate of the cost of the recommended energy conservation measure; and

      (d) Set a reasonable time schedule for effective implementation of the elements set forth in this section. [1981 c.708 §8]

 

      Note: See note under 469.860.

 

      469.865 Electric utility to adopt commercial energy conservation services program. (1) Within 180 days after the adoption of the rules by the Public Utility Commission under section 2, chapter 708, Oregon Laws 1981, each electric utility shall present for the commission’s approval a commercial energy conservation services program which shall, to the commission’s satisfaction:

      (a) Make information about energy conservation available to any commercial building customer of the electric utility, upon request;

      (b) Regularly notify all customers in commercial buildings of the availability of the services described in this section; and

      (c) Provide to any commercial building customer of the electric utility, upon request, an on-site energy audit of the customer’s commercial building, including, but not limited to, an estimate of the cost of the energy conservation measures.

      (2) The programs submitted and approved under this section shall include a reasonable time schedule for effective implementation of the elements set forth in subsection (1) of this section in the service areas of the electric utility. [1981 c.708 §3]

 

      469.870 Application of ORS 469.865, 469.870 and 469.900 (1) to electric utility. ORS 469.865, 469.900 (1) and this section shall not apply to an electric utility if the Public Utility Commission determines that its existing commercial energy conservation services program meets or exceeds the requirements of those sections. [1981 c.708 §4]

 

      469.875 Fee for gas utility audit. The Public Utility Commission shall determine whether the gas utility may charge a reasonable fee to the customer for the energy audit service and, if so, the fee amount. [1981 c.708 §9]

 

      469.878 [1991 c.711 §6; 1993 c.18 §123; 1995 c.746 §18a; 1999 c.623 §8; 1999 c.765 §6; renumbered 469B.171 in 2011]

 

      469.880 Energy audit program; rules. Each publicly owned utility serving Oregon shall, either independently or as part of an association, provide an energy audit program for its commercial customers. The Director of the State Department of Energy shall adopt rules governing the commercial energy audit program established under this section and may provide for coordination among electric utilities and gas utilities that serve the same commercial building. [1981 c.708 §14; 1987 c.158 §100; 2003 c.186 §49]

 

      469.885 Publicly owned utility to adopt commercial energy audit program; fee. (1) Within 180 days after the adoption of rules by the Director of the State Department of Energy under ORS 469.880, each publicly owned utility shall present for the director’s approval a commercial energy audit program that shall, to the director’s satisfaction:

      (a) Make information about energy conservation available to any commercial building customer of the publicly owned utility, upon request;

      (b) Regularly notify all customers in commercial buildings of the availability of the services described in this section;

      (c) Provide to any commercial building customer of the publicly owned utility, upon request, an on-site energy audit of the customer’s commercial building, including, but not limited to, an estimate of the cost of the energy conservation measures; and

      (d) Set a reasonable time schedule for effective implementation of the elements set forth in this section.

      (2) The commercial energy audit program submitted under subsection (1) of this section shall specify whether the publicly owned utility proposes to charge the customer a fee for the energy audit and, if so, the fee amount. [1981 c.708 §§15,16; 2003 c.186 §50]

 

      469.890 Publicly owned utility to adopt commercial energy conservation program; fees; rules. (1) Within 365 days after November 1, 1981, the Director of the State Department of Energy shall adopt rules governing energy conservation programs prescribed by ORS 469.895 and 469.900 (3) and this section and may provide for coordination among electric utilities and gas utilities that serve the same commercial building. Within 180 days of the adoption of rules by the director, each covered publicly owned utility shall present for the director’s approval a commercial energy conservation services program that shall, to the director’s satisfaction:

      (a) Make information about energy conservation available to all commercial building customers of the covered publicly owned utility, upon request;

      (b) Regularly notify all customers in commercial buildings of the availability of the services described in this section; and

      (c) Provide to any commercial building customer of the covered publicly owned utility, upon request, an on-site energy audit of the customer’s commercial building, including, but not limited to, an estimate of the cost of energy conservation measures.

      (2) The programs submitted and approved under this section shall include a reasonable time schedule for effective implementation of the elements set forth in subsection (1) of this section in the service areas of the covered publicly owned utility.

      (3) The commercial energy conservation services program submitted under subsections (1) and (2) of this section shall specify whether the covered publicly owned utility proposes to charge the customer a fee for the energy audit and, if so, the fee amount. [1981 c.708 §§18,19; 2003 c.186 §51]

 

      469.895 Application of ORS 469.890 to 469.900 to publicly owned utility. (1) ORS 469.890 and 469.900 (3) and this section apply in any calendar year to a publicly owned utility only if during the second preceding calendar year sales of electric energy by the publicly owned utility for purposes other than resale exceeded 750 million kilowatt-hours. For the purpose of ORS 469.890 and 469.900 (3) and this section, a publicly owned utility with sales for nonresale purposes in excess of 750 million kilowatt-hours during the second preceding calendar year shall be known as a “covered publicly owned utility.”

      (2) ORS 469.890 and 469.900 (3) and this section shall not apply to a covered publicly owned utility if the Director of the State Department of Energy determines that its existing commercial energy conservation services program meets or exceeds the requirements of those sections.

      (3) Before the beginning of each calendar year, the director shall publish a list identifying each covered publicly owned utility to which ORS 469.890 and 469.900 (3) and this section shall apply during that calendar year.

      (4) Any covered publicly owned utility is exempt from the requirements of ORS 469.880 and 469.885. [1981 c.708 §17; 2003 c.186 §52]

 

      469.900 Duty of commission to avoid conflict with federal requirements. (1) The Public Utility Commission shall insure that each electric utility’s commercial energy conservation services program does not conflict with federal statutes and regulations applicable to electric utilities and energy conservation in commercial buildings.

      (2) The commission shall insure that each gas utility’s commercial energy conservation services program does not conflict with federal statutes and regulations applicable to gas utilities and energy conservation in commercial buildings.

      (3) The Director of the State Department of Energy shall insure that each covered publicly owned utility’s commercial energy conservation services program does not conflict with federal statutes and regulations applicable to covered publicly owned utilities and energy conservation in commercial buildings. [1981 c.708 §§5,10,20]

 

      Note: 469.900 (1) and (2) were enacted into law by the Legislative Assembly but were not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

NORTHWEST INTERSTATE COMPACT ON LOW-LEVEL RADIOACTIVE WASTE MANAGEMENT

 

      469.930 Northwest Interstate Compact on Low-Level Radioactive Waste Management. The Northwest Interstate Compact on Low-Level Radioactive Waste Management is enacted into law by the State of Oregon and entered into with all other jurisdictions lawfully joining therein in a form as provided for as follows:

______________________________________________________________________________

ARTICLE I

Policy and Purpose

      The party states recognize that low-level radioactive wastes are generated by essential activities and services that benefit the citizens of the states. It is further recognized that the protection of the health and safety of the citizens of the party states and the most economical management of low-level radioactive wastes can be accomplished through cooperation of the states in minimizing the amount of handling and transportation required to dispose of such wastes and through the cooperation of the states in providing facilities that serve the region. It is the policy of the party states to undertake the necessary cooperation to protect the health and safety of the citizens of the party states and to provide for the most economical management of low-level radioactive wastes on a continuing basis. It is the purpose of this compact to provide the means for such a cooperative effort among the party states so that the protection of the citizens of the states and the maintenance of the viability of the states’ economies will be enhanced while sharing the responsibilities of radioactive low-level waste management.

ARTICLE II

Definitions

      As used in this compact:

      (1) “Facility” means any site, location, structure or property used or to be used for the storage, treatment or disposal of low-level waste, excluding federal waste facilities.

      (2) “Low-level waste” means waste material which contains radioactive nuclides emitting primarily beta or gamma radiation, or both, in concentrations or quantities which exceed applicable federal or state standards for unrestricted release. Low-level waste does not include waste containing more than 10 nanocuries of transuranic contaminants per gram of material, nor spent reactor fuel, nor material classified as either high-level waste or waste which is unsuited for disposal by near-surface burial under any applicable federal regulations.

      (3) “Generator” means any person, partnership, association, corporation or any other entity whatsoever which, as a part of its activities, produces low-level radioactive waste.

      (4) “Host state” means a state in which a facility is located.

ARTICLE III

Regulatory Practices

      Each party state hereby agrees to adopt practices which will require low-level waste shipments originating within its borders and destined for a facility within another party state to conform to the applicable packaging and transportation requirements and regulations of the host state. Such practices shall include:

      (1) Maintaining an inventory of all generators within the state that have shipped or expect to ship low-level waste to facilities in another party state.

      (2) Periodic unannounced inspection of the premises of such generators and the waste management activities thereon.

      (3) Authorization of the containers in which such waste may be shipped and a requirement that generators use only that type of container authorized by the state.

      (4) Assurance that inspections of the carriers which transport such waste are conducted by proper authorities and appropriate enforcement action is taken for violations.

      (5) After receiving notification from a host state that a generator within the party state is in violation of applicable packaging or transportation standards, the party state will take appropriate action to assure that such violations do not recur. Such action may include inspection of every individual low-level waste shipment by that generator.

      (6) Each party state may impose fees upon generators and shippers to recover the cost of the inspections and other practices under this Article. Nothing in this Article shall be construed to limit any party state’s authority to impose additional or more stringent standards on generators or carriers than those required under this Article.

ARTICLE IV

Regional Facilities

      (1) Facilities located in any party state, other than facilities established or maintained by individual low-level waste generators for the management of their own low-level waste, shall accept low-level waste generated in any party state if such waste has been packaged and transported according to applicable laws and regulations.

      (2) No facility located in any party state may accept low-level waste generated outside of the region comprised of the party states, except as provided in Article V.

      (3) Until such time as paragraph (2) of this Article takes effect as provided in Article VI, facilities located in any party state may accept low-level waste generated outside of any of the party states only if such waste is accompanied by a certificate of compliance issued by an official of the state in which such waste shipment originated. Such certificate shall be in such form as may be required by the host state and shall contain at least the following:

      (a) The generator’s name and address;

      (b) A description of the contents of the low-level waste container;

      (c) A statement that the low-level waste being shipped has been inspected by the official who issued the certificate or by an agent of the official or by a representative of the United States Nuclear Regulatory Commission, and found to have been packaged in compliance with applicable federal regulations and such additional requirements as may be imposed by the host state; and

      (d) A binding agreement by the state of origin to reimburse any party state for any liability or expense incurred as a result of an accidental release of such waste, during shipment or after such waste reaches the facility.

      (4) Each party state shall cooperate with the other party states in determining the appropriate site of any facility that might be required within the region comprised of the party states, in order to maximize public health and safety while minimizing the use of any one party state as the host of such facilities on a permanent basis. Each party state further agrees that decisions regarding low-level waste management facilities in the region will be reached through a good faith process which takes into account the burdens borne by each of the party states as well as the benefits each has received.

      (5) The party states recognize that the issue of hazardous chemical waste management is similar in many respects to that of low-level waste management. Therefore, in consideration of the State of Washington allowing access to its low-level waste disposal facility by generators in other party states, party states such as Oregon and Idaho which host hazardous chemical waste disposal facilities will allow access to such facilities by generators within other party states. Nothing in this compact shall be construed to prevent any party state from limiting the nature and type of hazardous chemical or low-level wastes to be accepted at facilities within its borders or from ordering the closure of such facilities, so long as such action by a host state is applied equally to all generators within the region comprised of the party states.

      (6) Any host state may establish a schedule of fees and requirements related to its facility to assure that closure, perpetual care, and maintenance and contingency requirements are met, including adequate bonding.

ARTICLE V

Northwest Low-Level

Waste Compact Committee

      The governor of each party state shall designate one official of that state as the person responsible for administration of this compact. The officials so designated shall together comprise the Northwest low-level waste compact committee. The committee shall meet as required to consider matters arising under this compact. The parties shall inform the committee of existing regulations concerning low-level waste management in their states and shall afford all parties a reasonable opportunity to review and comment upon any proposed modifications in such regulations. Notwithstanding any provision of Article IV to the contrary, the committee may enter into arrangements with states, provinces, individual generators or regional compact entities outside the region comprised of the party states for access to facilities on such terms and conditions as the committee may deem appropriate. However, it shall require a two-thirds vote of all such members, including the affirmative vote of the member of any party state in which a facility affected by such arrangement is located, for the committee to enter into such arrangement.

ARTICLE VI

Eligible Parties and Effective Date

      (1) Each of the following states is eligible to become a party to this compact: Alaska, Hawaii, Idaho, Montana, Oregon, Utah, Washington and Wyoming. As to any eligible party, this compact shall become effective upon enactment into law by that party, but it shall not become initially effective until enacted into law by two states. Any party state may withdraw from this compact by enacting a statute repealing its approval.

      (2) After the compact has initially taken effect pursuant to paragraph (1) of this Article any eligible party state may become a party to this compact by the execution of an executive order by the governor of the state. Any state which becomes a party in this manner shall cease to be a party upon the final adjournment of the next general or regular session of its legislature or July 1, 1983, whichever occurs first, unless the compact has by then been enacted as a statute by that state.

      (3) Paragraph (2) of Article IV of this compact shall take effect on July 1, 1983, if consent is given by Congress. As provided in Public Law 96-573, Congress may withdraw its consent to the compact after every five-year period.

ARTICLE VII

Severability

      If any provision of this compact, or its application to any person or circumstance, is held to be invalid, all other provisions of this compact, and the application of all of its provisions to all other persons and circumstances, shall remain valid; and to this end the provisions of this compact are severable.

______________________________________________________________________________ [1981 c.497 §1]

 

      469.935 [1981 c.497 §3; repealed by 1997 c.632 §14]

 

POWER COSTS AND RATES

 

      469.950 Authority to enter into interstate cooperative agreements to control power costs and rates; Bonneville Power Administration. The State of Oregon shall pursue and may enter into an interstate cooperative agreement with the states of Washington, Idaho and Montana for the purpose of making collective efforts to control Bonneville Power Administration wholesale power costs and rates by studying and developing a region-wide response to:

      (1) Federal attempts to increase arbitrarily the interest rates on federal funds previously used to build public facilities in the Pacific Northwest.

      (2) Federal initiatives to sell the Bonneville Power Administration.

      (3) Bonneville Power Administration rate increase and budget expenditure proposals in excess of their actual needs.

      (4) Regional uses of surplus firm power, including uses by existing or newly attracted Pacific Northwest industries, to provide long-term use of the surplus for job development.

      (5) Power transmission intertie access. [1985 c.780 §1]

 

      Note: 469.950 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 469 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.

 

      469.960 [2013 c.774 §1; 2014 c.38 §1; repealed by 2017 c.725 §22]

 

      469.961 [2013 c.774 §2; repealed by 2017 c.725 §22]

 

      469.962 [2013 c.774 §3; 2014 c.38 §2; repealed by 2017 c.725 §22]

 

      469.963 [2013 c.774 §4; 2014 c.38 §3; repealed by 2017 c.725 §22]

 

      469.964 [2013 c.774 §5; 2014 c.38 §4; repealed by 2017 c.725 §22]

 

      469.965 [2013 c.774 §6; 2014 c.38 §5; repealed by 2017 c.725 §22]

 

      469.966 [2013 c.774 §7; 2014 c.38 §6; repealed by 2017 c.725 §22]

 

PENALTIES

 

      469.990 Penalties. (1) In addition to any penalties under subsection (2) of this section, a person who discloses confidential information in violation of ORS 469.090, willfully or with criminal negligence, as defined by ORS 161.085, may be subject to removal from office or immediate dismissal from public employment.

      (2)(a) Willful disclosure of confidential information in violation of ORS 469.090 is a Class A misdemeanor. Notwithstanding ORS 161.635, the maximum fine for a violation is $10,000.

      (b) Disclosure of confidential information in violation of ORS 469.090 with criminal negligence, as defined by ORS 161.085, is a Class A violation.

      (3) Any person who violates ORS 469.825 commits a Class A misdemeanor. [1975 c.606 §20; subsection (3) enacted as 1981 c.49 §11; 1999 c.1051 §185; 2011 c.597 §212]

 

      469.991 [1989 c.926 §40; 1991 c.67 §142; repealed by 1999 c.880 §2]

 

      469.992 Civil penalties. (1) The Director of the State Department of Energy or the Energy Facility Siting Council may impose civil penalties for violation of ORS 469.300 to 469.619 and 469.930, for violations of rules adopted under ORS 469.300 to 469.619 and 469.930, for violation of any site certificate or amended site certificate issued under ORS 469.300 to 469.601 or for violation of a State Department of Energy order issued pursuant to ORS 469.405 (3). A civil penalty in an amount of not more than $25,000 per day for each day of violation may be assessed.

      (2) Subject to ORS 153.022, violation of an order entered pursuant to ORS 469.550 is punishable upon conviction by a fine of $50,000. Each day of violation constitutes a separate offense.

      (3) A civil penalty in an amount not less than $100 per day nor more than $1,000 per day may be assessed by the director or the Energy Facility Siting Council for a willful failure to comply with a subpoena served by the director pursuant to ORS 469.080 (2).

      (4) A civil penalty in an amount of not more than $25,000 per day for each day in violation of any provision of ORS 469.603 to 469.619 may be assessed by the circuit court upon complaint of any person injured by the violation. [Formerly 453.994; 1977 c.794 §17; 1981 c.707 §13; 1983 c.273 §4; 1987 c.158 §101; 1989 c.6 §12; 1991 c.480 §8; 1999 c.385 §13; 1999 c.1051 §309; 2003 c.186 §53]

 

      Note: The amendments to 469.992 by section 17, chapter 653, Oregon Laws 1991, become operative when the federal government or a state that has entered into an agreement under 42 U.S.C. 2021 exempts from regulation or changes the regulatory status of any radioactive material that is subject to regulation on January 1, 1989. See section 18, chapter 653, Oregon Laws 1991. The text of 469.992 that would become operative upon an exemption or change, including amendments by section 14, chapter 385, Oregon Laws 1999, section 310, chapter 1051, Oregon Laws 1999, and section 54, chapter 186, Oregon Laws 2003, is set forth for the user’s convenience.

      469.992. (1) The Director of the State Department of Energy or the Energy Facility Siting Council may impose civil penalties for violation of ORS 469.300 to 469.619 and 469.930, for violations of rules adopted under ORS 469.300 to 469.619 and 469.930, for violation of any site certificate or amended site certificate issued under ORS 469.300 to 469.601 or for violation of a State Department of Energy order issued pursuant to ORS 469.405 (3). A civil penalty in an amount of not more than $25,000 per day for each day of violation may be assessed.

      (2) Subject to ORS 153.022, violation of an order entered pursuant to ORS 469.550 is punishable upon conviction by a fine of $50,000. Each day of violation constitutes a separate offense.

      (3) A civil penalty in an amount not less than $100 per day nor more than $1,000 per day may be assessed by the director or the Energy Facility Siting Council for a willful failure to comply with a subpoena served by the director pursuant to ORS 469.080 (2).

      (4) A civil penalty in an amount of not more than $25,000 per day for each day in violation of any provision of ORS 469.603 to 469.619 or section 14, chapter 653, Oregon Laws 1991, may be assessed by the circuit court upon complaint of any person injured by the violation.

 

      Note: Section 18, chapter 653, Oregon Laws 1991, provides:

      Sec. 18. Sections 12 to 16 of this Act and the amendments to ORS 469.992 by section 17 of this Act do not become operative until the federal government or a state that has entered into an agreement under 42 U.S.C. 2021 exempts from regulation or changes the regulatory status of any radioactive material that is subject to regulation on January 1, 1989. [1991 c.653 §18]

 

      469.994 [1981 c.894 §8; 1983 c.346 §5; 1989 c.706 §18; 1989 c.880 §13a; 1991 c.734 §38; 1997 c.534 §13; renumbered 469B.991 in 2011]

_______________