Chapter 553 Oregon
Laws 2011
AN ACT
SB 384
Relating to
prompt payment provisions for private construction contracts; creating new
provisions; and amending ORS 701.620, 701.625, 701.630, 701.635 and 701.640.
Be It Enacted by the People of the State of Oregon:
SECTION 1. ORS 701.620 is amended to
read:
701.620. As used in ORS 701.620 to
701.640:
(1) “Construction contract” means a
written or oral construction agreement, including all [plans,] drawings, specifications and addenda relating to:
(a) Excavating, landscaping,
demolishing and detaching existing structures, leveling, filling in and other
preparation of land for the making and placement of a building, structure or
superstructure;
(b) Creation or making of a building,
structure or superstructure; and
(c) Alteration, partial construction
and repairs done in and upon a building, structure or superstructure.
(2) “Contractor” has the meaning given
that term in ORS 87.005.
(3) “Days” means calendar days.
(4) “Material supplier” means any
person providing materials or products under a construction contract by [any contractual means including] oral
authorization, written contract, purchase order, price agreement, [or] rental agreement or other
contractual means.
(5) “Original contractor” has the meaning
given that term in ORS 87.005.
(6) “Owner” has the meaning given that
term in ORS 701.410.
(7) “Subcontractor” has the meaning
given that term in ORS 87.005.
SECTION 2. ORS 701.625 is amended to
read:
701.625. [(1) By mutual agreement with an original contractor, an owner may make
progress payments to the original contractor on a construction contract that is
anticipated to last less than 60 days. An owner shall make progress payments to
the original contractor on all other construction contracts. Progress payments
shall be made on the basis of a certified billing or estimate for the work
performed and the materials or products supplied during the preceding 30-day
billing cycle, or an alternate billing cycle as stated in the construction
contract. If billings or estimates are to be submitted in alternate, rather
than 30-day billing cycles, the construction contract shall specify the
alternate billing cycles in a clear and conspicuous manner as prescribed in
subsection (2) of this section. Except as provided in subsection (3) of this
section, the owner shall make progress payments to the original contractor
within 14 days after the date the billing is submitted pursuant to subsection
(4) of this section.]
(1) If a construction contract is
for construction work that is expected to take 60 or more days to complete, an
owner shall make progress payments to the original contractor. By mutual
agreement with an original contractor, an owner may make progress payments to
the original contractor under a construction contract for which the
construction work is expected to take less than 60 days to complete.
(2) [A construction contract may provide for an alternate billing cycle if
the plans and specifications specifically set forth] The owner shall
make progress payments on the basis of a certified billing or estimate for work
performed, and for materials or products supplied, during the preceding monthly
billing cycle or during an alternative billing cycle identified in the
construction contract. If a construction contract identifies an alternative
billing cycle, the construction contract must expressly state in a clear and
conspicuous manner that there is an [alternate]
alternative billing cycle and the owner [provides for] must provide on each page of [plans] drawings and
specifications in the construction contract a statement substantially
similar to the following [statement]:
______________________________________________________________________________
Notice of [Alternate] Alternative Billing
Cycle
The construction contract will
allow the owner to require the submission of billings or estimates in billing
cycles other than [30-day] monthly
cycles. Billings or estimates for the construction contract shall be
submitted as follows:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
(3)(a) Except as provided in this
subsection, the owner shall:
(A) Make progress payments no later
than 14 days after the date the billing is received; and
(B) Make final payment of all
remaining amounts no later than seven days after the date that the owner
approves the work.
(b) An
owner may make progress payments or final payment later than [14 days after the date the billing or
estimate is submitted] the time allowed under paragraph (a) of this subsection
if:
[(a)]
(A) The owner [is responsible for
providing plans] provides drawings and specifications that expressly
[allow] state in a clear and
conspicuous manner that an extended payment[, defined by a specified] period is allowed and identify the
extended payment period as a specific number of days after the date that
the billing or estimate is [submitted]
received or the date that the owner approves all work; and
[(b)]
(B) The owner provides [for]
on each page of [plans] drawings
and specifications a statement substantially similar to the following [statement]:
______________________________________________________________________________
Notice of
Extended Payment Provision
The construction contract will
allow the owner to make [payment within]:
(1) Progress payments no later than ____
days after the date a billing or estimate is [submitted] received.
(2) Final payment of all remaining
amounts no later than
_____days after the date the owner approves all
work.
______________________________________________________________________________
(4) Payment is not required under
this section unless the owner receives from the original contractor a billing
or estimate for the work performed or the materials or products supplied in
accordance with the terms of the construction contract.
[(4)]
(5) The owner is deemed to have received the billing or estimate when the
billing or estimate is [submitted to]
received by any person designated by the owner for the receipt, review or
approval of the billing or estimate. A billing or estimate is deemed to be
certified 10 days after the owner receives the billing or estimate, unless
before that time the owner or the owner’s agent prepares and issues a written
statement detailing those items in the billing or estimate that are not
approved. An owner may decline to approve a billing or estimate or portion of a
billing or estimate [for] because
of:
(a) Unsatisfactory work progress;
(b) Defective construction work,
materials or products not remedied;
(c) Disputed work, materials or
products, except that the declined amount may not [to] exceed 150 percent of the amount in dispute;
(d) Failure to comply with other
material provisions of the construction contract;
(e) A third party [claims] claim being filed or
reasonable evidence that [such] a third
party claim will be filed;
(f) Failure of the original contractor
or a subcontractor to make timely payments to subcontractors and material
suppliers for labor, equipment, materials and products;
(g) Damage to the owner;
(h) Reasonable evidence that the
construction contract cannot be completed for the unpaid balance of the
construction contract sum; or
(i) Other items as allowed under the construction
contract terms and conditions.
[(5)
An owner may withhold from a progress payment an amount that is sufficient to
pay the direct expenses the owner reasonably expects to incur to correct any
items set forth in writing pursuant to subsection (4) of this section. The
owner may also withhold a reasonable amount as retainage as defined in ORS
701.410.]
(6) An owner may extend the period
within which the billing or estimate may be certified if:
(a) The owner [is responsible for providing plans] provides drawings and
specifications that expressly allow in a clear and conspicuous manner an
extended period within which a billing or estimate may be certified; and
(b) The owner provides for each page
of [plans] drawings and
specifications, including bid [plans and
construction plans,] drawings and specifications and construction
drawings and specifications, a statement substantially similar to the
following statement:
______________________________________________________________________________
Notice of
Extended
Certification Period Provision
The construction contract will
allow the owner to certify billings and estimates [within] no later than ____ days after the billings and
estimates are received from the original contractor.
______________________________________________________________________________
(7) Any requirement under this
section that a statement be provided on a page of drawings or specifications
may be satisfied by placing the required statement on either side of the page.
[(7)]
(8) After a subcontractor or material supplier submits a bid or proposal or
other written pricing information to an original contractor, an owner and the
original contractor may agree in writing to change the specified number
of days after certification during which the owner may make payment to the
original contractor or within which the owner must certify a billing or
estimate. The billings by any [original
contractor,] subcontractor or material supplier that does not provide
written consent to the change [will
continue to be paid as] remain subject to the certification period
indicated in the [plans] drawings
and specifications. A construction contract may not be changed in a manner
that alters the right of any subcontractor or material supplier to receive
prompt and timely progress payments as provided under ORS 701.630.
(9) An owner may withhold from a
progress payment an amount that is sufficient to pay the direct expenses the
owner reasonably expects to incur to correct any items detailed in a written
statement under subsection (5) of this section. The owner may also withhold a
reasonable amount as retainage. As used in this subsection, “retainage” has the
meaning given that term in ORS 701.410.
[(8)]
(10) When an original contractor completes and an owner approves all work
under a construction contract, the owner shall make payment in full of all
remaining amounts due on the construction contract [within seven days] as described in subsection (3) of this
section. When an original contractor completes and an owner approves all
work under a portion of a construction contract for which the construction
contract states a separate price, the owner shall make payment in full of all
remaining amounts due on that portion of the construction contract, subject to
the satisfaction of any [issue described
in] items detailed under subsection [(4)] (5) of this section or ORS 701.630 (4).
[(9)
Payment is not required under this section unless the original contractor
provides the owner with a billing or estimate for the work performed or the
materials or products supplied in accordance with the terms of the construction
contract between the parties.]
[(10)
A construction contract may not alter the right of any original contractor,
subcontractor or material supplier to receive prompt and timely progress
payments as provided under this section.]
(11) If an owner or a person
designated by the owner as responsible for making progress payments on a
construction contract does not make a timely payment under this section, the
owner shall pay the original contractor interest on the unpaid balance at the
rate of one and one-half percent a month or fraction of a month, or at a higher
rate as the parties to the construction contract may agree.
(12) On the written request of a
subcontractor, the owner shall notify the subcontractor [within] no later than five days after the issuance of a
progress payment to the original contractor. On the written request of a
subcontractor, the owner shall notify the subcontractor [within] no later than five days after the owner makes the
final payment to the original contractor on the construction contract.
[(13)
In any action, claim or arbitration brought to collect payments or interest
pursuant to this section, the prevailing party shall be awarded reasonable
costs and attorney fees.]
[(14)]
(13) If the owner and original contractor are a single entity, that entity
shall [pay] make progress and
final payments to subcontractors and material suppliers [within 14 days after the billing or estimate
is received unless the deadlines for certification or payment have been
modified pursuant to] as described in subsection (3) or (6) of this
section.
(14) In any action, claim or
arbitration brought to collect interest pursuant to this section, the
prevailing party shall be awarded costs and reasonable attorney fees.
SECTION 3. ORS 701.630 is amended to
read:
701.630. (1) [Performance by] An original contractor, subcontractor or material
supplier [in accordance with the
provisions of a construction contract entitles the original contractor,
subcontractor or material supplier] that performs in accordance with a
construction contract is entitled to payment from the party with whom the
original contractor, subcontractor or material supplier contracts.
[(2)
If a subcontractor or material supplier has performed in accordance with the
provisions of a construction contract, the original contractor shall pay to the
subcontractor or material supplier, and each subcontractor shall pay to its
subcontractors or material suppliers, the full amount received for such
subcontractor’s work and for materials and products supplied based on the
subcontract or purchase order terms and conditions within seven days of receipt
by the original contractor or subcontractor of a progress payment or final
payment.]
(2)(a) If a subcontractor has
performed in accordance with a construction contract, and the original
contractor receives payment from the owner for work performed by the
subcontractor, the original contractor shall pay the subcontractor for that
work no later than seven days after the original contractor receives the
payment. If a material supplier has performed in accordance with a construction
contract, and the original contractor receives payment from the owner for
materials or products provided by the material supplier, the original
contractor shall pay the material supplier for those materials and products no
later than seven days after the original contractor receives the payment. An
original subcontractor that receives payment under this subsection for work
provided to the original subcontractor by another subcontractor, or for
materials or products provided to the original subcontractor, shall pay the
other subcontractor or material supplier for the work, materials or products no
later than seven days after the original subcontractor receives the payment.
(b)
Payment is not required under this subsection unless a subcontractor or
material supplier provides to the original contractor or subcontractor a
billing or invoice for the work performed or materials or products supplied in
compliance with the terms of the contract between the parties. Each
subcontractor or material supplier must provide an appropriate waiver of any [mechanic’s or materialman’s] lien for
labor, equipment, services, materials or products in accordance with
subcontract or purchase order terms and conditions. The original contractor or
subcontractor may require that such waivers of lien be notarized.
(3) Any failure to reasonably account
for the application or use of payments, as proven in a legal proceeding
authorized under the terms of the construction contract, may constitute grounds
for disciplinary action by the Construction Contractors Board under ORS
701.098.
(4) [Nothing in this section prevents] An original contractor [when submitting a bill] that submits
a billing or estimate to an owner, or [a]
an original subcontractor [when
submitting a bill] that submits a billing or estimate to the
original contractor, [from omitting from
the bill] may omit from the billing or estimate amounts to be
withheld from payment to a subcontractor or material supplier [for] because of:
(a) Unsatisfactory work progress;
(b) Defective construction work,
materials or products not remedied;
(c) Disputed work, materials or
products, except that the withheld amount may not [to] exceed 150 percent of the amount in dispute;
(d) Failure to comply with other
material provisions of the construction contract;
(e) A third party [claims] claim being filed or
reasonable evidence that [such] a third
party claim will be filed;
(f) Failure of the subcontractor to make
timely payments to subcontractors and material suppliers for labor, equipment,
materials and products;
(g) Damage to an original contractor,
subcontractor or material supplier;
(h) Reasonable evidence that the
subcontract cannot be completed for the unpaid balance of the subcontract sum;
or
[(i)
A reasonable amount for retainage, as defined in ORS 701.410, that does not
exceed the actual percentage allowed by the subcontract or purchase order; or]
[(j)]
(i) Other items as allowed under the subcontract or purchase order terms
and conditions.
(5) An original contractor or
original subcontractor may also omit from a billing or estimate a reasonable
amount for retainage, except that the amount omitted may not exceed the actual
percentage allowed by the construction contract, subcontract or purchase order.
As used in this subsection, “retainage” has the meaning given that term in ORS
701.410.
[(5)]
(6) If a progress or final payment to a subcontractor or material supplier
is delayed by more than seven days after receipt of a progress or final payment
by an original contractor or subcontractor, the original contractor or
subcontractor shall pay its subcontractor or material supplier interest
beginning on the eighth day, except during periods of time during which payment
is withheld pursuant to subsection (4) or (5) of this section, at the
rate of one and one-half percent a month or a fraction of a month on the unpaid
balance or at such higher rate as the parties agree.
[(6)]
(7) In any action, claim or arbitration brought to collect [payments or] interest under this
section, the prevailing party shall be awarded [reasonable] costs and reasonable attorney fees.
SECTION 4. ORS 701.635 is amended to
read:
701.635. (1) An original contractor
may suspend performance under a construction contract, or if performance is
suspended for longer than one month may terminate a construction contract,
if [performance is suspended for longer
than 30 days, for failure by] the owner fails to make timely payment
of the amount certified under ORS 701.625. An original contractor shall provide
written notice to an owner at least seven days before the original contractor
suspends performance or terminates the construction contract, unless a
shorter notice period is prescribed in the construction contract. An
original contractor may not be deemed in breach of a construction contract for
suspending performance or terminating a construction contract pursuant to this
subsection. A construction contract may not extend the notice period under this
subsection.
(2) A subcontractor may suspend
performance under a construction contract, or if performance is suspended
for longer than one month may terminate a construction contract, if
[performance is suspended for longer than
30 days, for failure by] the owner fails to make timely payment of
amounts certified under ORS 701.625 or the subcontractor [fails to] does not receive payment for the certified work
under ORS 701.630 (2). A subcontractor shall provide written notice to the
original contractor and owner at least three days before the subcontractor
suspends performance or terminates the construction contract, unless a
shorter notice period is prescribed in the construction contract. A
subcontractor may not be deemed in breach of a construction contract for
suspending performance or terminating a construction contract pursuant
to this subsection. A construction contract may not extend the notice period
under this subsection.
(3) A subcontractor may suspend
performance under a construction contract, or if performance is suspended
for longer than one month may terminate a construction contract, [if performance is suspended for longer than
30 days,] if the owner makes timely payment of amounts certified under ORS
701.625 for the subcontractor’s work but the original contractor fails to pay
the subcontractor for the certified work. A subcontractor shall provide written
notice to the original contractor and owner at least seven days before the
subcontractor suspends performance or terminates the construction
contract, unless a shorter notice period is prescribed in the construction
contract. A subcontractor may not be deemed in breach of a construction
contract for suspending performance or terminating a construction
contract pursuant to this subsection. A construction contract may not extend
the notice period under this subsection.
(4) A subcontractor may suspend
performance under a construction contract, or if performance is suspended
for longer than one month may terminate a construction contract, [if performance is suspended for longer than
30 days,] if the owner declines or fails to approve portions
of the contractor’s billing or estimate under ORS 701.625 for that
subcontractor’s work [but] and
the reasons for [that failure]
nonapproval are not the fault of or directly related to the subcontractor’s
work. A subcontractor shall provide written notice to the original contractor
and the owner at least seven days before the subcontractor suspends performance
or terminates the construction contract, unless a shorter notice period
is prescribed in the construction contract. A subcontractor may not be
deemed in breach of a construction contract for suspending performance or
terminating a construction contract pursuant to this subsection. A
construction contract may not extend the notice period under this subsection.
(5) A contractor or subcontractor may
not submit a notice of suspension under this section until the lawful period
for payment to the contractor or subcontractor has expired.
(6) An original contractor or
subcontractor that suspends performance as provided in this section [is not required to furnish further labor,
materials, products or services until the original contractor or subcontractor
is paid the amount that was certified under ORS 701.625, together with]
may condition the supplying of further labor, equipment, services, materials or
products upon the owner or original contractor paying, in addition to any
amounts certified under ORS 701.625, any documented, substantial and
reasonably incurred costs for mobilization resulting from the shutdown or
start-up of a project.
(7) In any action, claim or
arbitration brought pursuant to this section, the prevailing party shall be
awarded [reasonable] costs and reasonable
attorney fees.
(8) Written notice required under this
section is deemed to have been provided if the notice:
(a) Is delivered in person to the
owner, original contractor, subcontractor or a person designated by the owner,
original contractor or subcontractor to receive notice; or
(b) Is delivered by certified mail,
return receipt requested, or other means that provides written, third party
verification of delivery to the last business address of the owner, original
contractor or subcontractor known to the party giving notice.
SECTION 5. ORS 701.640 is amended to
read:
701.640. (1) A construction contract
may not include any provision, covenant or clause that:
(a) Makes the construction
contract subject to the laws of another state or that requires any litigation,
arbitration or other dispute resolution proceeding arising from the construction
contract to be conducted in another state; or
(b) States that a party to the construction
contract cannot suspend performance under the construction contract or
terminate the construction contract if another party to the construction
contract fails to make prompt payments under the construction contract
pursuant to ORS 701.620 to 701.640.
(2) Any provision, covenant or clause
described in subsection (1) of this section is void and unenforceable.
SECTION 6. The amendments to ORS
701.620, 701.625, 701.630, 701.635 and 701.640 by sections 1 to 5 of this 2011
Act apply to construction contracts that an owner enters into on or after the
effective date of this 2011 Act.
Approved by
the Governor June 28, 2011
Filed in the
office of Secretary of State June 29, 2011
Effective date
January 1, 2012